ML18031A141

From kanterella
Jump to navigation Jump to search
Submits Licensing Schedule for Facility.Press Releases Encl
ML18031A141
Person / Time
Site: Susquehanna  Talen Energy icon.png
Issue date: 06/20/1979
From: Curtis N
PENNSYLVANIA POWER & LIGHT CO.
To: Harold Denton
Office of Nuclear Reactor Regulation
References
NUDOCS 7906260380
Download: ML18031A141 (10)


Text

REGULATORY FORMATION DISTRIBUTION SY M (RIDS)

'CCESSION NBRt7906260380 DOC ~ DATE 79/06/20 NOTARIZED!

NO FACILt50 387 Susauehanna Steam Electric Statfon< Unit 1g Pennsylva 50 388 Susquehanna Steam Electric Statfon~

Unit 2g Pennsylva AUTH BYNAME AUTHOR AF F ILIATION CURTISeNeWo Pennsylvania Power 8 Light Co, REC IP ~ NAME RECIPIENT AFFILIATION OENTONtH ~ RE Offfce of Nuclear Reactor Regulation

SUBJECT:

Submits licensing, schedule for facf1ity,Pr ess releases encl

~

DISTRIBUTION CODE:

B001B COPIES RECEIVED:LTR

~

ENCL j SIZE:

TITLE! PSAR/FSAR AMOTS ANO RELATED CORRESPONDENCE

~

DOCKET ¹ 05000387 05 053 REC IP IENT IO COOE/NAPE ACTION:

05 PM mlle'E'4 C

i~aiPS:WFay,~>> ~ B~ ~a+>> Aic ~~~, c,,B, /gy~gggp~~iQ&

COPIES REC IP IENT COPIES LTTR ENCL IO CODE/NAME LTTR ENCL 1

1 AD gyssg6ao 1

0 1

0 LA 1

0 INYEPNAL!

REG 06 I tt E

09 GEOSC IEN BR 11:lECH ENG BH 13 MATL ENG BR 16 ANALYSIS BR 18 AUX SYS, BR 20 I 8

C SYS BR 22 AO SITE TECH 27 EFFL TRT SYS 29

'KIRK'>tOOD AO PLANT SYS AO SITE ANLYSIS tap A EXTERNAL: 03 LPOR 30 ACRS 1

1 2

2 1

1 2

2 1

1 1

1 1

1 1

1 1

1 1

0 1

0 1

0 1,

1 10 10 02 NiRC POR 08 OPERA LIC 8R 10 QA8 12 STRUC ENG HH 15 REAC SYS BH 17 CORE PERF 9R 19 CONTAIN SYS 21 PO'KER SYS BR 26 ACCD"'T ANLYS 28 RAO ASMT BR AD FOR EiNG AD REAC SAFETY DIRECTOR NRR OELO Ot1 NS IC 1

1 1

1 1

i 1

1 1

1 1

1 1

1 1

1 1

1 1

1 0

1 0

1 0

1 0

1 1

pug g'l le&

na~4E Ega c.Sight t Pc3 yah. +

87 V7 TOTAL NUMBER OF COPIES REQUIRED:

LTTR ~

ENCL'

PPaL TWO NORTH NINTH STREET, ALLENTOWN, PA.

18101 PHONE: (215)'21-515'I NORMANW. CURTIS Vice President Engineering 8, Construction 821-5381 4

June 20, 1979 Dr. Harold Denton, Director Office of Nuclear Reactor Regulation U.S. Nuclear Regulatory Commission Washington, D.C.

20555 SUS UEHANNA SES SCHEDULE (g[flgii6PVflfl5'P Etiam Pony

Dear Harold:

The opportunity to discuss licensing schedules was appreciated by us and, I'm sure, by the other utilities present on June 13.

The situation with the Susquehanna licensing schedule is perplexing and I believe it would be beneficial to review this situation.

In"May, 1978, our Licensing and Scheduling people met with NRC's Caseload Forecast Panel to discuss the status of construction, the methods used by PP8L and our Contractor to assess schedule status, and the expected project completion date.

The panel assessed the Susquehanna Project as being 6-7 months behind PP8L's official completion date of May, 1980.

A date of December, 1980 was chosen by NRC as the completion date, and the staff licensing review was keyed to it.

We, too, have been concerned about the schedule for completion of Susquehanna and have devoted substantial resources to improving our.schedule performance.

The changes made since May, 1978 have resulted in substantial improvements in the pace of construction,, setting some new industry records in bulk installation rates in the process.

As a result of this improvement, we requested that the Forecast Panel return to Susquehanna=-

and reassess the construction schedule.

.This activity took place in May, 1979.

While we have received no notification from you, we understand that the panel's assessment was even more pessimistic than their previous date of

December, 1980.
Further, we understand your "blue book" schedule specifies
June, 1981 as the date for completion of Licensing and identifies December, 1980 as our assessment of fuel load date.

The conflict of schedules between our organizations is counterproductive and must be eliminated.

