1 UNITED STATES NUCLEAR REGULATORY COMMISSION

+++++

MEETING ON STRATEGIC PROGRAMMATIC OVERVIEW OF THE NEW REACTORS BUSINESS LINE

+++++

THURSDAY, JANUARY 25, 2018

+++++

ROCKVILLE, MARYLAND

+++++

The Commission met in the Commissioners' Hearing Room at the Nuclear Regulatory Commission, One White Flint North, 11555 Rockville Pike, at 10:04 a.m., Kristine L. Svinicki, Chairman, presiding.

COMMISSION MEMBERS:

KRISTINE L. SVINICKI, Chairman JEFF BARAN, Commissioner STEPHEN G. BURNS, Commissioner ALSO PRESENT:

ANNETTE VIETTI-COOK, Secretary of the Commission MARGARET DOANE, General Counsel

2 NRC STAFF:

FRANK AKSTULEWICZ, Director, Division of New Reactor Licensing MICHAEL JOHNSON, Deputy Executive Director for Reactor and Preparedness Programs BILL JONES, Director, Division of Construction, Region II TIMOTHY MCGINTY, Director, Division of Construction Inspection and Operational Programs JOHN MONNINGER, Director, Division of Safety Systems, Risk Assessment, and Advanced Reactors VONNA L. ORDAZ, Deputy Director, Office of New Reactors

3 1 PROCEEDINGS 2 10:04 a.m.

3 CHAIRMAN SVINICKI: Well, good morning 4 everyone. I call this meeting of our Commission to order.

5 Today, we will receive a briefing from the NRC staff 6 Regarding Strategic Considerations Associated with the New 7 Reactors Business Line.

8 This is one in a series of business line meetings that 9 we sprinkle throughout the course of the year. I derive a lot of value 10 from them as a Member of the Commission because it allows us to 11 take some look at different aspects.

12 There's always a tremendous amount of activity in 13 each business line, but the staff is allowed to highlight certain 14 accomplishments and also work that's very active.

15 And then, going forward, challenges and other 16 strategic considerations.

17 And, the Commission is given the opportunity to ask 18 about that or any other topics related to the business line that they 19 would like.

20 So, again, I find a good programmatic value in these 21 meetings.

22 Before we begin, I will ask if my colleagues have any 23 opening comments they would like to make?

24 (No audible response) 25 CHAIRMAN SVINICKI: No? Hearing none, again, 26 we will hear from one panel today comprised of NRC staff members.

4 1 And, to lead off, I will turn over to acting in the role of 2 the Executive Director for Operations today is the Deputy EDO Mike 3 Johnson.

4 Michael, please proceed.

5 MR. JOHNSON: Thank you.

6 Good morning, Chairman and Commissioners.

7 Today, representatives from the Office of New 8 Reactors in Region II will brief you on the major activities in the New 9 Reactor Business Line.

10 The business line is at a transition point. We've 11 completed our review of the active combined license application that 12 are before us.

13 We're in the early phases of a review of the first small 14 modular reactor application.

15 We're making progress on our review of an early site 16 permit and design -- and a design certification application, specifically, 17 I'm referring to the APR1400.

18 In parallel, we're preparing for licensing the next 19 generation of new reactors that being the advanced non-light water 20 reactors.

21 In the area of oversight with, certainly with support 22 across the Agency, the New Reactors Business Line completed an 23 effective and timely action to adjust our workload and resources in 24 response to a significant change.

25 That is, the VC Summer licensee cancelling their 26 construction project.

27 In addition, we continue to effectively oversee

5 1 construction and conduct reviews of license amendment requests 2 associated with the new units at Vogtle.

3 We're also preparing to transition to operations for the 4 new Vogtle units. And, that'll be a first for plants licensed under the 5 Part 52 process.

6 You're going to hear in this briefing about our 7 accomplishments, accomplishments of the new reactors program and 8 our plans going forward.

9 And, as we've approached each endeavor, we've 10 explored and implemented process improvements. You'll hear about 11 those. And, those are intended to make our processes more efficient 12 and more safety focused.

13 I also hope you take from this briefing our focus on 14 agility and resourcefulness. I think the reactor team -- the new 15 reactor team has been agile and resourceful.

