Application for Amend to License DPR-20,changing Tech Specs Re Surveillance of Containment Prestressing Sys
ML18052B002
Person / Time
Site: Palisades Entergy icon.png
Issue date: 05/04/1987
From: Buckman F
CONSUMERS ENERGY CO. (FORMERLY CONSUMERS POWER CO.)
To:
Shared Package
ML18052A999 List:
References
RTR-NUREG-0820, RTR-NUREG-820, TASK-03-07.A, TASK-3-7.A, TASK-RR NUDOCS 8705120075
Download: ML18052B002 (6)


Text

"*

I

\.

CONSUMERS POWER COMPANY Docket 50-255 Request for Change to the Technical Specifications License DPR-20 For the reasons hereinafter set forth, it is requested that the Technical

  • Specifications contained in the Provisional Operating License DPR-20, Docket 50-255, issued to Consumers Power Company on October 16, 1972, for the Palisades Plant be changed as described in Section I below:

I. Changes A. Change 4.5.4a. to read as follows:

"Tendon inspection shall be accomplished at five-year intervals for the life of the plant. The scheduled inspection dates for all inspections may be varied by not more than plus or minus one year from the* base schedule."

B. Delete sections 4.5.4b., c. and d., and renumber 4.5.4e., f., g.,

h. , and i
  • as 4
  • 5 . 4b * , c . , d . *~ e . and f * "

C. Change re-lettered section 4.5.4b. (old section 4.5.4e.) as follows:

"The surveillance te.ndons shall be randomly selected from the following groups:

1. One dome tendon from each of the three dome tendon groups.
2. Three vertical tendons located approximately 120° apart.
3. One hoop tendon from each 120° sector of the containment wall.

For each inspection, the tendons shall be **. "

D. Change re-lettered section 4.5.4c.l. (old section 4.5.4f.l) to read as follows:

"l. Lift-off readings shall be taken for each of the surveillance tendons. The tests shall include the follo~ing actions:

(a) One tendon, randomly selected from .each group of tendons during each inspection, shall be subjected to essentially complete detensioning to identify broken or damaged wires. *

(b) The- simultaneous measurement of elongation and jacking force during retensioning shall be made at a minimum of three approximately equally spaced levels of force between the seating force and zero."

OC0886-0i36-NL04 9705120075 870504 PDR. f'DOCK 05000251

' PDR*

P ;o

> t.

TSCR - Containment Testing 2 Palisades Plant*

E. Delete re-lettered section 4.5.4c.6. (old section 4.5.4f.6)

F. Change re-lettered section 4.5.4d. (old section 4.5.4g.) as follows:

"Following the field testing of Paragraph 4.5.4c., the following laboratory testing shall be done.

1. Three tensile test specimens shall be cut from each of the three inspection wires removed (one from each end and one from the middle). One additional specimen shall be cut from the wire determined by field visual inspection to have the greatest amount of corrosion. Each of the wire samples shall be tested for ultimate s_trength, yield strength, and elongation.
2. The sheathing filler samples shall be taken from each end of each tendon examined. Vertical tendon samples shall be taken from the lower end. Samples shall be thoroughly mixed and analyzed for reserve alkalinity, water content, and concentra-tion of water soluble chlorides, nitrates, and sulfides.

Analyses shall be performed in accordance with the procedures and within the acceptance limits specified in ASME Code Section XI, Table IWL-2525-1.

Procedures shall be established to minimize voids and to assure that the volume of sheathing filler removed has been replaced upon completion of the inspection and amounts documented."

G. Change re-lettered section 4.5.4e.l. (old section 4.5.4h.l.) to.

read as follows:

"1. The average of all measured tendon forces for each type* of tendon shall be equal to or greater than the minimum required prestress level of 584 kips per tendon for dome tendons and 615 kips per tendon for hoop and vertical tendons. The

  • measured force in each individual tendon shall not be less than 95% of the predicted force, or (a) the measured force in not more than one tendon is between 90% and 95% of the predicted force, and (b) The measured forces in two tendons located adjacent to the.tendon in (a) above are not less than 95% of the predicted forces, and (c) the measured forces in all the remaining sample tendons are not less than 95% of the predicted force.

-OC0886-0136-NL04

~.!

TSCR - Containment Testing 3 Palisades Plant If measured force in any tendon is less tha~ 90% of its predicted force, the tendon shall be completely detensioned and a determination shall be made as to the cause of such an occurrence and corrective action shall be taken. In addition, all such tendons shall have their forces measured as additional tendons in the next scheduled inspection period.

The Commission shall be'notified in accordance with Paragraph 4.5.4f."

H. Change in re-lettered section 4.5.4e.3. (old section 4.5.4h.3.)

"Paragraph 4.5.4i." to."Paragraph 4.5.4f."

L Change re-lettered section 4. 5. 4f. (old section 4. 5. 4i.) to read as follows:

"i. If any element of the prestressing system fails to meet the acceptance criteria of Paragraph 4.5.4e. the following provision of 6.9.3.3 shall apply."

  • . J. Change section 4.5.5 in its entirety, to read:

"4.5.5 End Anchorage Concrete Surveillance

a. A VT-1 visual examination shall be performed on the end anchorage concrete surface at the surveillance tendon anchor points for signs of cracking, popbuts, spalling, or corrosion. Concrete cracks having widths greater than *o.010 inches shall be evaluated and documented.
b. The inspection interval shall be the same as tendon surveillance period.
c. Acceptance criteria
1. Crack widths shall be measured by using optical comparators or wire feele.r gauge;, Movements shall be measured by using demountable mechanical extensometers *

. 2. Concrete anchorage areas are acceptable if no concrete cracks are wider than 0.010 inches and no signs of new or progressive deterioration since previous inspection are found.

