Monthly Oper Rept for Oct 1978
ML18043A261
Person / Time
Site: Palisades 
Issue date: 11/03/1978
From: Bollnow D
CONSUMERS ENERGY CO. (FORMERLY CONSUMERS POWER CO.)
To:
Shared Package
ML18043A259 List:
References
NUDOCS 7811140148
Download: ML18043A261 (4)


Text

(_

,(..

OPER.ATING DATA REPORT OPERA TING ST A TUS DOCKET NO.

DATE COMPLETED BY TELEPHONE

. 50-255 11-3-78 DIBollnow.*

616-764-8913

1. Unit Name:

Palisades Notes

2. Reporting Period:

781001 to 781031 2530

3. Licensed Thermal Power (MWt):
4. Nameplate Rating (Gross MWe):* ---------=8,....,1,....,le--._7 __
5. Design Electrical Rating (Net MWe):

805

6. Maximum Dependable Capacity (Gross MWe):
  • 6 7 5
  • 635
7. Maximum Dependable Capacity (Net MWe):
8. If Changes Occur in Capacity Ratings (items Number 3 Through 7) Since Last Report. Give Reasons:
9. Power Level To Which Restricted, If Any (Net MWe):
10. Reasons For Restrictions, If Any:

This Month Yr.-to-Date Cumulative

11. Hours In Reporting Period 745 7,296 60,207
12. Number Of Hours Reactor Was Critical 495.0 3,647.8 33,047.2
13. Reactor Reserve Shutdown Hours
14. Hours Generator On-Line 478.4, 3,282.2 31,115.0
15. Unit Reserve Shutdown Hours
16. Gross Thermal Energy Generated (MWH) 1, 172, 520
17. Gross Electrical Energy Generated (MWH) 346 '390
18. Net Electrical Energy Generated (.MWH) 325, 995 6,910,560 56,932,224 2,026,490 17,613,100 16,502,050 1,888,683
19. Unit Service Factor
64. 2%

45.0%

51.7%

20. Unit Availability Factor 64.2%

45.0%

51. 7%
21. Unit Capacity Factor (Using MDC Net) 68
  • 9%
22. Unit Capacity Factor (Using DER Net) 54.4%

40.8%

43.2%

32.2%

  • 34~1%
23. Unit Forced Outage Rate
35. 8%'

26.9%

39. 3%.
24. Shutdowns Scheduled Over Next 6 Months (Type. Date. and Duration of Each):
25. If Shut Down At End Of Report Period, Estimated Date of Startup:
26. Units In Test Status (Prior to Commercial Operation):

INITIAL CRITICALITY INITIAL ELECTRICITY C0'.\\*1MERCIAL OPERATION.

Forecast Achieved

  • Based on Condenser Backpressure

('ci/77)

Limitations 75/1/YtfJ/I/ o

  • No.

Date 781002 781010 781011 2

F: Forced S: Scheduled (lJ/77)

~

r

  • 1 UNIT SHUTDOWNS AND POWER REDUCTIONS REPORT MONTH October 1978 r I F

123.4 A

1 F

133.5 A

1 F

9.7 A

3 Reason:

A-Equipment Failure (Explain)

B-Mainlenance or Test

('-Refueling D-Regulat ory Restriction Licensee Event Report it N/A N/A*

N/A E-Opcratur Training & License Examination F-Ad mi nist rat ive G-Opera tiunal Error (Explain)

I I-Other (Explain) 3 N/A N/A N/A Method:

I-Manual h

"'tri c:

OJ 0 "O

0. ':J Eu 0 u N/A N/A N/A 2-Manual Scram.

3-Autumatic Scram.

4-0ther (Explain)

DOCKET NO.

UNIT NAME DATE COMPLETED BY TELEPHONE Cause & Corrective Action to Prevent Recurrence Leaking CRDM Seals.

Leaking CRDM Seals Feedwater Pump Trip 4

50-255 Palisades 11-3-78 DIBollnow 616-764-8913 Exhibit G - Instructions for Preparation of Data Entry Sheets ror Licensee 5

Event Report (lER) File (NUREG-0161}

Exhibit I *Same Source

(~.

c

-..,,.... r*

AVERAGE DAILY UNIT POWER LEVEL DOCKET NO.

50-255

. UNIT PALISADES DATE 11-3-78 DIBollnow COMPLETED BY TELEPHONE 616-764-8913 MONTH October 1978 DAY AVERAGE DAILY POWER LEVEL DAY AVERAGE DAILY POWER LEVEL (MWe-Net)

(MWe-Net) 723 17 426*

327 688 2

18 3

19 723 4

20 724 5

21 707 6

22 693 7

385 23 730 8

7 99.

24 738 728 720 9

25 10 567 26 725

])

739 27 726 12 28 13 29 771 14 30 735 725 15 31 16 438 INSTRUCTIONS On this format, list the average daily unit power level in MWe-Net for each day in the reporting month. Compute to the nearest whole megawatt.

(9/77)

~-

-~

CONSUMERS POWER COMPANY PALISADES NUCLEAR PLANT DOCKET No. 50-255

SUMMARY

OF SHUTDOWN EXPERIENCE FOR OCTOBER 1978 10-2-78 10-10-78 10-17-78 The plant was taken off-line in order to permit repairs to leaking CRDM Seals.

Two seals were replaced.

In addition, the position indication on one CRDM was re-zeroed, oil was added to one Primary Coolant Pump (P-50C) and changed in another Primary Coolant Pump (P-50A).

The outage lasted 123.4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br />.

The plant was taken off-line for CRDM repairs.

Seventeen seals were replaced.

In addition, the Auxiliary Feedwater Pumps were repacked.

This outage lasted 133.5 hours5.787037e-5 days <br />0.00139 hours <br />8.267196e-6 weeks <br />1.9025e-6 months <br />.

Because of a Feedwater Pump trip when attempting to change the steam supply from high pressure to low pressure steam, the Reactor tripped on low Steam Generator water level.

The plant was off-line for 9.7 hours8.101852e-5 days <br />0.00194 hours <br />1.157407e-5 weeks <br />2.6635e-6 months <br />.