16 And, when I say team, I'm including all of our partners 17 across the Agency. And, we've done that in meeting our program 18 goals with a strong focus on safety and a clear vision with plans for 19 the future.

20 Slide two, please?

21 For today's briefing, for NRO, Vonna Ordaz, who is 22 the Deputy Director for the Office of New Reactors is going to highlight 23 the business line accomplishments from the past year.

24 Frank Akstulewicz is going to discuss the Large Light 25 Water Reactor and Small Modular Reactor Licensing activities.

26 John Monninger will discuss progress and preparing 27 for Advanced Reactor Licensing.

6 1 Tim McGinty will highlight activities in the areas of 2 Operator Licensing, Inspections, Tests, Analyses and Acceptance 3 Criteria, known as ITAAC, vendor inspections and transition to 4 operations.

5 And then, finally, Bill Jones from Region II will 6 summarize construction oversight and inspection activities.

7 And so, now, I'll turn it over to Vonna to begin our 8 briefing.

9 MS. ORDAZ: Thank you, Mike.

10 Good morning, Chairman and Commissioners.

11 We appreciate the opportunity to brief you today on 12 the New Reactors Business Line.

13 As Mike mentioned, our briefing will provide an 14 overview of the new reactor program accomplishments and progress 15 of ongoing activities.

16 Next slide, please?

17 I would like to open by acknowledging the New 18 Reactors Business Line staff, the supervisors and executives 19 supporting the program's mission as well as our inspectors in the field.

20 I'd also like to note that the business line successes 21 would not be possible without the contributions from all of our 22 business line partners.

23 Over the last year, we made process in support of our 24 core mission of enabling the safe, secure and environmentally 25 responsible use of nuclear power and meeting our nation's future 26 energy needs.

7 1 We completed several milestones in our ongoing 2 large light water reactor design reviews and made progress in 3 reviewing the first small modular reactor design.

4 The business line also continue to ensure that the 5 AP1000 units are constructed in accordance with the licenses and the 6 NRC's regulations.

7 We accomplish this work with an emphasis on more 8 efficient and safety focused reviews that effectively utilize our 9 resources.

10 While we have met many of our goals, we recognize 11 that much work remains to complete our current workload this fiscal 12 year and to be fully prepared to review future applications.

13 In accomplishing its mission, the New Reactors 14 Business Line has focused on actively engaging and communicating 15 with the industry and external stakeholders.

16 We use numerous public meetings, workshops, 17 written communications to ensure that expectations and feedback are 18 clearly communicated and that we understand the industry's plans and 19 positions.

20 We also continue to see benefits from our interactions 21 with all of our international counterparts.

22 Next slide, please?

23 We are continuously looking at ways to improve the 24 effectiveness and efficiency of our reviews through innovative 25 approaches.

26 We have identified ways to improve our review 27 processes such as through an enhanced use of audits, which reduce

8 1 or eliminate the need for RAIs, more stringent measures by metrics 2 and implementing an enhanced safety focused review for the NuScale 3 design application.

4 We've implemented enhancements to our processes 5 such as the operator licensing enhancements, improvements to the 6 way we evaluate and inspect ITAAC closure notifications and the 7 establishment of more stringent metrics for tracking ITAAC 8 completions and also licensing actions.

9 We understand that a critical aspect of effective and 10 efficient reviews is early resolution of key issues.

11 We began early in the NuScale review by identifying 12 technical issues during the acceptance review. As critical issues 13 have been identified, we've developed plans on schedule for 14 resolution.

15 Also, a critical part of our preparation for advanced 16 reactor applications has been the identification and resolution of 17 advanced reactor policy issues.

18 Through enhanced outreach to applicants and 19 stakeholders, we are able to better schedule our work, anticipate 20 complex issues and understand the issues.

21 The new reactor's management team meets 22 frequently with applicants and licensees to discuss schedules and also 23 challenges.

24 We've also been diligent about reaching out to 25 stakeholders regarding advanced reactor preparations through our 26 routing public meetings.

27 These interactions ensure that the industry is aware

9 1 of the expectations and will make for more complete applications in 2 the future.