We acknowledge that achieving our May, 1980 target fuel load date is unlikely; "However, we are confident that we could achieve a September; 1980 fuel load date.

o PENNSYLVANIA POWER 8

LIGHT COMPANY v eosseO~Z&

Dr; Harold Denton Page 2

June 20, 1979 Based on your presentation at the June 13 meeting, we conclude that NRC licensing activities are the critical path fot the Susquehanna Project.

It appears that even if you develop the additional resources necessary to continue

casework, you will not be able to recover schedule sufficiently to support our construction completion date.

Consequently, we have decided to reschedule the fuel load date for Susquehanna Unit 1 to December, 1980, the date established by you for the completion of licensing.

This also necessitates a change in the fuel load date of Susquehanna Unit 2 from November, 1981 to April, 1982.

In the June 13 meeting, you asked to be informed of the actions taken by utilities in response to the TNI incident.

PPSL has initiated an in-house re-evaluation program consisting of the following five areas:

1)

Review of radiation monitoring program 2)

Reassessing Emergency Procedures 3)

Review of the Susquehanna Design 4)

Re-examining personnel qualifications and training.programs 5)

Broadening PPSL s Communication and public information program.

Attached are copies of a news release and an internal bulletin board announcement describing this program.

Me will, of course, present the results of this effort to the staff at the appropriate time.

Very truly yours, N.

W. Curtis Project Director-Susquehanna

/jm

~ ~

fromPal CONTACT:

SOURCE:

Nancy Bishop (215) 821-5687 Implementation of a five-point program to reassess certain aspects of the Susquehanna nuclear plant has been started by Pennsylvania Power 4 Light Co-Announcement of the program was made by PPRL President and Chief Executive Officer Robert K. Campbell following the accident at the Three Mile Island nuclear plant.

It includes reviewing design of the Susquehanna plant; re-examining the radiation monitoring program planned for the plant; reassessing emergency procedures; reviewing the qualifications and training programs.for personnel involved in the plant's

" operation and broadening the - company's communication program to keep the public well informed about the plant.

Located in Salem Township north of Berwick, the Susquehanna plant is PAL's first nuclear facility.

jointly owned with Allegheny Electric Cooperative, Inc., it is 73 percent complete.

The two 1,050,000-ki lowatt generating units at the facility are scheduled for operation in 1981 and 1982.

more

"This will be just as complete and thorough a review as we can possibly make it," Campbell said..

"The people who will conduct it have been carefully selected for their competency in their areas oi.expertise."

Serving on the committee reviewing the plant's design will be Eugene A.

Saltarelli, vice president of NUS Corp., Rockville, MD, chairman; Dr. Gordon E.

Robinson, professor of nuclear 'engineering, Pennsylvania State University, University Park; Hugh L. Campbell III, technical director of EBECO

~ Associates,

Hazleton, who is a member of PPdcL's Public Advisory Committee; James M. Smith Jr., consulting environmental engineer, General Electric Co., San
Jose, CA, and Joseph B.

Violette, manager-corporate quality assurance, Bechtel Power Corp., San Francisco, CA.

Included in the group's review will be an assessment, when the information is available, of'the hardware failures, operating procedures and their consequences at Three Mile Island and the capability of the Susquehanna plant to

\\

withstand similar events; an examination of possible combinations of equipment failure and operator error which were not considered in the original plant design, but which should be considered as a result of the Three Mile Island accident.

A review of the data available to the operator and how it's presented during an unusual operating condition, including an analysis of the ability of an operator to respond to multiple alarms and to initiate multiple manual actions to prevent unsafe operating conditions also willbe conducted.

more

In addition, the group will revi'ew the safeguards used at Susquehanna which assure that safety systems function properly and will re-examine the capability of plant systems to respond in a variety of emergencies including the presence of excess hydrogen, fission gases and contaminated water.

Another committee studying the radiation monitoring program will review the existing program detailed in the licensing documents for the plant and willdevelop recommendations for a more comprehensive system.

Among the things to be considered will be providing monitoring data at sites away from the plant to keep the plant staff, PPRL management, government and civil defense agencies informed in the event of unusual radiation releases.

Also, the most

recent, state-of-the-art techniques for detection, continuous monitoring and sampling of radiation in the environment will be investigated.

The goal of the group studying Susquehanna emergency procedures is

. to establish an emergency plan that gives first consideration to public health and safety while meeting the Nuclear Regulatory Commission requirements for an operating license for the plant.

<<1 As part of the group's study, the present Susquehanna emergency plan willbe re-evaluated.

Representatives of local government agencies, Civil Defense and the public willparticipate in the evaluation.

more

o

~

. included in the study will be developrr.ent of an evacuation plan modeled after the successful natural disaster evacuation plans and of a written statement of the roles and responsibilities of various public agencies in case of an emergency at the plant.

Implementation of an effective management control system to insure that the highest qualifications and training standards fo; Susquehanna personnel are maintained is the goal of the group evaluating personnel qualifications and training.

