Advises That Mark I long-term Program Mods Will Be Completed Prior to Start of Cycle 8 in 1984,per 820119 Order Re Conformance to NUREG-0661,App a
ML18038A566
Person / Time
Site: Nine Mile Point Constellation icon.png
Issue date: 01/05/1983
From: Mangan C
NIAGARA MOHAWK POWER CORP.
To: Vassallo D
Office of Nuclear Reactor Regulation
References
RTR-NUREG-0661, RTR-NUREG-661 NUDOCS 8301070265
Download: ML18038A566 (2)


Text

NIAGARA MOHAWK POWER CORPORATION/300 ERIE BOULEVARD WEST, SYRACUSE, N.Y. 13202/TELEPHONE (315) 474-1511 January 5, 1983 Director, Nuclear Reactor Regulation Attn: Mr. Domenic B. Vassallo, Chief Operating Reactors Branch No. 2 United States Nuclear Regulatory Commission Washington, D.C. 20555 Re: Nine Mile Point Unit 1 Docket No. 50-220 DPR-63

Dear Mr. Vassallo:

Your order dated January 19, 1982 outlined the schedule for completing the Mark I long-term program at Nine Mile Point Unit 1. This program involves modifications which are needed to conform to the staff 's Acceptance Criteria contained in Appendix A to NUREG-0661. The order stated that the required completion date for plant modifications was "Prior to the start of Cycle 8 at the completion of your spring 1983 refueling outage".

As indicated in our letters of May 11 and August 6, 1982, Nine Mile Point Unit 1 was shut down in mid-Cycle 7 for the replacement of reactor recirculation system safe ends and piping. This unscheduled outage, which began in March of 1982, is not expected to be completed until summer 1983.

Upon completion of the outage, Cycle 7 operation will resume for approximately one year, at which time refueling will commence. Therefore, Cycle 8 will not commence until completion of the refueling outage now scheduled for 1984.

Based on the aforementioned, the completion of plant modifications needed to conform to the staff 's Acceptance Criteria will be at the completion of the 1984 refueling outage prior to the start of Cycle 8.

Your timely review of our stated schedule is requested.