3 You'll hear more about each of these approaches 4 later in the presentation.

5 Next slide, please?

6 The New Reactors Business Line is continuing to 7 prepare for changes in our workload, changes to the industry and also 8 changes to the NRO organization to address the associated workload.

9 Changes to the industry's plans require us to be 10 continually agile. As we look forward, we are actively preparing for 11 future new reactor applications that include advanced reactor designs.

12 We've positioned ourselves to conduct those reviews 13 efficiently through various framework documents that John will share 14 during his presentation.

15 At the same time, we're implementing detailed plans 16 for the transition of the first units from construction to operations.

17 And, we're beginning to make plans for the merger of 18 NRR and NRO within the next few years in coordination with NRR.

19 I'll now turn the presentation over to Frank 20 Akstulewicz to discuss the large light water and small modular reactor 21 licensing.

22 Frank?

23 MR. AKSTULEWICZ: Slide seven, please?

24 Thank you, Vonna.

25 Good morning, Chairman and Commissioners.

26 As you're aware, this past fiscal year, we have seen 27 changes in the nuclear industry that, by extension, have led to

10 1 reshaping of the new reactor licensing construction oversight work 2 within this business line.

3 Even as the regulatory landscape has been evolving, 4 the New Reactor Business Line has continued to make substantial 5 progress in completing its ongoing licensing activities and have been 6 effective and efficient at meeting our safety and licensing mission.

7 Next slide, please?

8 I want to take a few moments to summarize some of 9 the business line accomplishments this past fiscal year before we 10 discuss where the new light water reactor licensing activities are 11 headed in the coming year and beyond.

12 During this fiscal year, NRO issued a combined 56 13 license amendments to the Vogtle and Summer licensees on the 14 schedule that always supported construction activities.

15 Even with the decision by SCANA to stop construction 16 at the Summer site and by Duke Power to suspend the Levy and Lee 17 projects in Florida and South Carolina, respective, NRO has an active 18 inventory of 33 license amendment requests that are tied to Vogtle 19 construction efforts.

20 We have instituted a process to track the timeliness of 21 our licensing activities and we will discuss that later in this 22 presentation.

23 The business line completed its safety and 24 environmental reviews for the Turkey Point Combined Licensed 25 Application, successfully completed the mandatory hearing this past 26 December 12th and look forward to issuing the licenses for Units 6 27 and 7 should the Commission determine it is acceptable to do so.

11 1 We also successfully completed the mandatory 2 hearing and issued the combined license to Virginia Electric Power 3 Company for North Anna Unit 3 on June 2nd, of 2017.

4 Next slide, please?

5 The picture shows a bird's eye view of the proposed 6 Clinch River site. The early site permit and environment and safety 7 reviews for the Clinch River site are proceeding on or are slightly 8 ahead of their public milestone schedules.

9 Interactions with the applicant have been frequent 10 and effective at identifying and resolving licensing questions.

11 We met the Phase A safety evaluation review 12 milestone which is preparing the preliminary safety evaluation report 13 and issuing Requests for Information in just five months.

14 And, we are currently ahead of our public milestone to 15 issue our draft environmental impact statement by June of 2018.

16 You may recall that the KHNP application was the first 17 design certification for which the staff established a 42 month review 18 schedule.

19 While we continue to exercise strong management 20 attention to completing the safety evaluation with no open items, 21 KHNP has been challenged to provide the necessary information to 22 resolve some open items on the schedule that we would need -- that 23 would be necessary to meet the public milestone.

24 As such, we issued a letter to KHNP that extended 25 the public milestone for completing the safety evaluation by three 26 months.

27 Since that letter, submittals from KHNP have not

12 1 achieved the progress hoped for in resolving remaining technical 2 matters.

3 As such, we have implemented a strategy that still 4 hopes to preserve the overall 42 month schedule, but will require the 5 staff to establish new milestones for completing the safety evaluation 6 and meeting with ACRS.

7 The success of this strategy hinges on submittals 8 arriving now through mid-March.

9 Next slide, please?

10 This past March, the staff accepted for review the 11 NuScale design certification application. The safety review is 12 scheduled to be completed in 42 months and the staff has completed 13 about 80 percent of the preliminary safety evaluations with open items 14 to date.

