Forwards Insp Rept 50-255/87-21 on 870824-28.No Violations Noted.Comments Re Review of Fitness for Duty Program Requested within 60 Days
ML18052B369
Person / Time
Site: Palisades Entergy icon.png
Issue date: 11/08/1987
From: Partlow J
Office of Nuclear Reactor Regulation
To: Buckman F
CONSUMERS ENERGY CO. (FORMERLY CONSUMERS POWER CO.)
Shared Package
ML18052B370 List:
References
NUDOCS 8711160061
Download: ML18052B369 (4)


See also: IR 05000255/1987021

Text

UNITED STATES

NUCLEAR REGULATORY COMMISSION

WASHINGTON, D. C. 20555

NOV

8 1987

Docket No. 50-255

-

...

Consumers Power*company

ATTN:

Dr. F. W. Buckman

Vice President, Nuclear Operations

1945 West Parnall Road

Jackson, Michigan 49201

Gentlemen:

SUBJECT:

Inspection Report No. 50-255/87-21

This letter forwards the report of an inspection conducted by an NRC team

on August 24-28, 1987 to review the Consumers Power Company's fitness for duty

program.

This inspection was conducted jointly by members of NRC's Region III

Office and the Office of Nuclear Reactor Regulation.

At the conclusion of the

inspection, the observations were discussed at an exit meeting with your staff

members identified in the enclosed inspection report.

The NRC's Policy Statement on Fitness for Duty of Nuclear Power Plant Personnel

(51 FR 27921) and the EEI Guide to Effective Drug and Alcohol/Fitness for

Duty Policy Development describe a general approach to designing a fit~ess

for duty program.

The inspection report describes areas where your fitness

for duty program does not appear to meet certain standards adopted by the

nuclear power industry in these documents.

In order to evaluate the overall

effectiveness of your program and to collect information to assist the Commission

in deciding future actions with respect to fitness for duty, the inspectors

reviewed certain supplemental elements of the program not described in the

EEI Guide, such as topics for written.procedures, cutoff limits for chemical

testing, and program performance data.

Our review of these supplem~ntal

elements is not intended to imply that they are or may become requirements.

Within 60 days of receipt of this letter, it is requested that you provide

this office with any comments concerning the results of our review, including

a description of your planned actions to further incorporate appropriate

provisions of the EEI Guide on fitness for duty.

Your special attention

is directed to the first four observations addressed in the Inspection

Summary.

Should you have any questions concerning this inspection report,

please contact me or Loren Bush at (301) 492-8080.

.. ~

-*


~--7-f10-er-~--- -~\\

11160061 85000255

R.

ADOCK 0.

PDR

.J

Sincerel~ Q~

James ~ Partlow, Director

Division of Reactor Inspection and Safeguards

Office of Nuclear Reactor Regulation

Enclosure:

Inspection Report No.

50-255/87-21

~1111 6006 I

Consumers Power Company

cc:

M. I. Miller, Esquire

Isham, Lincoln &_Beale

51st Floor

Three First National Plaza

Chicago, Illinois 60602

Mr. Thomas A. McNish, Secretary

Consumers Power Company

212 West Michigan Avenue

Jackson, Michigan 49201

Judd L. Bacon, Esquire

Consumers Power Company

212 West Michigan Avenue

Jackson, Michigan 49201

Regional Administrator, Region III

U.S. Nuclear Regulatory Commission

799 Roosevelt Road

Glen Ellyn, Illinois 60137

Jerry Sarno

Township Supervisor

Covert Township

36197 M-140 Highway

Covert, Michigan 49043

Office of the Governor

Room 1 - Capitol Building

Lansing, Michigan 48913

Mr. David P. Hoffman

Plant General Manager

Palisades Plant

27780 Blue Star Memorial Hwy.

Covert, Michigan 49043

Resident Inspector

c/o U.S. Nuclear Regulatory Commission

Palisades Plant

27782 Blue Star Memorial Hwy.

Covert, Michigan 49043

.r

- 3 -

Palisades Plant

-

Nuclear Facilities and

Environmental Monitoring

Section Office

Division of Radiological

Health

P.O. Box 30035

Lansing, Michigan 48909

Mr. Kenneth W. Berry, Director

Nuclear Licensing

Consumers Power Company

1945 West Parnall Road

Jackson, Michigan 49201

  • DISTRIBUTION:

DCS Docket Files 50-255

NRC PDR

Local PDR

RSGB Reading

ORIS Reading

JMTaylor

RWStarostecki

JGPartlow

BGrimes

RAErickson

LLBush

EWMcPeek

RPRosano, OE

RFBurnett, NMSS

WTRussell; Region I

RRKeimig, Region I

JHWilliams, Regfon I

JNGrace, Region II

DRMcGuire, Region II

WJTobin, Region II

ABDavis, Region III

JRCreed, Region III

RDMartin, Region IV

LYandell, Region IV

JBMartin, Region V

MDSchuster, Region V

JLCrews, Region V

JAHind, Region III

BSMallett, Region III

BSDrouin, Region III

GLPirtle, Region III

NRR Project Manager, T. Wambach

- 4 -

NRR Project Division Director, 0. Crutchfield

NRR Project Division Assistant Director, G. Holahan

NOV

8 1987

~::::~ ::::s

~~----:~~;~~~~ -:------------:------------:------------:--------

~~~~-jii"i/.~;-------)i1'X/~;------=;,;-~1~;-----: ------------: ------------: ------------: --------

r>,J

,i_~

,

.

"

DISTRIBUTION:

cnm:tLO&e~t~F-i-le.s-50 ... 2_.sst

NRC PDR

Local PDR

RSGB Reading

ORIS Reading

JMTaylor

RWStarostecki

JGPartlow

BGrimes

RAErickson

LLBush

EWMcPeek

RPRosano, OE

RFBurnett, NMSS

WTRussell, Region I

RRKeimig, Region I

JHWilliams, Region I

JNGrace, Region II

DRMcGuire, Region II

WJTobin, Region II

ABDavis, Region III

JRCreed, Region III

RDMartin, Region IV

LYandell, Region IV

JBMartin, Region V

MDSchuster, Region V

JLCrews, Region V

JAHind, Region III

BSMallett, Region III

BSDrouin, Region III

GLPirtle, Region III

NRR Project Manager, T. Wambach

- 4 -

NRR Project Division Director, D. Crutchfield

NRR Project Division Assistant Director, G. Holahan

NOV

8 1987

~~~~~~----~~~~

~~----:~~~=:~-

-*------------*------------*------------*--------

111111111': LLBush:mkm

REr
JGPartl

.

.

.

.

~~~~-jii"ii_~;------- ~bi~;~;------=;,;-[;~;-----:------------:------------:------------:--------

~