ML18052B505

From kanterella
Jump to navigation Jump to search
Safety Insp Rept 50-255/88-04 on 880105-07,12-14, 21 & 22. No Violations or Deviations Noted.Major Areas Insp:Licensee Actions in Response to IE Bulletins & Review of Inservice Insp Program & Procedures
ML18052B505
Person / Time
Site: Palisades Entergy icon.png
Issue date: 02/04/1988
From: Danielson D, Schapker J
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
To:
Shared Package
ML18052B503 List:
References
50-255-88-04, 50-255-88-4, IEB-87-001, IEB-87-1, NUDOCS 8802110336
Download: ML18052B505 (7)


See also: IR 05000255/1988004

Text

U.S. NUCLEAR REGULATORY COMMISSION

REGION III

Report No. 50-255/88004(DRS)

Docket No. 50-255

License:

Consumers Power Company

212 West Michigan Avenue

Jackson, MI

49201

Facility Name:

Palisades Nuclear Generating Plant

Inspection At:

Palisades site, Covert, MI

Inspection

Inspector:

Con~1/j;-*

January 5-7,

  • +

F. Schap er

12-14, 21, 22, 1988

h<Uf-~_,y~A.)jv.-"\\..

Approved By:

D. H. Danielson, Chief

Materials and Processes

Section

Inspection Summary

License No. DPR-20

Dat'e

7

Date

Inspection on January 5-7, 12-14, 21, 22, 1988 (Report No. 50-255/88004(DRS))

Areas Inspected:

Unannounced safety inspection of licensee actions in response

to IE Bulletins (92703); review of inservice inspection (!SI) program (73051)

and procedures (73052); observations of !SI work and work activities (73753);

!SI data review and evaluation (73755); and of the Steam Generator Sludge

lancing (73051, 73052, 73753).

Results:

No violations or deviations were identified.

The activities

inspected appeared to meet the safety objectives of the applicable regulatory

requirements.

8802110336 ~~ggg~55

PDR

ADOCK

PDR

Q

Details

1.

Persons Contacted

Consumers Power Company (CPCo)

  • D. P. Hoffman, Plant General Manager

J. G. Lewis, Technical Director

  • C. S. Kozup, Technical Engineer
  • R. P. Margol, QA Administrator
  • B. V. VonWagner, Inservice Inspection (ISI) Supervisor
  • K. V. Cedarquist, ISI Engineer
  • K. E. Osborne, Projects Superintendent
  • R. D. Orosz, Engineering and Maintenance Manager

S. R. Willman, NOT Project Supervisor

R. M. Rice, Operations Manager

T. D. Fouty, ISI Engineer

G. Y. Yeisley, QA Engineer

Allen Nuclear Associates, Inc. (ANA)

B. L. Curtis, President, Level III ET

U.S. Nuclear Regulatory Commission (NRC) *

E. R. Swanson, Senior Resident Inspector

C. D. Anderson, Resident Inspector

N. R. Williamsen, Reactor Inspector

Other members of the plant staff and contractors were also contacted.

  • Denotes those present at the exit interview.

2.

Licensee Action Taken on Bulletins

(Open) Bulletin No. 87-01 Thinning of Pipe Walls in Nuclear Power Plants.

The purpose of this bulletin is to request that licensees submit

information concerning their programs for monitoring the thickness of

pipe walls in high-energy single phase and two-phase carbon steel piping

systems.

Background

On December 9, 1986, Unit 2 at the Surry Power Station experienced a

catastrophic failure of a main feedwater pipe, which resulted in fatal

injuries to four workers.

Investigations of the accident and examination

of data by the licensee, NRC, and others led to the conclusion that

failure of the piping was caused by erosion/corrosion of the carbon steel

pipe wall.

2

Main feedwater systems, as well as other power conversion systems, are

important to safe operation.

Failures of active components in these

systems, for example, valves or pumps, or of passive components such

as piping, can result in undesirable challenges to plant safety systems

required for safe shutdown and accident mitigation.

Failure of

high-energy piping, such as feedwater system piping, can result in

complex challenges to operating staff and the plant because of potential

systems interactions of high-energy steam and water with other systems,

such as electrical distribution, fire protection, and security systems.

All licensees have either explicitly or implicitly committed to maintain

the functional capability of high-energy piping systems that are a part

of the licensing basis for the facility.

An important part of this

commitment is that piping will be maintained within allowable thickness

values.

Licensee action:

The licensee

1 s program for inspection of pipe wall

thinning was initiated in the 1983-1984 refueling outage due to a

Westinghouse Electric Corporation memo recommending an inspection of 'the

Palisades turbine crossunder piping for wear resulting from steam

erosion.

The program was expanded in 1986-87 to include the following

systems:

  • Condensate
  • Auxilliary Steam
  • Heater Drains and Vents

The program will follow the basic outline set forth by EPRI NP-3944.