15 To this point, we've held over 49 public meetings and 16 conducted over 30 technical audits as part of this review.

17 We have used the lessons learned from earlier 18 reviews to employ a proactive approach to engage the applicant.

19 And, we have identified about 20 technical topics that will require 20 elevated management attention because they could adversely impact 21 the review schedule.

22 NRC's senior managers meet with the NuScale 23 executives on these topics quarterly. These meetings provide 24 executives from both organizations the opportunities to discuss review 25 progress, to identify emerging issues and to establish priorities and 26 time lines for the resolution of regulatory topics to keep the project 27 review on schedule.

13 1 Next slide, please?

2 The New Reactor Business Line is always looking 3 proactively for ways to increase the effectiveness and efficiency of our 4 reviews.

5 To better coordinate our licensing activities at the 6 Vogtle site, the business line established quarterly scheduling and 7 status meetings between NRC division level executives and 8 executives from Southern Nuclear Company to monitor progress of 9 licensing actions tied to construction at the site.

10 These so-named licensing activities readiness 11 meetings provide a unique opportunity for both the NRC and Southern 12 Nuclear Company management to be both tactical and strategic in 13 establishing priorities and schedules for resolving topics that are tied 14 to construction at the Vogtle site.

15 In mid-2017, the NRO management noticed a 16 substantial upward trend in the average time to complete Vogtle 17 license amendments and implemented a new internal process to 18 better track license amendment reviews related to the Vogtle project.

19 Under this process, license amendments that are 120 20 days or more in review are discussed to determine what elevated 21 management attention is needed to support a goal of completing 22 amendment requests in 180 days.

23 We have incorporated many of the review lessons 24 learned into our review activities for the active design certification and 25 the early site permit applications.

26 Our initiative last year to improve the focus of 27 Requests for Additional Information has improved the safety focus of

14 1 those requests, provided the applicants greater clarity on the 2 information the staff needs to reach its safety findings and has 3 reduced the need for second and third round follow up questions.

4 We are also using regulatory audits earlier in the 5 process to better inform the staff about the issues underlying the 6 tendered application and, therefore, better focus the staff's Requests 7 for Additional Information to those that are directly necessary to 8 support the staff's safety findings.

9 Finally, NRO has implemented its enhanced safety 10 focus review initiative. This initiative provided a review tool that the 11 staff could use to optimize the NuScale design review.

12 The tool included a framework for the reviewers to 13 place more or less emphasis on selected aspects of the design based 14 on considerations such as the novelty of the design features, 15 regulatory compliance, risk insights, relationship to defense in depth 16 and the relationship to safety margins.

17 The framework does not eliminate NRC requirements 18 or obviate the need to review the design, including the quality, 19 accuracy and completeness of an application.

20 Using this initiative, the staff has optimized its reviews 21 in areas such as transient and accident analysis, thermal hydraulic 22 design, instrumentation and control system architecture and operator 23 licensing, to name just a few.

24 But, there is still a way to go before we can achieve a 25 consistent application of the framework.

26 We will continue to employ this initiative as we resolve 27 questions and open items during the NuScale review. And, at the

15 1 appropriate time, we'll reflect the lessons learned in revised guidance 2 and simplification of the framework tool.

3 Next slide, please?

4 As we have for the past ten years, the New Reactor 5 Business Line is actively engaged with the industry to assess the 6 potential licensing workload so that we can be prepared to meet our 7 licensing mission and the applicant's needs.

8 Last month, issued Risk 2017-08 entitled Process for 9 Scheduling and Allocating Resources for Fiscal Years 2020 through 10 2022 for the review of new licensing applications for light water 11 reactors and non-light water reactors, to promote early communication 12 between the NRC and potential applicants related to future licensing 13 applications.

14 Using information from previous Risk responses and 15 our annual business plan meetings, we have current and potential 16 applicants, we don't expect to receive applications for a new light 17 water reactor combined license, early site permit or design certification 18 in the near term.

