UNITED STATES
NUCLEAR REGULATORY COMMISSION
REGION I
631 PARK AVENUE
KING OF PR.USSIA, PENN~YLVANIA 19406
Docket No. 50-311
MAY 8
1979
Public Service Electric & Gas Company
ATTN:
Mr. T. J. Martin
Vice President
Engineering and Construction
80 Park Place
Newark, New Jersey
07101
Gentlemen:
Subject:
Inspection 50-311/79-22
~This refers to the inspection conducted by Mr. H. Nicholas of this
office on March 29 - April 9, 1979 at Salem Nuclear Generating Station,
Unit 2, Hancocks Bridge, New Jersey of activities authorized by NRC
License No. CPPR-53 and to the discussions of our findings held by Mr.
Nicholas with Mr. E .. Meyers of your staff at the conclusion of the
inspection.
Areas examined during this inspection are described in the Office of
Inspection and Enforcement Inspection Report which is enclosed with this
letter. Within these areas, the inspection consisted of selective
examinations of procedures and representative records, interviews with
personnel, and observations by the inspector.
Within the scope of this inspection, no items of noncompliance were
observed.
In accordance with Section 2.790 of the NRC
1s "Rules of Practice," Part
2, Title 10, Code of Federal Regulations, a copy of this letter and the
enclosed inspection report will be placed in the NRC 1s Public Document
Room.
If this report contains any information that you (or your contrac-
tor) believe to be proprietary, it is necessary that you make a written
application within 20 days to this office to withhold such information
from public disclosure.
Any such application must be accompanied by an
affidavit executed by the owner of the information, which* identifies the
document or part sought to be withheld, and which contains a statement
of reasons which addresses with specificity the items which will be
considered by the Commission as listed in subparagraph (b) (4) of Section
2.790.
The information sought to be withheld shall be incorporated as
far as possible into a separate part of the affidavit. * If we do not
hear from you in this regard within the specified period, the report
will be placed in the Public Document Room.
GrJ
79071101'f8\\~
(/)
(_j
Public Service Electric & Gas
Company
2
MM 8
1979
No reply to this letter is required; however, if you should have any
questions concerning this inspection, we will be pleased to discuss them
with you.
Sincerely,
Ef71 J.~ Brunner, Chief.
.
- !~~or Operations and Nuclear
Support Branch
Enclosure: Office of Inspection and Enforcement Inspection
Report Number 50-311/79-22
cc w/encl:
E. N. Schwalje, Manager - Quality Assurance,
Engineering and Construction Department