ML18045A549

From kanterella
Jump to navigation Jump to search
Responds to NRC Requesting Addl Info Re Adequacy of Station Electric Distribution.Relay Mods Completed & Final Version of Logic Diagram Incorporated W/Drawing E-17, Sheets 1 & 2 of Facility P&Ids
ML18045A549
Person / Time
Site: Palisades Entergy icon.png
Issue date: 08/22/1980
From: Hoffman D
CONSUMERS ENERGY CO. (FORMERLY CONSUMERS POWER CO.)
To: Crutchfield D
Office of Nuclear Reactor Regulation
References
NUDOCS 8008280440
Download: ML18045A549 (4)


Text

General Offices: 212 West Michigan Avenue, Jackson, Michigan 49201 * (517) 788-0550 August 22., 1980 Director, Nuclear Reactor Regulatidn.

Att Mr Dennis M <:;rutchfield, Chief Op~rating Reactors Branch No 5 us* Nuclear Regulatory Commission Washington, DC 20555 DOCKET 50-255 - LICENSE DPR PALISADES PLANT L RESPONSE TO ADEQUACY OF STAT~ON'POWER Consumers Power Company was requested by NRC letter dated June 19, 1980; to provide additional information on adequacy of station electric distribution system voltages for our Palisades Plant. *our responses are as follows:~

Question 1 "Does the 86.25% of 2400 V setpoint of your second level of voltage protection (attachment 2a) adequately protect 480 V and 120 V class lE equipment?

Response td item* 1 d indicates this setpoint is 0. 913 PU.

Resolve the discrepancy."

Re'sponse to Question 1 Relay modifications have been completed and the final version of the logic diagram has been incorporated on Drawing E-17, Sh 1 & 2 of the Palisade$'

P&IDs.

  • The actual relay setting values are. reflected in the Relay Setting Data Sheets submitted in our May 7, 1980 le"tter to the NRC.

Our October 2, 1978 letter states*in the response to Position la, "The.

proposed ~ndervo~tage relays will be set to protect the 460 V motors fr~m ldng-term voltages pelow 86.25~~ of 480 V (not 2400 V), and this setting'.

reflect~d to.th* 2400 V bus will more than adequately protect the 2300 V motors."

Our subsequent voltage drop calculations have shown that a value of 9i.3% dn the 2400 V bus is needed to ens~re a value of 86.25% on the 486 V bus.

!~o'f.1 b

.80 0 8 280Jlf0

2 Question 2 "Per* NRC guidelines 3 and 9b, compare the effect of starting and running the larg~st non-class iE load on all class lE equipment with the required voltage rang'e for hormal operation of these loads (starters' contactors' motors' etc.).

What is the duration of identified transient undervoltage conditions?"

Response to Question 2 Item 4 in the NRC letter to CP Co dated June 6, 1979 asked basically the same question.

CP Co responded to that question in a submittal letter dated February 27, 1980.

The following is an elaboration.on the analysis that was performed and referenced in the February 27, 1980 letter.

Referring to the one-line diagrams for the Palisades Plant, it can be seen that the typical large nonclass lE.loads (condensate, primary coolant, cooling tower) are rated at 4160 V.

These loads are connected directly to the main transmission system (345 kV) and the analysis shows that the starting and running of these loads has *no effect on the voltage at the 2400 V buses.

The 2400 V and 4160 V buses are directly*connected to the. 345 kV system and are not interconnected to each other.

Therefore, loads from the 4160 V bus do not affect the loads of the 2400 V bus.

The largest nonclass lE load on the 2400 V buses is an 800 hp heater drain pump which is only operated when the unit is on line.

An analysis was performed assuming the lowest typical generator voltage and found that the 2400 V bus voltage drops to 91%. while starting the motor.

This voltage level is sustained for approximately 0.7 seconds.

The total motor acceleration time was'calculated to be approximately 1.6 seconds which is well below the six-second time delay which initiates further undervoltage protection as outlined in Drawing E-17, Sh 1 & 2, of the Palisades Plant P&IDs.

Question 3 "As required by NRC guideline 9, CP should provide analysis and comparison of terminal voltages on all class lE loads (2300 V, 480 V, and lower voltage loads) for the worst case starting voltage and steady state running voltages.

The CP submittalsa,c,d do not include all of these values."

Res?onse to Question 3 The analysis and comparison of terminal voltages on Class lE loads for the worst case starting voltage was previously submit'ted in the Response to Item 9 of the March 7, 1980 letter to the NRC.

The' analysis of terminal voltages on Class lE loads for steady-state running conditions shows a per unit (PU) voltage of L 015 (Bus lC),. 974 (LC 11),. 970 (MCC-1), 1. 015 (Bus lD),. 995 (LC 12),. 993 (MCC 2).

In comparison, as stated in the Response to Question 1 above, the 480 V buses need a voltage of 86.25%

to ensure proper operation.

Question 4 "Plant FSAR, Section 8.3.2.2 and single line diagram indicate three alternate sources of offsite.power to class lE buses.

Reference 2 includes analysis only, for one offsite source (startup transformer).

Separate ~nalysis for the other two offsite ~ources (service transformer and st~tion power transformer) is required."

Response to Question 4 3

As stated in the R~sponse to Item 1 of the March 7, 1980 letter to the NRC; the largest load demand situation occurs following an accident which trips the unit; and initiates an SIS signal.

Tripping the unit results in a fast trans-fer from station power to start~up power.

Because of this feature, the Station Power Transformer l.s not subjected to the same loads as the start-up transformer.

Therefore, we did not analyze this voltage condition.

We did, however, analyze the effects of starting a large nonclass lE load (800 hp heater drain pump) 1while connected to the Station Power Transformer and re-ported the results.of this analysis in the Response to Item 1 in the letter to the NRC dated January 9, 1980.

A discussion of this analysis is also included in the Response to Item 4 in the letter to the NRC dated February 27, 1980.

Per unit voltages from this analysis have been included in the Response to Question 3 above.

Based on the above, we feel that the Station Power Transformer has been sufficiently analyzed for its duties as a source of off-site power.

The Reserve Transformer, referred to by the NRC as a Service Transformer, is only* used in the event that the Start-Up Transformer has to be taken out of service and the plant would have to be maintained in a shutdown mode using the

~on-site power sources (diesel generators).

The transformer has a rated capacity equal to both of the diesel generators.

If the Reserve Transformer is ever.used in a shutdown mode, it will be manually loaded in the same manner as the diesel generators.

Since this transformer has no normal operating conditions or automatic loading schemes, no further analysis is required.

Question 5 "As per reference ~. the generic issue in reference b, is part of SEP topic VIII-1-A.

CP should, therefore, review the station power system for possible

  • 1 t" f GDC 17 t d 1"n reference b."

v10 a ion o

-. as reques e

i Re~ponse to Question 5 as it applies to the Palisades Plant will be reviewed under SEP Topic evaluation.

Dapid P Hoffman Nuplear Licensing Administrator CCi Director, Region III, USNRC NRC Resident Inspector-Palisades 4

' L' i

"