19 Nonetheless, we have a large baseload of work 20 resulting from a steady flow of license amendments related to the 21 Vogtle construction efforts as well as the ongoing reviews of the 22 KHNP APR1400 design certification, the NuScale design certification, 23 the MHI-US-APWR design certification, the GE -- I'm sorry, the 24 General Electric-Hitachi ABWR renewal and the TVA Clinch River 25 early site permit applications.

26 The business line stands ready to support the license 27 transfer reviews for the Bellefonte Units 1 and 2 should it be submitted

16 1 and to support licensing activities should the Bellefonte efforts move 2 forward.

3 Finally, the business line is prepared to support 4 pre-application interactions with the Utah Associated Municipal Power 5 Systems, or UAMPS, and TVA as they evaluate their respective plans 6 for future COL applications.

7 And, with Blue Castle Holdings for a COL application 8 for a new reactor project in the Western U.S.

9 The business line will continue to be involved with 10 Agency supported international efforts on licensing, construction and 11 operations topics on both large light water reactor and small modular 12 reactors via the multinational design evaluation program and other 13 regulators, activities and forums.

14 This concludes my portion of the presentation. John 15 Monninger will now discuss licensing activities for advanced reactors.

16 MR. MONNINGER: Thanks, Frank.

17 Good morning, Chairman and Commissioners.

18 I'm pleased to be here to provide an overview of NRC 19 activities to prepare for the potential licensing of advanced reactors 20 with a focus on non-light water reactors.

21 There continues to be significant stakeholder interest 22 in advanced reactors. As such, we are proactively planning and 23 updating our regulatory framework to be responsive to the needs of 24 developers and applicants.

25 As I'll discuss in my presentation, we've made 26 substantial progress this past year. And, we are continuing to do so 27 this year.

17 1 Next slide, please?

2 To prepare to review and regulate non-light water 3 reactors, this past year, we issued the NRC vision and strategy 4 entitled Safely Achieving Mission Readiness, Safely Achieving an 5 Effective and Efficient Non-Light Water Reactor Mission Readiness.

6 In it, we describe our goals, objectives and strategies 7 necessary to achieve this mission readiness.

8 To do this, we developed implementation action 9 plans, or what we call IAPs, that define the near-term, mid-term and 10 long-term activities.

11 Following significant stakeholder interactions including 12 the NRC's Advisory Committee on Reactor Safeguards, we issued the 13 final IAPs this past July.

14 We are now executing our vision and strategy through 15 the IAPs and made incremental progress consistent with available 16 resources this past year.

17 Next slide, please?

18 For today's discussion, I'll focus on the near-term 19 IAPs. We have six strategies under the IAPs, as noted by the blue 20 boxes across the top.

21 Efforts are underway under each of these strategies 22 and under each strategy and I'll highlight a few of them.

23 For example, Strategy 2 involves modifying or 24 developing sufficient computer codes and tools to perform regulatory 25 reviews.

26 Our efforts this past year, which have been led by the 27 Office of Nuclear Regulatory Research have focused on evaluating

18 1 the capabilities of existing codes to inform the non-light water reactor 2 code selection process.

3 Strategy 3 is focused on developing guidance for 4 flexible regulatory review processes including conceptual design and 5 staged review processes. I will discuss this further on the next slide.

6 Strategy 4 entails facilitating development of the 7 industry codes and standards needed to support the non-light water 8 reactor review cycle.

9 We are participating with standards development 10 organizations to develop consensus codes and standards such as 11 ASME Section 3 Division V for high temperature materials.

12 Strategy 5 is about the identification and resolution of 13 technology inclusive policy issues that could impact the regulatory 14 reviews of non-light water reactors.

15 We are working with our stakeholders to identify and 16 prioritize the key issues. I'll discuss some of the higher priority issues 17 on a later slide.

18 Progress is underway in all six strategies. I've circled 19 Strategies 3 and 5 to highlight the priority we are placing upon them 20 based upon stakeholder feedback and recommendations from our 21 ACRS.

22 Many of these activities are focused on advancing 23 risk-informed and performance-based approaches and the resolution 24 of key policy issues.

25 Next slide, please?

26 Under Strategy 3, we developed the regulatory review 27 roadmap for non-light water reactors. This document describes the

19 1 flexible end stage licensing processes within NRC's current regulatory 2 framework.

