Notice of Violation from Insp on 950107-0221.Violation Noted:Temporary Mod Installed on Main Generator Demand Meter W/O Independent Verification
ML18064A655
Person / Time
Site: Palisades Entergy icon.png
Issue date: 03/06/1995
From:
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
To:
Shared Package
ML18064A654 List:
References
50-255-95-02, 50-255-95-2, NUDOCS 9503220012
Download: ML18064A655 (2)


See also: IR 05000107/2002021

Text

  • '

NOTICE OF VIOLATION

Consumers Power Company

Palisades Nuclear Generating Facility

Docket No. 50-255

license No. DPR-20

During an NRC inspection conducted from January 7 through February 21, 1995, a

violation of NRC requirements was identified.

In accordance with the "General

Statement of Policy and Procedure for NRC Enforcement Actions," 10 CFR Part,

Appendix C, the violation is listed below:

Technical Specification 6.8.1.a requires, in part, that written

procedures be established, implemented, and maintained covering the

applicable procedures recommended in Appendix A of Regulatory Guide

1.33, Revision 2 (February 1978), Quality Assurance Program

Requirements, as endorsed by CPC-2A, Quality Program Destription.

The

Quality Program Description in CPC-2A endorses, among other things,

general procedures for control of modification work, as stated in

Appendix A of Regulatory Guide 1.33, paragraph 9.e.

11

Rev.8~

step 7.2.4, established to implement the procedure listed in Appendix A

of Regulatory Guide 1.33, paragraph 9.e, requires that the installation

of Temporary Modifications shall be independently verified, shall be

documented on the. Temporary Modification form, and shall occur

  • cqncurrent with the Temporary Modificat1on installation.

Contrary to the above, on January 11, 1995, a Temporary Modification was

installed on the main generator demand meters without any independent

verificatjon.

As a result,. an indicated reactor trip occurred with the

plant at 100 percent power.

This is a Severity Level IV violation (Supplement I).

Pursuant to the provisions of 10 CFR 2.201, Consumers Power Company is hereby

required to submit a written statement or explanation to the U.S. Nuclear

Regulatory Commission, ATTN:

Document Control Desk, Washington, D.C. 20555

with a copy to the Regional Administrator, Region Riii, and a copy to the NRC

Resident Inspector at the facility that is the subject of this Notice, within

30 days of the date of the letter transm1tting this Notice of Violation

(Notice). This reply should be clearly marked a~ a "Reply to a* Notice of

Violation" and should include for each violation:

(1) the reason for the

violation, or, if contested, the basis for disputing the. violation, (2) the

corrective steps that have been taken and the results achieved, (3) the

corrective steps that will be taken to avoid further violations, and (4) the

date wh~n full compliance will be achieved. If an adequate reply is not

received within the time specified in this Notice, an order or a Demand for

Information may be issued to show cause why the license should not be

modified, suspended, or revoked, or why such other action as may be proper

should not be taken.

Where good cause is shown, consideration will be given

to extending the response time.

9503220012 950306

PDR

ADOCK 05000255

Q

PDR

.*

..:::-. N~tice of Violation

-2-

Under the authority of Section 182 of the Act, 42 U.S.C. 2232, this response

shall be submitted under oath or affirmation.

Dated at Lisle, Illinois this

6th day of March 1995

\\