Provides Editorial Changes to 840731 Cover Ltr & Attachment 1 Re Suppl 1 to NUREG-0737,safety Parameter Display Sys PSAR & Implementation Schedule,Per Reg Guide 1.97 Variables
ML18051B025
Person / Time
Site: Palisades Entergy icon.png
Issue date: 08/09/1984
From: Johnson B
CONSUMERS ENERGY CO. (FORMERLY CONSUMERS POWER CO.)
To: Crutchfield D
Office of Nuclear Reactor Regulation
References
RTR-NUREG-0737, RTR-NUREG-737, RTR-REGGD-01.097, RTR-REGGD-1.097 NUDOCS 8408140295
Download: ML18051B025 (6)


Text

,...

consumers Power company General Offices: 1945 West Parnall Road, Jackson, Ml 49201 * (517) 788-0550 August 9, 1984 Dennis M Crutchfield, Chief Operating Reactor Branch No 5 Nuclear Reactor Regulation US Nuclear Regulatory Commission Washington, DC 20555 DOCKET 50-255 - LICENSE DPR PALISADES PLANT - SUPPLEMENT 1 TO NUREG-0737 - SAFETY PARAMETER DISPLAY SYSTEM

- PRELIMINARY SAFETY ANALYSIS REPORT AND IMPLEMENTATION SCHEDULE, REGULATORY GUIDE 1.97 VARIABLES AVAILABLE AT EMERGENCY RESPONSE FACILITIES -

CORRECTED COVER LETTER AND ATTACHMENT 1 The purpose of this submittal is to make editorial changes to the cover letter and Attachment 1 of the July 31, 1984 submittal. Accordingly, the cover letter and Attachment 1 of the July 31, 1984 submittal are reprinted below in their entirety and replace the corresponding sections of the previous letter.

Corrections are indicated by a bar in the right hand margin.

Supplement 1 to NUREG-0737, December 17, 1983 provides, in part, NRC guidance for completion of Safety Parameter Display System (SPDS) and Regulatory Guide 1.97 Projects. The purpose of our July 31, 1984 submittal was to fulfill commitments associated with each project as stated in Consumers Power Company submittals dated September 16, 1983 and September 13, 1983.

Safety Parameter Display System In accordance with Supplement 1 to NUREG-0737, the SPDS will provide a concise display of critical plant variables to the control room operators to aid them in rapidly and reliably determining the safety status of the plant. The SPDS display augments the Critical Function Monitoring System (CFMS). The SPDS and CFMS are complimentary systems. Each is described in Attachment 2.

With the exception of a dedicated display in the control room, the SPDS will be fully operational and operators trained by December 1985. The capability will exist, by December 1985, to display SPDS parameters in the control room through a CRT which is not dedicated to display of SPDS parameters (the CRT will be shared with the CFMS). A CRT dedicated to the display of SPDS para-meters will be added to the control room before startup from the next refuel-ing outage.

',--------8408140295 840809 PDR ADOCK 05000255 F PDR floo.3 OC0684-0020A-NL02

'/'

DMCrutchfield, Chief Palisades Plant

Regulatory Guide 1.97 Consumers Power Company's submittal dated September 13, 1983 committed to provide a detailed list of CFMS variables which will be available by data-link to the Technical Support Center, Emergency Operations Facility and General Office Control Center. This commitment was made in response to Sections 6.1.c and 6.1.d of Supplement 1 to NUREG-0737 to fulfill the need of making appropriate Regulatory Guide 1.97 variables available to appropriate Emergency Response Facilities. Appendix C of Attachment 2 of our July 31, 1984 submittal provides the list of variables. CFMS variables will be available by May 1985. This schedule is consistent with the operability and turnover of CFMS to the Plant Operations Department. Consumers Power Company submittal dated September 16, 1983 provides additional response regarding Regulatory Guide 1.97. In summary, the CFMS is considered an enhancement to the Emergency Response Facilities.

Conclusion of this submittal provides a summary of Milestone Commitments on Supplement 1 to NUREG - 0737. The Attachment was last submitted July 31, 1984 and is revised to reflect an SPDS completion date consistent with the cover letter.

Brian D Johnson Staff Licensing Engineer CC Administrator, Region III, USNRC NRC Resident Inspector - Palisades Attachment OC0684-0020B-NL02

ATTACHMENT 1 Consumers Power Company Palisades Plant - Docket 50-255 MILESTONE CO:MMITMENTS ON SUPPLEMENT 1 TO NUREG-0737 REVISION 4 August 9, 1984 3 Pages MI0684-0018A-NL02

~ Consumers Power Company Palisades Plant MILESTONE COMMITMENTS ON SUPPLEMENT 1 TO NUREG-0737 REVISION

SUMMARY

Consumers Revision Power Company Number Submittal REVISION

SUMMARY

0 September 16, 1983 Original Submittal 1 April 2, 1984 Modify Emergency Operating Procedure and Detailed Control Room Design Review schedules to accomodate increased scope for function and task analysis. The increased scope addresses NRC letters of February 29, 1984 and May 16, 1984.

2 June 29, 1984 a) Revise wording to be consistent with NRC Confirmatory Order dated June 12, 1984 b) Document EOP Procedure Generation Package submittal c) Provide EOP implementation schedule d) Provide date for DCRDR report and implementation schedule e) Revise Regulatory Guide 1.97 commitment dates to accomodate increased scope of function and task analysis and a resequencing of activities 3 July 31, 1984 a) Document SPDS safety analysis report submittal b) Provide implementation schedule for SPDS fully operational and operators trained 4 August 9, 1984 Editorial Change. Revise SPDS implementation schedule (item lb) to be consistent with schedule proposed in July 31, 1984 cover letter.

MI0684-0018B-NL02

CONSUMERS POWER COMPANY PALISADES PLANT MILESTONE COMMITMENTS ON SUPPLEMENT 1 TO NUREG-0737 REVISION 4 AUGUST 9, 1984 TITLE REQUIREMENT COMPLETION SCHEDULE (Or Status)

1. Safety Parameter Display la. Submit a safety analysis Complete (Consumers Power Company System (SPDS) and an implementation plan letter dated July 31, 1984) to the NRC.

lb. SPDS fully operational and December 1985 operators trained.

2. Detailed Control Room Design 2a. Submit a program plan to Complete (Consumers Power Company letters Review (DCRDR) the NRC. dated March 16, 1982 & June 7, 1983.)

2b. Submit a summary report May 1985 to the NRC including a proposed schedule for implementation,

3. Regulatory Guide 1.97 - 3a. Submit a report to the NRC May 1986 Application to Emergency describing how the require-Response Facilities ments of Supplement 1 to NUREG-0737 have been or will be met.

3b. Implement (installation or Plan and schedule to be upgrade) requirements. provided with report in May 1986 MI0684-0018B-NL02

CONSUMERS POWER COMPANY PALISADES PLANT MILESTONE COMMITMENTS ON SUPPLEMENT 1 TO NUREG-0737 REVISION 4 AUGUST 9, 1984 TITLE REQUIREMENT COMPLETION SCHEDULE (Or Status)

4. Upgrade Emergency Operating 4a. Submit a Procedures Complete (Consumers Power Procedures (EOPs) Generation Package to Company letter June 29, 1984) the NRC.

-I 4b. Implement the upgraded February 1986 EOPs.

5. Emergency Response Facilities 5a. Technical Support Center Complete*

full functional.

5b. Operational Support Center Complete*

fully functional.

5c. Emergency Operations Complete*

Facility fully functional.

  • Except for any additional changes that may be required as a result of the other items in this order.

MI0684-0018B-NL02