The

inspection points are selected using maintenance history, input from

other utilities and Keller

1s equation:

s=f(T)*f(x)*c*Kc-Ks.

where:

s

is the maximum local depth of material loss in mm/10 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br />.

f(T) is a dimensionless variable denoting the influence of

temperature on E/C damage.

f(x) is a dimensionless variable denoting the influence of

K c

c

K s

steam wetness on E/C loss. For subcooled water it has been

suggested that this has a value of un~ty, but for two-phase

mixtures it has the form f(x) = (1-x) x, where x is the

steam fraction and O<K <1.0.

A value of K = 0.5 is

considered the most ap~ropriate one.

x

is a variable accounting for the effect of local geometry

on the fluid flow.

is the fluid velocity in m/s.

is a threshold value constant which the product of f(T),

f(x), c, and K must exceed before E/C is observed.

A

value of 1.0 mM/10 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br /> has been given by Keller.

3

This initial inspection utilizing the above guidelines was completed

January 16, 1987.

The fa 11 owing areas were inspected:

  • Turbine cross over piping.
  • Heater drain pumps inlet and discharge.
  • Air ejector piping.

The result of the inspections revealed no degradation below minimum

wall.

Minimum wall was calculated utilizing ANSI 831.1, 1973 Edition,

Section 104.

The NRC inspector reviewed the secondary side ISI program specification

for the current outage, applicable procedures, and ultrasonic examination

data.

Inspection data to date has not identified erosion/corrosion which

violates minimum wall thickness.

However, substantial erosion/corrosion

was exhibited in localized areas.

The licensee elected to repair these

areas.

A trending program for erosion/corrosion wear is i~ the process

~

of development and will be incorporated in the secondary side inspection

program.

This program area requires further review as the inspection and trending

program are newly instituted and insufficient data has been gathered to

conclude the pipe wall thinning inspection program is adequate.

3.

Inservice Inspection (ISI) Program Review (73051)

_)

The NRC inspector reviewed the second ten year ISI Plan for the Palisades

plant.

The ISI plan conforms to the American Society of Mechanical

Engineers (ASME), Boiler and Pressure Vessel Code,Section XI, 1977

Edition through the Summer 1978 Addenda.

Relief requests in accordance

with lOCFR 50.55a (g)(S)(iv) were reviewed.

The licensee only performed

ISI for Class 1 components on steam generator tubes for this outage.

The remainder of the ISI will be performed in the Fall

188 scheduled

maint~nance outage.

The Program reviewed is effective with respect to meeting the safety

objectives of the ASME Section XI requirements.

4.

Steam Generator Eddy Current Examination

As a result of a steam generator (SG) tube leak indication, the Palisades

Plant was shutdown on December 4, 1987.

Eddy current examination (ET)

which was planned for the 1988 fall outage was performed during this*

forced outage due to the SG tube leak indication.

4

The NRC inspector verified that the ET was performed in Accordance with

the augmented ISI program for steam generators as specified in the

Palisades Technical Specification (TS).

A relief request was made by the

licensee concerning the ET of previously installed sleeves.

(Technical

Specification 4.14.5), due to high radiation exposure times to perform

the examination, and that the previous ET of sleeves had shown no

degradation.

The relief request was not formally approved at this date;

however, verbal approval had been granted by NRR.

The NRC inspector

informed the licensee that the exclusion of the ET of installed sleeves

would be identified as an open item pending official approval of the

relief request by the NRC (255/88004-0l(DRS)).

The NRC inspector reviewed ET tapes of examinations performed during the

1983 and the current outage, including the leaking SG tube.

The ET of the

leaking tube revealed a circumferential 90° thru wall indication, whereas

the previous examination of this tube (1983 outage) did not reveal this

indication.

The leaking SG tube was located in Row 122, Line 35, at the

lower edge (both inside and outside) of the No. 13 tube support plate

of SG

11 8

11 *

As required by the Palisades Technical Specification, ET inspection of

all unplugged tubes with ET indications of greater than or equal to 30%

in either of the previous two inspections was performed.

In addition, a~

random sample of 2% of the tubes in the hot leg and 1% of the tubes in

the cold leg of each SG was performed.

One crack-like indication was

observed in the

118

11 cold leg random sample.

Consequently, a 6%

supplementary sample was performed as required.

The licensee also

elected to inspect an additional 12% sample in the

11 8

11 SG, together with

40 tubes in the vicinity of the leaker.

The licensee utilized two ET

procedures for these examinations - NDT-ET-07, Revision 4,

11Circumferentially

Wound Bobbin Type probe (540SFW) Differential Coil, Multifrequency,

Multiparameter

11 , and NDT-ET-08, Revision 4,

11 Pancake Probe, (4C4F)

Differential, Multi coil, Multifrequency, Multiparameter.

11

The 540SFW

11 Bobbin

11 examination is required by TS and is sensitive to

tube degradation associated with wastage and pitting.

The 4C4F

11 Pancake

11

examination which is not required by TS is utilized to detect

intergranular corrosion and circumferential cracking.

The licensee utilized a motorized rotating pancake coil (MRPC) to examine

locations where 4C4F signals were indeterminate as to flaw condition.

The results of these examinations confirmed that the defects detected in

this outage are of the same size or smaller than those observed in 1983.

The MRPC is not a

11 pull through

11 technique, but a special tool to examine

selected areas of interest.

