Responds to Generic Ltr 86-04, Policy Statement on Engineering Expertise.... Request for Changes to Tech Specs to Clarify Use of Individuals in Dual Capacity Will Be Submitted.Description of Current Training Program Encl
ML18030B374
Person / Time
Site: FitzPatrick Constellation icon.png
Issue date: 05/15/1986
From: Brons J
POWER AUTHORITY OF THE STATE OF NEW YORK (NEW YORK
To: Muller D
Office of Nuclear Reactor Regulation
Shared Package
ML18030B375 List:
References
GL-86-04, GL-86-4, JPN-86-23, NUDOCS 8605200342
Download: ML18030B374 (5)


Text

lf W.P ACCESSION NBR:

FAC IL:50-333 AUTH. NAME BRONS> J. C.

REC IP. NAME MUt LER> D. R.

REQULAT INFORMATION DISTRIBUTION STEM (R IDS) 8605200342 DOC. DATE: 86/05/15 NOTARIZED:

NQ DOCKET James A. FitzPatrick Nuclear Power Planti PoweT Autho 05000333 AUTHOR AFFILIATION New York Power Authority (formerly Power Authority af the S

RECIPIENT AFFILIATION BMR PT oJect Directorate 2

SUBJECT:

Responds to Generic Ltr 86-04 "Policy Statement on Engineering Expertise....

" Request for changes to Tech Specs to clarify use of individuals in dual capacity will be submitted. Description of current training program encl.

DISTRIBUTION CODE:

M003D COPIES RECEIVED: LTR ENCL SIZE TITLE: Operator Requalification Program NOTES:

EXTERNAL: 24X NRC PDR 02 RECIPIENT ID CODE/NAME BAR PD2 PD INTERNAL: NRR/DHFT/HFIB REC FILE 00 COPIES LTTR ENCL 1

1 1

1 1

1 1

1 RECIPIENT D="CODE/NA ABELSQNi NRR/DHFT/MTB RQNi LPDR NSIC 03 05 COP IES LTTR ENCL 1

1 1

1 1

1 1

1.

TOTAL NUMBER OF COPIES REQUIRED'TTR 10 ENCL 10

~

~ a l

e(

r 4 ~

r

~ 4 r, ~

123 Main Street White Plains, New York 10601 914 661.6240 NGRfYQTkPGW38F J.UiAoij'PJ May 15, 1986 JPN-86-23 John C. Brons Senior Vice President Nuclear Generation Director of Nuclear Reactor Regulation U.S. Nuclear Regulatory Commission Washington, D.

C.

20555 Attention:

Mr. Daniel R. Mullez, Director BWR Project Directorate No.

2 Division of,BWR Licensing

Subject:

James A. FitzPatrick Nuclear Power Plant Docket No. 50-333

Response

to Generic Letter 86-04 En ineerin Ex ertise on Shift

References:

1.

NRC Generic Letter 86-04, "Policy Statement on Engineering Expertise on Shift", dated February 13, 1986.

2.

NYPA letter, J.

P.

Bayne to D. B. Vassallo, dated September 7,

1984, (JPN-84-59),

provided a

description of the FitzPatzick Advanced Technical Training program.

3.

NRC letter, D. B. Vassallo to J.

P.

Bayne, dated December 11, 1984, transmitted a safety evaluation of the FitzPatrick Advanced Technical Training Program.

Dear Sir:

i Reference 1 requested information concerning engineering expertise on shift at the FitzPatrick plant.

The Authority has implemented a program to combine the Shift Technical Advisor and Senior Reactor Operatorl(SRO) in a dual-role.

The SRO is provided with advanced technical, training.

A detailed descziption of the current tzaining progzam is attached.

It is essentially the same as the program described in Reference 2 and approved by the NRC in Reference 3.

l The original program was conducted by the Memphis State University Center for Nuclear Studies.

However, Memphis State University has terminated its program.

The Authority then contracted with the State University of New York (SUNY) to conduct the current program for,FitzPatrick.

8b05200342 Sb0515 PDR ADOCK 05000333 V

PDR iL

~,

y ~

Both the original and current programs.

when combined with training provided for an SRO license, essentially constitute the equivalent technical portion of a Bachelor's Degree.

The 13 courses provided under the State program are the same as those provided in the Memphis program.

Both programs consist of 540 contact hours of instruction and an additional 540 hours0.00625 days <br />0.15 hours <br />8.928571e-4 weeks <br />2.0547e-4 months <br /> of structured self-study.

The State program consists of 48 credits as opposed to 41 credits in the Memphis program.

This difference is attributed to

.administrative diffezences between the two institutions, not differences between the programs.

The project courses originally'a part of. the Memphis program have been eliminated in the State program.

Under separate

cover, the Authority will submit a request foz changes to the Technical Specifications to clarify the use of individuals in a dual-role capacity.

Since some shifts will use a

separate STA, the proposed Technical Specifications would also preserve this option for the Authozity.

Should you or your staff have any questions regarding this

matter, please contact Mr. J.

A. Gray, Jr. of my staff.

Very truly yours, n

. Brons enioz Vice President uclear Generation CC:

Office of the Resident Inspecto U. S. Nuclear Regulatory Commis

'on P.

O. Box 136 Lycoming, N.Y.

13093 F.

Rowsome Division of Human Factors Technology U.

S. Nuclear Regulatory Commission Washington, D.

C.

20555

V