TVA - Rugby-Sunbright Areas, Tennessee Tennessee Valley Authority About TVA Newsroom Careers Index Search TVA Energy Environment Economic Development You are here: Home / Energy / Transmission Share this page

/ Transmission System Projects Rugby-Sunbright Areas, Tennessee Update - January 2015 TVA evaluated each route using social, engineering, and environmental factors. Information sources included available data, aerial photography, limited onsite reviews, public review and comment, and property owner input. Based on public input and evaluation, the preferred locations are expected to have the least overall project impacts of the alternatives.

The new substation would be located in Rugby, Tennessee, and would connect to the existing Livingston-Huntsville 161-kV Transmission Line (substation location alternative number one). TVA would also build 7.25 miles of power line from the new Rugby Substation to Plateau ECs existing Sunbright Substation. The route selected was Alternative number one and consists of segment numbers. 1, 2, 3, 5, 8, 11, 12 and 14.

The line would consist of steel pole structures on 100-foot-wide right of way.

The National Environmental Policy Act review is expected to be completed by June 2016. Construction is scheduled to begin in spring 2017 on the substation and in summer 2017 on the power line. The project is scheduled to be complete in fall 2018.

Background - April 2014 TVA is considering improvements to its transmission system that will improve reliability in Morgan County.

TVA is proposing to build a new Rugby Substation and connect it to the nearby Livingston-Huntsville 161-kilovolt line. TVA also proposes to build six to nine miles of transmission line from the new Rugby Substation to Plateau Electric Cooperatives (Plateau ECs) existing Sunbright Substation.

Plateau EC plans to build the Deer Lodge Substation and transmission line from the Sunbright Substation to power the new https://www.tva.gov/Energy/Transmission-System/Transmission-System-Projects/Rugby-Sunbright-Areas-Tennessee[1/27/2017 2:08:02 PM]

TVA - Rugby-Sunbright Areas, Tennessee substation.

TVA is considering several substation locations and 16 alternate line segments. The line would be built on steel pole structures on new 100-foot right of way.

TVA will hold an open house on April 3, 2014 to provide information, answer questions and receive comments about the proposed transmission project.

The project is expected to be in service summer 2017. Construction is scheduled to begin summer 2016.

(Dates are subject to change. During projects of this magnitude, unexpected issues may arise, resulting in the need to adjust the schedule.)

Map The map shows the route TVA is considering for the proposed transmission line. The map is also available below as a PDF file.

Substation tap line (loop) details are shown in PDF map Possible routes of proposed transmission line (PDF, 4.9 mb)

Preferred route of proposed transmission line (PDF, 5.4 mb)

If you have questions or need help understanding the map, please contact TVA.

Environmental reviews The appropriate National Environmental Policy Act review will be conducted to ensure that the environmental impacts are minimized. TVA attempts to minimize land requirements, private property impacts, and environmental impacts associated with this proposed project.

Efforts are made during the siting process to avoid or minimize impacts to floodplains and wetlands in accordance with Executive Orders 11988 and https://www.tva.gov/Energy/Transmission-System/Transmission-System-Projects/Rugby-Sunbright-Areas-Tennessee[1/27/2017 2:08:02 PM]

TVA - Rugby-Sunbright Areas, Tennessee 11990. Floodplain and wetlands along with alternative routes are shown in the referenced map. The map illustrates how each alternative route avoids or impacts floodplains and wetlands. Because of project and topographic constraints and because of minimizing impacts to other social, environmental, and engineering resources, no practicable alternative may be available that would allow complete avoidance of impacts to floodplains and wetlands which may require mitigation for minimizing impacts. Also, best management practices would be utilized throughout the project to minimize adverse floodplain and wetland impacts. In compliance with Section 404 of the Clean Water Act, TVA will be coordinating wetland findings with U.S. Army Corps of Engineers.

Project schedule Dates are subject to change. During projects of this magnitude, unexpected issues may arise, resulting in the need to adjust the schedule.

Open house April 3, 2014 Comments accepted May 5, 2014 Determine preferred route for field surveys January 2015 Surveys of the right of way are scheduled to begin spring 2015 Easement purchases are scheduled to begin fall 2015 Construction is scheduled to begin spring 2017 Project in service fall 2018 Contact More information on this project can be obtained from:

ToddMoore newtransline@tva.gov (800) 362-4355 1101 Market Street, MR 4G Chattanooga,TN37402 Employees and Retirees Energy Facebook TennesseeValleyAuthority https://www.tva.gov/Energy/Transmission-System/Transmission-System-Projects/Rugby-Sunbright-Areas-Tennessee[1/27/2017 2:08:02 PM]

TVA - Rugby-Sunbright Areas, Tennessee TVA Kids Environment Twitter 400 West Summit Hill Doing Business With TVA Economic Development Instagram Drive TVA Privacy Policy Newsroom YouTube KnoxvilleTN37902 Freedom of Information Careers LinkedIn (865) 632-2101 Act About Flickr tvainfo@tva.com Legal Notices Investor Relations Information Quality No Fear Act Data Equal Employment Opportunity Policy Accessibility Information Inspector General TVA Police https://www.tva.gov/Energy/Transmission-System/Transmission-System-Projects/Rugby-Sunbright-Areas-Tennessee[1/27/2017 2:08:02 PM]