Forwards Revised Milestone Activity Commitment List,Per Generic Ltr 82-33,Suppl 1 to NUREG-0737,in Response to 830811 Telcon Request.Upgraded Emergency Operating Prpcedures Will Be Implemented by Dec 1985
ML18051A598
Person / Time
Site: Palisades Entergy icon.png
Issue date: 09/16/1983
From: Toner K
CONSUMERS ENERGY CO. (FORMERLY CONSUMERS POWER CO.)
To: Crutchfield D
Office of Nuclear Reactor Regulation
References
RTR-NUREG-0737, RTR-NUREG-737 GL-82-33, NUDOCS 8309200343
Download: ML18051A598 (3)


Text

--~

consumers Power company General Offices: 1945 West Parnall Road, Jackson, Ml 49201*(517)788-0550 September 16, 1983 Dennis M Crutchfield, Chief Operating Reactor Branch No 5 Nuclear Reactor Regulation US Nuclear Regulatory Commission Washington, DC 20555 DOCKET 50-255 - LICENSE DPR PALISADES PLANT - SUPPLEMENT 1 TO NUREG-0737, MILESTONE ACTIVITY COMMITMENT LIST The NRC Staff requested that Consumers Power Company revise the milestone activity list originally included in our submittal dated April 14, 1983 entitled "Response to Generic Letter 82-33, Supplement 1 to NUREG-0737." The request was made August 11, 1983 in a telephone conference call between NRC and Consumers Power Company representatives. The purpose of the revision is to highlight, for each initiative, the following milestone activities:

A. Identify when a majority of the initiative's front end work will be complete independent of downstream impact of other initiatives (i.e.

date at which a majority of the open items are identified).

B. Identify when Consumers Power Company can submit a schedule to close the initiative. This schedule is to include the downstream impact of other initiatives (to the extent possible).

The attached commitment list is sent in response to the Staff's request. This list supercedes Section 4 and the integrated summary schedule figure provided in the April 14, 1983 submittal.

It is Consumers Power Company's understanding that the NRC will issue a Confirmatory Order based on the commitments provided in the attached list.

Kerry A Toner Senior Licensing Engineer CC Administrator, Region III, USNRC NRC Resident Inspector - Palisades flooJ OC0983-0005A-NL02 83092-00343 830916 .

PDR ADOCK 05000255 F PDR '/ J

CONSUMERS POWER COMPANY PALISADES PLANT COMMITMENTS ON SUPPLEMENT 1 TO NUREG-0737

  • TITLE MILESTONE DESCRIPTION COMPLETION SCHEDULE (Or Status)
1. Emergency Operating la. NRC acceptance of Combustion Complete Procedures (EOP) Engineering Owners' Group (NRC letter February 8, 1983)

Emergency Procedures Guideline Program lb. Submit a Procedures Generation May 1984 Package to the NRC le. Implement the upgraded EOPs December 1985

2. Detailed Control Room 2a. Submit a program plan Complete Design Review to the NRC (Consumers ~ower Company letters May 16, 1982 and June 7, 1983) 2b. Submit an interim report to December 1984 the NRC including a proposed schedule for implementation
3. Regulatory Guide 1.97 3a. Submit a report to the NRC May 1985 Application to Emergency describing how the requirements Response Facilities of Supplement 1 to NUREG-0737.

have been or will be met; include a proposed schedule for implementation.

OC0983-0005C-NL02

CONSUMERS POWER COMPANY PALISADES PLANT COMMITMENTS ON SUPPLEMENT 1 TO NUREG-0737 TITLE MILESTONE DESCRIPTION COMPLETION SCHEDULE (Or Status)

4. Safety Parameter 4a. Submit a comparison report of July 1984 Display System (SPDS) the Critical Functions Monitoring System to the SPDS criteria, a preliminary safety analysis report and an implementation plan to the NRC.

S. Emergency Response Sa. Technical Support Center (TSC) End of 1983 Refueling Outage Facilities fully functional.* (Open item is currently addressed by NRC Confirmatory Open Item - complete TSC Order dated March 14, 1983, habitability modifications Item III. D. 3. 4 "Control Room Habitability")

Sb. Operational Support Center Complete fully functional.*

Sc. Emergency Operations Facility Complete fully functional.*

  • Except for any additional changes that may be required as a result of completion of the other initiatives (i.e., items 1 through 4)

OC0983-0005C-NL02