The equipment used during this inspection

was identical to that used during the 1985 inspection, except for the

MRPC probe and its signal analysis by a Zetec MIZ-18 analyzer.

As in the

previous two inspections, the 540 SFW probe was employed_~o detect and

size 11wastage 11 type defects.

The 4C4F probe was used to detect and size

circumferentially oriented defects, including volumetric IGC and cracking.

The Zetec MIZ-12 signal analyzer was used with both of these probes.

The licensee is developing programs and qualifying procedures for the use

of the MIZ-18 analyzer for future examinations.

This system enhances the

interpretation ability of the indications detected.

5

l __

The results of the ET for this outage required 14 SG tubes to be plugged

in

118

11 SG and 4 SG tubes requiring plugging in SG

11A

11 *

The licensee also

performed ~ profilometry examination to detect denting growth.

This

examination is also voluntary and is utilized to determine SG degradation

due to denting of the SG tubes.

During this examination it was discovered

that SG

11 8

11 tube in Quadrant 3, Line 2, Row 121 was misplugged in 1985.

Further investigation disclosed that the misplugging was due to the

installation of the template,. utilized for locating the correct tube

for plugging, was installed in reverse.

The licensee issued a deviation

report and took appropriate corrective action to correct the misplugging

and prevent recurrence.

The NRC inspectors review and observations

concluded that the licensee appeared to have satisfactorily completed all

required examinations with the exception of the installed sleeves for

which relief was requested.

In addition, the licensee performed

additional examinations to assure the cause of the tube leak was not due

to a prevailing degradation of the SG tubes.

Of the 18 tubes requiring

plugging, 7 crack-like indications were observable in the 1983/1985

tapes.

These indications were not reported as defects at that time due

to small amplitude signal responses, poor signal to noise ratio inherent

to the 4C4F technique, and interpreter oversight due to these conditions.

With the addition of the MRPC combined with the MIZ 18 analyzer the

ability to interpret and size defects will be greatly enhanced.

The ET program inspected appeared to be adequate to assure the steam

generators do not exhibit degradation which would be safety significant.

5.

Augmented Inservice Inspection Program For High Energy Lines

Outside of Containment

This is a Technical Specification requirement which applies to welds in

piping systems or portions of systems located outside of containment

where protection from the consequences of postulated ruptures, is not

provided by a system of pipe whip restraints, jet impingement barriers,

protective enclosures, and/or other measures designed specifically to

cope with such ruptures.

For the Palisades Plant, the applicable welds in the main steam and

main feedwater lines are located inside the Main Steam and Feedwater

Penetration Rooms.

The Tech Spec requirement for examination of the specified welds requires

volumetric examination of all welds in the first inspection interval at

each three and a third year increment of the ten year plan.

The

successive inspection intervals requires volumetric examination of one

third of the specified welds at the expiration of each one third of the

ten year inspection interval.

The welds selected during each inspection

period is distributed among the total number to be examined to provide a

representative sampling of the conditions of all welds.

The current

inspection plan is in the second ten year interval.

6

. '

i

The NRC inspector reviewed the secondary side ISI program for the high

energy lines, the ultrasonic and liquid penetrant examinations, equipment

personnel certifications, applicable nondestructive examination procedures,

and reviewed the radiographs performed for this inspection.

No violations or deviations were identified.

6.

Steam Generator Sludge Lancing

The licensee performed their initial sludge lancing of the steam

generators during this outage.

Sludge lancing is the removal of

undesirable deposits on the secondary side which can contribute to

intergranular corrosion of the SG tubes.

Eddy current examinations of

the sludge pile revealed a deposit of 15 inches at the tube sheet.

Combustion Engineering (CE) Services Inc. performed the sludge lancing.

The sludge is removed by use of high pressure, high flow, closed loop

water lancing and filtering system.

The high pressure lance is directed into the sludge pile from various

angles, once dislodged and flushed to the outside of the tube bundle, the

slurry is picked up by the filtering system suction lines and directed to

the diatomaceous earth and particulate filters where the sludge is

removed from the slurry and returned to the high pressure pump.

A total ~

of 4400 pounds of sludge was removed from the steam generators.

The

remaining sludge pile was reduced to approximately 2 to 3 inches in the

cold leg and 5 to 7 inches in the hot leg of the S.G ..

The NRC inspector reviewed the program, procedures, personnel

certifications and observed the sludge lancing process.

No violations or deviations were identified.

7.

Open Items

8.

Open items are matters which have been discussed with the licensee, which

will be reviewed further by the inspector, and which will involve some

action on the part of the NRC or licensee or both.

An open item disclosed

during the inspection is discussed in Paragraph 4.

Exit Meeting

The ~nspector met with licensee representatives (denoted in Paragraph 1)

at the conclusion of the inspection on January 22, 1988.

The inspector

summarized the scope and findings of the inspection activities.

The

licensee acknowledged the inspection findings.

The inspector also

discussed the likely informational content of the inspection report with

regard to documents or processes reviewed by the inspectors during the

inspection.

The licensee did not identify any such documents/processes

as proprietary.

7