ML18058B417

From kanterella
Jump to navigation Jump to search
Monthly Operating Rept for Jan 1993 for Palisades Nuclear Plant
ML18058B417
Person / Time
Site: Palisades Entergy icon.png
Issue date: 01/31/1993
From: Handlovits S, Kluskowski P
CONSUMERS ENERGY CO. (FORMERLY CONSUMERS POWER CO.)
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
References
NUDOCS 9302110185
Download: ML18058B417 (4)


Text

consumers Power POW ERi Nii MICHlliAN'S PROliRESS Palisades Nuclear Plant: 27780 Blue Star Memorial Highway, Covert, Ml 49043 February 3, 1993 US Nuclear Regulatory Commission Document Control Desk Washington, DC 20555 LICENSEE REPORT OF MONTHLY OPERATING DATA DPR-20, DOCKET NO 50-255 Enclo$ed is a copy of the Monthly Operating Data and Summary of Operating Experience for the Palisades Nuclear Plant for the month of January, 1993.

If you have any questions or concerns, please feel free to contact me at (616) 764-8913, extension 0113.

Sincerely,

. - -~.

~ '.

~

.. * ::* /:c;.~ :*.,,1.:~*...

':,* ;~'.-_..,~~

PJ Kl uskowski

  • Reactor Engineer CC:

DPHoffman, P26-117B ABDavis, USNRC.

JLKuemin, Palisades

. :.. ~.. *.,. '

Resident Inspector, Paljsades

DRHahn, Df~ of Rad Health Services, Lansing, MI BWJorgensen, Michigan Dept of Labor, Lansing, MI JPadgett, Michigan Public Service Commission Records Center, INPO, Atlanta, GA RWTaylor, CE, Palisades MPKnopp, Palisades
  • SMMclntyre,. P13-121 Administrator, USNRC Document Control, 950*22*35*10/L

=--. SMH93"*0-4

~-llO_O_O_S_

(

9302110185 930-1-:cc3-1 _

__,..._~,\\

PDR ADDCK 05000255 R

PDR A CMS' ENERGY COMPANY

OPERATING STATUS:

1.

UNIT NAME

2.

REPORTING PERIOD:

3.

LICENSED THERMAL POWER CMWt)

4.

NAMEPLATE RATING (GROSS MWe)

5.

DESIGN ELECTRICAL RATING (NET MWe)

6.

MAXIMUM DEPENDABLE CAPACITY (GROSS MWe)

OPERATING DATA REPORT Palisades 930101-930131 2530.0 811. 7 805.0

    • 770
7.

MAXIMUM DEPENDABLE CAPACITY (NET MWe)

    • 739
8.

IF CHANGES OCCUR IN CAPC !TY RATINGS ( ITEM NUMBERS 3 ANO 7) SINCE LAST REPORT, GIVE REASONS:

9.

POWER LEVEL TO WHICH RESTRICTED, IF ANY (NET MWe):

10. REASONS FOR RESTRICTIONS, IF ANY:
11. HOURS IN REPORTING PERIOD
12. NUMBER OF HOURS REACTOR WAS CRITICAL
13. REACTOR RESERVE SHUTDOWN HOURS
14. HOURS GENERATOR ON-LINE
15. UNIT RESERVE SHUTDOWN HOURS
16. GROSS THERMAL ENERGY GENERATED CMWH)
17. GROSS ELECTRICAL ENERGY GENERATED CMWH)
18. NET ELECTRICAL ENERGY GENERATED CMWH)
19. UNIT SERVICE FACTOR
20. UNIT AVAILABILITY FACTOR
21. UNIT CAPACITY FACTOR (USING MOC NET)
22. UNIT CAPACITY FACTOR (USING DER NET)
23. UNIT FORCED OUTAGE RATE This Month Yr-to-Date 744.0 744.0 744.0 744.0 744.0 744.0 1879536.0 1879536.0 618530.0 618530.0 589156.0 589156.0 100.0%

100.0%

100.0%

100.0%

108.5%

108.5%

98.4%

98.4%

0.0%

0.0%

24. SHUTDOWNS SCHEDULED OVER THE NEXT 6 MONTHS CTYPE, DATE ANO DURATION OF EACH):
25. IF SHUTDOWN AT END OF REPORT PERIOD, ESTIMATED DATE OF STARTUP:
26. UNITS IN TEST STATUS (PRIOR TO COMMERCIAL OPERATION):

Forecast

--*- -*--------~-----* -------

INITIAL CRITICALITY INITIAL ELECTRICITY COMMERCIAL OPERATION

    • Based on condenser backpressure
  • Weighted Average (635 MWe used as MOC Net prior to October 1985)

DOCKET NO DATE 50-255 01-31-93 COMPLETED BY SMHandlovits TELEPHONE (616)764-8913 NOTES:

Cumulative 185151.0 104476.6

. 99950.6 214175508.0 67508713.0 63626236.0 54.0%

54.0%

51.4%*

42.7%,

30.2%

---~Achieved~--

~* ---

AVERAGE DAILY UNIT POWER LEVEL MONTH JANUARY 1993 DAY AVERAGE DAILY POWER LEVEL (MWe Net)

l.

793

2.

793

3.

789

4.

789

5.

792

6.

793

7.

792

8.

794

9.

795

10.

793

11.

794

12.

794

13.

790 1_4 _..

793

15.

788

16.

792 INSTRUCTIONS:

DAY

17.
18.
19.
20.
21.
22.
23.
24.
25.
26.
27.
28.
29.
30.
31.

DOCKET NO 50-255 UNIT Palisades DATE 02/02/93 COMPLETED BY SMHandlovits TELEPHONE (616)764-8913 AVERAGE DAILY POWER LEVEL (MWe Net) 794 794 797 791 790 797 788 792 793 788 792 778 798 791

-~ -..--- -

792 On this format, list the average daily unit power level in MWe-NET for each day in the reporting month.

Compute to the nearest whole megawatt.

SUMMARY

OF OPERATING EXPERIENCE FOR JANUARY 1993 The unit began the month at full power; but on January 28 during a test, power decreased to 96% at 0218 hours0.00252 days <br />0.0606 hours <br />3.604497e-4 weeks <br />8.2949e-5 months <br /> when the Moisture Seperator Reheater valves closed.

Power was increased to 100% the same day by 1102 hours0.0128 days <br />0.306 hours <br />0.00182 weeks <br />4.19311e-4 months <br />.

The plant operated at 100% power for the remainder of the month.