3. Concrete surface conditions exceeding those stated in (2) above shall be evaluated for the effect on tendon and containment structural*

integrity. The results of evaluation shall be

  • included in the final surveillance report."

OC0886-0136-NL04

TSCR - Containment Testing 4 Palisades Plant K. Delete sections 4.5.6 "Liner Plate Surveillance" and 4.5.7 "Penetration Surveillance."

L. Revise 4.5 Basis as shown in attached page changes.

II. Discussion A~ Proposed in section 4.5.4 is the inspection schedule stipulated in the pending ASME B&PV Code,Section XI, Subsection IWL-2400, and stipulated as different allowable interval extension than that in Section 4.0.2.

Deleted are the requirements for surveillance tests that have been previously accomplished. The results of these prior tests are described in the updated FSAR, section 5.8.8.3.

B. Deleted in old sections 4.5.4b., e., and d. are out of date surveillance requirements that have been previously accomplished and the results of which are described in* the Updated FSAR.

C. Re-lettered section 4.5.4b. has had editorial changes that are consistent with change *B. above .

.D. Proposed in re-lettered section 4.5.4c.1 are the new provisions stipulated in the Regulatory Position No. 4 of the proposed revision 3 to Regulatory Guide 1.35 and ASME Code,Section XI, Subsection IWL-2523.1. The new provisions require complete detensioning of only one tendon per each group of the surveillance tendons and additional information which is not covered in the existing Technical Specifications.

E. Re-lettered item 4.5.4c.6 has been superseded by the retension requirement in 4.5.4c.l(b).

F. The changes to re-lettered 4.5.4d.1. and 2. are made to include the additional requirements stipulated in draft ASME B&PV Code,Section XI, .Subsection IWL-2523, for tensile test and IWL-2526 for sheathing filler examination, which were not clearly described in the existing Technical Specifica~ions.

G. The changes to re-lettered 4.5.4e.1 are made to incorporate the requirement stipulated in the draft ASME B&PV Code,Section XI, Subsection IWL-3221.1 for the acceptance of tendon force. These added requirements clarify the tolerances permissible for lift-off deviation.

H. The change in re-lettered section 4.5.4e.3 are editorial.

I. The change to section 4.5.4f is editorial to align it with the reporting requirements in 6.9.3.3 and delete obsolete wording.

OC0886-0136-NL04

TSCR - Containment Testing 5 Palisades Plant J. The changes to section 4.5.5 are made to incorporate the

. requirements stipulated in the draft ASME B&PV Code,Section XI, Subsection IWL-2524 and IWL-3221.3 which are more consistent with the overall tendon surveillance activities, rather than as a

.separate activity.

The change to the inspection interval is intended to eliminate the redundant inspection schedule for end anchorage concrete as separated from the tendon surveillance schedule to avoid confusion.

K.

  • Sections 4.5.6 "Liner Plate Surveillance" and 4.5.7 "Penetration Surveillance) contain obsolete requirements that have been previously accomplished and the results of which are described in the Updated FSAR, section 5.8.8.5.

The Standard Technical Specifications (STS) contain requirements for an examination of containment surfaces, which.are similar to these out-of-date requirements. The STS surveillance is accomplished prior to a Type A, containment integrated leak rate test. However, the STS requfrement is also stipulated in 10CFR50 Appendix J, section V.A and is, therefore, unnecessary in the Technical Specifications.

L. *Revisions to the Basis section 4.5 are to update the information.

Deletion of the next to last paragraph is consistent with information in FSAR section 5.8.8.5.

Analysis of No Significant Hazards Consideration The proposed revision to the surveillance method incorporates current methods of conducting inservice inspections of prestressed concrete containments. The proposed changes incorporate the revisions agreed upon by the NRC. and Consumers_ Power Company in the resolution of SEP Topic III-7.A as described in the Integrated Plant Safety Assessment,

  • NUREG-0820, October 1982. The revisions to the method of conducting lift-off readings and conducting of the laboratory testing and accept-ance criteria are acceptable methods per the pending ASME B&PV Code,Section XI, Subsection IWL. There are no changes to the physical part of the surveillance field activitie~. The deletion of several sections in the specifications is considered editorial to remove obsolete requirements that have been previously accomplished and described in the Updated FSAR. As a result, there is no increase in the probability of occurrence or consequences of an accident or malfunction of equipment and the possibility of a new or different accident has not been created.

The CQange does not result in a reduction in the margin of safety as defined in the basis of the Specifications as in the FSAR. The revisions in measurement methods, definition of laboratory testing and acceptance criteria do not affect the basis of the Specifications.

OC0886-0136-NL04

TSCR - Containment Testing 6 Palisades Plant Additionally, the number of tendons undergoing complete detensioning has been reduced from the previous requirements. This acceptable reduction ensures the margin of safety of the containment structure is not affected by detensioning and retensioning a larger sample than is necessary to conduct an appropriate surveillance program.

III. Conclusion The Palisades Plant Review Committee has reviewed this Technical Specification Change Request and has determined that this change does not involve an unreviewed safety question and, therefore, involves no significant hazards consideration. This change has also been reviewed under the cognizance of the Nuclear Safety Board. A copy of this Technical Specification Change Request has been sent to the State of Michigan official designated to receive such Amendments to the Operating License.

CONSUMERS POWER COMPANY Buckman, Vice Presiden Nuclear Operations Sworn and subscribed to before me this 4th day of May 1987.

~~*~*

Elaine E Buehr~otary Public Jackson County, Michigan My commission expires October 31, 1989 OC0886-0136~NL04