Ack Receipt of Transmitting Rev 8 of Section 4 to Site Emergency Plan.Review Included 880304 Telcon in Which Agreement Made That Emergency Action Level Changes Would Be Submitted within 90 Days of Ltr Date
ML18054A283
Person / Time
Site: Palisades 
Issue date: 03/11/1988
From: Shafer W
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
To: Buckman F
CONSUMERS ENERGY CO. (FORMERLY CONSUMERS POWER CO.)
References
NUDOCS 8803210223
Download: ML18054A283 (2)


Text

...

Docket No. 50-255 Consumers Power Company ATTN:

Dr. F. W. Buckman Senior Vice President Energy Supply 212 West Michigan Avenue Jacks6n, MI 49201 Gentlemen:

MAR 1 t 1988 This is to acknowledge receipt of your letter of Dec~mber 29, 1987, which transmitted Revision 8 to Section 4, Emergency Conditions, of the Palisades Plant Site Emergency Plan.

We have completed our review of Revision 8 to Section 4 of the Site Emergency Plan (SEP).

This review included a table of revised Emergency Action Levels (EALs).

Our review of these EALs included a.teleconference on March 4, 1,988, between Messrs. James Patterson and James Foster of my staff and Messrs. James Brunet, Ronald Frigo and Daniel Malone of your staff.

We have agreed that certain EAL changes will be submitted to our offica for final r~view within 90 days of the date of this letter.

At that time we will make our fi*nal decision on the acceptabilit~ of this emergency plan change; Please be reminded that 10 CFR 50.54(q) requires NRC approval.of any changes to your plan which may decrease the effectiveness of the plan.

However, if your safety review indicates no de.crease in emergency preparedness effectiveness, then changes can be made without prior NRC approval.

In all cases, you must fu~nish copies of each proposed change t6 ~he NRC in accordance wi~h 10 CFR 50.54(q).

Also, any changes to the Emergency Plan Implementing Procedures should be made in accordance with the* requirements of 10 CFR. Part 50, Appendix E, Sectibn V (Implementing Procedures).

In* accordance with 10 CFR 2.790 bf the.Commission's regulations, a copy of this letter will be placed i.n the NRC Public Document Room.

If you have any que~tions concerning this letter, ~lease contact Mr. James P. Patterson of my staff at (312) 790-5536.

See Attached Distributio~

RI!i Pattet'5'on/ j 1 r _

'46 8803210223 880311 PDR ACOCK 05000255 PJ -*rJ

.1fIJ11 snJJ'i

... ~

Sincerely, w0r1g1nal signed by W.D. Sha:f!'o,l-"

W. D. Shafer, Cbief Emergency Preparedness and Radiological Protection Branch

\\~

Wf1

. r Consumers Power Company Distribution cc:

Mr. Kenneth W. Berry, Director Nuclear Licensing David P. Hoffman, General Manager DCD/DCB (RIDS)

Licensing Fee Management Branch Resident Inspector, RIII Ronald Callen, Michigan Public Service Commission Michigan Department of Public Health D. Matthews, EPB, NRR W. Weaver, FEMA, RV

... -. :*... :"'.. ~***.... ~.. ~"... -

~.-

. 2. MAR 11 1988