Specific actions to meet this goal are pr sently being developed.

PPRL's system, procedures and facilities for public communications are being evaluated by a fifth group.

Emphasis will be placed on determining and evaluating concerns expressed by customers, employees and the general public; and insuring that appropriate responses are developed and communicated.

Results of other task forces will serve as input for this communica-tion process.

Consideration also. willbe given to how to best coordinate and utilize aH available specialized services and resources existing within the company.

The importance of providing

accurate, consistent and timely information for the communities, employees and the news media will be stressed, not only for the period of construction and operation of the plant, but more

" importantly, to be able to react immediately to provide all necessary communication services in the event of an emergency.

05N099A1 NUCZZAR

SUS UEHANNASES TASK FORCES Implementation of the five-point program to reassess certain aspects of the Susquehanna nuclear plant project has begun.

Announcement of the program was made by PPRL President Robert K. Campbell following the accident at Ihe Three Mile Island nuclear plant.

It includes reviewing the. design of Susquehanna; rewxamining the radiation monitoring program; reassessing emergency procedures; reviewing qualifications and training programs of those people involved in the Susquehanna project and broadening the communication program to keep the public welf informed about the plant.

Serving on the team reviewing the Susquehanna design willbe Eugene A. Saltarelll, vice president of NUS Corp., Rockville, MD, chairman; Dr. Gordon E.

Robinson, professor of nuclear engineering, Pennsylvania State University, University Park; Hugh L. Campbell ill, technical director of EBECO Associates, Hazleton, and a member of PAL's Public Advisory Committee jPAC); James M.

Smith Jr., consulting environmental engineer, General Electric Co., San Jose, CA; Joseph B. Violette, manager-corporate quality assurance, Bechtel Power Corp., San Francisco, CA; Earle M. Mead, PAL's manager-nuclear plant engineering, and Howard W.Holland, senior project engineer, System Planning.

included in the team's review will be an assessment, when the Information Is available, ot the hardware failures, operating procedures and their consequences at Three Mile island and the capability of the Susquehanna plant to withstand similar events; an. examination of possible combinations of equipment failure and operator error which were not considered in the original plant design, but which should be considered as a result of the Three Mile island accident, and a review of the data available to the operator and how it is presented during an unusual operating condition, including an analysis of the ability of an operator to respond to multiple alarms and to initiate multiple manual actions to prevent unsafe operating conditions.

The group also will review the safeguards used at Susquehanna which assure that safety systems function properly and will re-examine the capability of plant systems to respond in a variety of emergencies including the presence of excess hydrogen, fission gases and contaminated water.

James R. Evans, supervisor-system operating computers, is heading the team reviewing the radiation monitoring program. That group will review the existing radiation monitoring programs'as detailed in the licensing documents for the plant and willdeveiop recommendatlons for a more comprehensive system.

Among the things to be considered willbe providing monitoring data at sites away from the plant to keep the plant staff, PPRL management, government and civil defense agencies informed in the event ot unusual radiation releases.

Also, the most
recent, statewf-the-art techniques fdr detection, continuous monitoring and sampling of radiation In the environment will be investigated.

Heading the group studying Susquehanna emergency procedures is Gerald S. Farber, supervisor-community planning. The group's goal is to establish an emergency plan that gives first consideration to public health and safety while meeting the Nuclear Regulatory Commission requirements for an operating license for the plant.

Lift U= For More

As part of the group's study, the present Susquehanna emergency plan will be re-evaluated.

Representatives of local government agencies, Civil Defense and the public willparticipate in the evaluation.

Included in the study will be development of an evacuation plan modeled after the successful natural disaster evacuation plans and of a written statement of the roles and responsibilities of various public agencies in case of an emergency at the plant.

The team evaluating Susquehanna personnel qualifications and training is led by William Scheffley, manager-system operation, assisted by Fred Kornet, manager-corporate administration.

Implementation of an effective management control system to insure that the highest qualifications and training standards for Susquehanna personnel are maintained is the goal of the group. Specific actions to meet this goal are presently being developed.

Under the direction of Leon L. Nonemaker, vice president-Division Operations, the company's

system, procedures and facilities for public communications are being evaluated.

Emphasis will be placed on determining and evaluating concerns expressed by customers, employees and the general public and insuring that appropriate responses are developed and communicated.

Results of'he other task forces will serve as valuable input for this communication process.

Consideration will, of course, be given to how to best coordinate and utilize all available specialized services and resources existing within.the company.

The importance of providing

accurate, consistent and timely information for the communities, employees ahd the news media mill be stressed not only for the period of constrqction and operation of the plant but more importantly, to be able to react immediately to provide all.necessary communica-

'tion services in the event of an emergency.

Coordinating the activities of the five groups is 'William L. Bohner, manager-Susquehanna project services.

'l Post on "SYSTEM NEWS"Section, Please Remove May 17 5/10/79

i