Text
(_
,(..
OPER.ATING DATA REPORT OPERA TING ST A TUS DOCKET NO.
DATE COMPLETED BY TELEPHONE
. 50-255 11-3-78 DIBollnow.*
616-764-8913
- 1. Unit Name:
Palisades Notes
- 2. Reporting Period:
781001 to 781031 2530
- 3. Licensed Thermal Power (MWt):
- 4. Nameplate Rating (Gross MWe):* ---------=8,....,1,....,le--._7 __
- 5. Design Electrical Rating (Net MWe):
805
- 6. Maximum Dependable Capacity (Gross MWe):
- 6 7 5
- 635
- 7. Maximum Dependable Capacity (Net MWe):
- 8. If Changes Occur in Capacity Ratings (items Number 3 Through 7) Since Last Report. Give Reasons:
- 9. Power Level To Which Restricted, If Any (Net MWe):
- 10. Reasons For Restrictions, If Any:
This Month Yr.-to-Date Cumulative
- 11. Hours In Reporting Period 745 7,296 60,207
- 12. Number Of Hours Reactor Was Critical 495.0 3,647.8 33,047.2
- 13. Reactor Reserve Shutdown Hours
- 14. Hours Generator On-Line 478.4, 3,282.2 31,115.0
- 15. Unit Reserve Shutdown Hours
- 16. Gross Thermal Energy Generated (MWH) 1, 172, 520
- 17. Gross Electrical Energy Generated (MWH) 346 '390
- 18. Net Electrical Energy Generated (.MWH) 325, 995 6,910,560 56,932,224 2,026,490 17,613,100 16,502,050 1,888,683
- 19. Unit Service Factor
- 64. 2%
45.0%
51.7%
- 20. Unit Availability Factor 64.2%
45.0%
- 51. 7%
- 21. Unit Capacity Factor (Using MDC Net) 68
- 9%
- 22. Unit Capacity Factor (Using DER Net) 54.4%
40.8%
43.2%
32.2%
- 34~1%
- 23. Unit Forced Outage Rate
- 35. 8%'
26.9%
- 39. 3%.
- 24. Shutdowns Scheduled Over Next 6 Months (Type. Date. and Duration of Each):
- 25. If Shut Down At End Of Report Period, Estimated Date of Startup:
- 26. Units In Test Status (Prior to Commercial Operation):
INITIAL CRITICALITY INITIAL ELECTRICITY C0'.\\*1MERCIAL OPERATION.
Forecast Achieved
- Based on Condenser Backpressure
('ci/77)
Limitations 75/1/YtfJ/I/ o
- No.
Date 781002 781010 781011 2
F: Forced S: Scheduled (lJ/77)
~
r
- 1 UNIT SHUTDOWNS AND POWER REDUCTIONS REPORT MONTH October 1978 r I F
123.4 A
1 F
133.5 A
1 F
9.7 A
3 Reason:
A-Equipment Failure (Explain)
B-Mainlenance or Test
('-Refueling D-Regulat ory Restriction Licensee Event Report it N/A N/A*
N/A E-Opcratur Training & License Examination F-Ad mi nist rat ive G-Opera tiunal Error (Explain)
I I-Other (Explain) 3 N/A N/A N/A Method:
I-Manual h
"'tri c:
OJ 0 "O
- 0. ':J Eu 0 u N/A N/A N/A 2-Manual Scram.
3-Autumatic Scram.
4-0ther (Explain)
DOCKET NO.
UNIT NAME DATE COMPLETED BY TELEPHONE Cause & Corrective Action to Prevent Recurrence Leaking CRDM Seals.
Leaking CRDM Seals Feedwater Pump Trip 4
50-255 Palisades 11-3-78 DIBollnow 616-764-8913 Exhibit G - Instructions for Preparation of Data Entry Sheets ror Licensee 5
Event Report (lER) File (NUREG-0161}
Exhibit I *Same Source
(~.
c
-..,,.... r*
AVERAGE DAILY UNIT POWER LEVEL DOCKET NO.
50-255
. UNIT PALISADES DATE 11-3-78 DIBollnow COMPLETED BY TELEPHONE 616-764-8913 MONTH October 1978 DAY AVERAGE DAILY POWER LEVEL DAY AVERAGE DAILY POWER LEVEL (MWe-Net)
(MWe-Net) 723 17 426*
327 688 2
18 3
19 723 4
20 724 5
21 707 6
22 693 7
385 23 730 8
7 99.
24 738 728 720 9
25 10 567 26 725
])
739 27 726 12 28 13 29 771 14 30 735 725 15 31 16 438 INSTRUCTIONS On this format, list the average daily unit power level in MWe-Net for each day in the reporting month. Compute to the nearest whole megawatt.
(9/77)
~-
-~
CONSUMERS POWER COMPANY PALISADES NUCLEAR PLANT DOCKET No. 50-255
SUMMARY
OF SHUTDOWN EXPERIENCE FOR OCTOBER 1978 10-2-78 10-10-78 10-17-78 The plant was taken off-line in order to permit repairs to leaking CRDM Seals.
Two seals were replaced.
In addition, the position indication on one CRDM was re-zeroed, oil was added to one Primary Coolant Pump (P-50C) and changed in another Primary Coolant Pump (P-50A).
The outage lasted 123.4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br />.
The plant was taken off-line for CRDM repairs.
Seventeen seals were replaced.
In addition, the Auxiliary Feedwater Pumps were repacked.
This outage lasted 133.5 hours5.787037e-5 days <br />0.00139 hours <br />8.267196e-6 weeks <br />1.9025e-6 months <br />.
Because of a Feedwater Pump trip when attempting to change the steam supply from high pressure to low pressure steam, the Reactor tripped on low Steam Generator water level.
The plant was off-line for 9.7 hours8.101852e-5 days <br />0.00194 hours <br />1.157407e-5 weeks <br />2.6635e-6 months <br />.