ML18037A427

From kanterella
Jump to navigation Jump to search
Notice of Violation from Insp on 930712-16.Violations Noted: TVA Did Not Update & Revise Pipe Support Calculations CD-Q2074-894004 & -894005 for Listed Pipe Supports to Reflect Latest Revised Stress Loads
ML18037A427
Person / Time
Site: Browns Ferry  Tennessee Valley Authority icon.png
Issue date: 08/12/1993
From:
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
To:
Shared Package
ML18037A426 List:
References
50-259-93-26, 50-260-93-26, 50-296-93-26, NUDOCS 9308250130
Download: ML18037A427 (2)


Text

ENCLOSURE 1

NOTICE OF VIOLATION Tennessee Valley Authori.ty Browns Ferry Docket Nos.: 50-259, 50-260 and 50-296 License Nos.:

DRP-33, DRP-52 and DRP-68 During an NRC inspection conducted on July 12 - 16,

1993, two violations of NRC requirements were identified.

In accordance with the "General Statement of Policy and Procedure for NRC Enforcement Actions," the violations are listed below:

A.

10 CFR 50, Appendix B,, Criterion XVI, requires that measures shall be established to assure that conditions adverse to quality such as noncon-formances are promptly identified and corrected.

Criterion XVI also requires that the measures shall assure that the cause of the condition is determined and corrective actions taken preclude repetition.

TVA's letter of response, dated February 10, 1993, to NRC Notice of Violation No. 50-259,260,296/92-43-01 stated that to prevent recurrence of a welding program discrepancy, "GE has initiated the development and use of a Design Change Notice (DCN) requirements checklist.

This checklist identifies the requirements in the DCN and provides a tracking method of accounting for completion of each requirement.

" In addition, the complete checklist is then reviewed and is approved by the Project Manager and GE's gC group.

The effective date for implementing the DCN checklist form was January 5, 1993.

Contrary to the above, on July 15, 1993, discussions with GE's gC personnel and review of DCN W-18096A revealed that GE's DCN checklist is presently not being used by GE for DCNs involving welding and weld repairs in the plant.

In addition, GE had not revised their welding manual or administrative procedures to implement this commitment for preventing recurrence of the nonconforming condition.

This is a Severity Level IV violation (Supplement 1).

B.

10 CFR 50, Appendix B, Criteria III, Design Control, requires that design changes, including field changes, shall be subject to design control measures commensurate with those applied to the original design and be approved by the organization that performed the original design unless the applicant designates another responsible organization.

TVA Nuclear Engineering Procedure, NEP-3.1, calculations, page 1 of 1 of, requires that design inputs, including information such as

loads, temperatures, and pressure originated within engineering or supplied by vendors, and codes, standards, regulatory requirements, and FSAR commitments, shall be current and correctly selected, referenced and applied.

9308250130 '9308l2

.PDR

  • DOCK.05000259>I<

O' PDR. g'~

Tennessee Valley Authority 2

Docket Nos.: 50-259, 50-260 and 50-296 Browns Ferry License Nos.:

DRP-33, DRP-52 and DRP-68 TVA Procedure BFN-RAH-401, Rigorous Analysis Handbook, Section 7.0 of Rigorous Analysis checklist, requires that the correct support loads from the post processor output, or adjusted loads from hand calculations be transmitted to the support designer.

Contrary to the above, TVA did not update and revise pipe support calculations CD-Q2074-894004 and

-894005 for pipe supports 2-47B452S0247 and 2-47B452S0248 to reflect the latest revised stress loads shown in the stress calculation CD-Q2074-893811, Revision 4.

This is a Severity IV violation (Supplement I)

Pursuant to'the provisions of 10 CFR 2.201, is hereby required to submit a

written statement or explanation to the U.S. Nuclear Regulatory Commission, ATTN:

Document Control Desk, Washington, D.C. 20555 with a copy to the Regional Administrator, Region II, and a copy to the NRC Resident Inspector at the facility that is the subject of this Notice, within 30 days of the date of the letter transmitting this Notice of Violation (Notice).

This reply should be clearly marked as a "Reply to a Notice of Violation" and should include for each violation:

(I) the reason for the violation, or, if contested, the basis

~

~

~

~

~

~

~

~

~

~

~

~

~

~

~

~

~

for disputing the violation, (2) the corrective steps that have been taken and the results

achieved, (3) the corrective steps that will be taken to avoid further violations, and (4) the date when full compliance will be achieved.

..If an adequate reply is not received within the time specified in this Notice, an order or Demand for Information may be issued as to why the license should not be modified, suspended, or revoked, or why such other action as may be proper should not be taken.

Where good cause is shown, consideration will be given to extending the response time.

Dated at atlanta, Georgia this (gray of August 1993