3 This flexibility accommodated designers and 4 applicants with a range of financial, technical and application 5 readiness.

6 It is important to recognize that, while some non-light 7 water reactor designs are in the pre-conceptual design stage, others 8 are nearly in the final stages of design.

9 Designer plans for the deployment of non-light water 10 reactor designs might include multiple projects including decisions on 11 research and test reactors, first of a kind large-scale plants and 12 subsequent commercial plants.

13 Their long-term deployment strategies might include 14 combinations of licensing under both Part 50 and Part 52.

15 Our review and licensing processes are flexible and 16 support interactions relating to this wide variation in design 17 development.

18 The timing and scope associated with regulatory 19 interactions are intended to align with other aspects of technology 20 development, including plant design, research and development, 21 finance, public policy and the fuel cycle.

22 As an example, issues related to the use of higher 23 assay, low-enriched uranium and fuel cycle facilities have been 24 discussed with the staff during several recent meetings.

25 We will continue to work with each developer and 26 applicant to establish a mutually agreeable regulatory engagement 27 plan that includes defined scope and level review, desired outcomes,

20 1 focus areas, estimated review costs and review schedule.

2 The roadmap also includes updated guidance on 3 testing needs for designs which differ significantly from light water 4 reactors and the potential use of a prototype plant demonstrate the 5 performance of key safety features.

6 Next slide, please?

7 The staff is focused on resolving key issues early.

8 This includes both technical issues and potential policy issues.

9 For the past couple years, we have been working on 10 a project with the Department of Energy to develop non-light water 11 reactor design criteria.

12 The NRC's general design criteria in Appendix A to 13 Part 50 are light water reactor specific and they are a key aspect of 14 licensing any nuclear power plant.

15 We are adapting these criteria to meet the unique 16 needs of non-light water reactor designs.

17 Last year, we issued Draft Reg Guide DG-1330 18 entitled Guidance for Developing Principle Design Criteria for 19 Non-Light Water Reactors for public comment.

20 We are on schedule for issuing the final Reg Guide 21 this spring.

22 Another key activity we are continuing this year is 23 working with stakeholders to develop guidance for a risk-informed and 24 performance-based approaches for licensing basis event selection, 25 the use of probabilistic risk assessments, the maintenance of 26 defense-in-depth and the classification of system structures and 27 components.

21 1 A significant issue identified during interactions with 2 stakeholders is that identifying is defining the appropriate performance 3 characteristics for the design features serving to retain radionuclides.

4 This is often referred to as functional containment performance 5 criteria.

6 We have been interacting with stakeholders and are 7 developing a proposal for a risk-informed and performance-based 8 approach to be provided to the Commission later this year.

9 Another priority issue identified during interactions 10 with stakeholders is establishing the appropriate security 11 requirements. The design and behavior of non-light water reactors 12 can be significantly different from large light water reactors in terms of 13 the potential for core damage and radiological releases.

14 As such, we are assessing the merits of different 15 physical security requirements. We have held a series of public 16 stakeholder meetings. We are assessing the feedback received and 17 will provide a recommendation and path forward later this year.

18 Next slide, please?

19 The non-light water reactor landscape is evolving with 20 a broad range of domestic and international stakeholders.

21 The NRC continues to actively interact with them as 22 we prepare for potential applications in the next two to four years.

23 The staff has received responses to our 2016 24 regulatory information summary that we used to inform our budgeting 25 process.

26 A total of five non-light water reactor developers 27 expressed their intent to begin regulatory interactions. We expect

22 1 updated responses in the near future.

2 The nuclear industry has established technology 3 working groups around liquid metal fast reactors, high temperature 4 gas reactors and molten salt reactors.

5 The NRC activities are likewise organized by these 6 groupings.

7 The pace of NRC's readiness activities is dependent 8 upon budget authority and we continue to prioritize our efforts to make 9 the most efficient use of available resources.

10 We closely monitor the Department of Energy 11 activities such as grants to non-light water reactor developers and 12 potential plans for a new test reactor as they will impact the pace and 13 direction of technology development.

14 Next slide, please?

15 As noted previously, we've received responses from 16 five developers including Oklo, Transatomic, Terrestrial Energy, 17 Xenergy and TerraPower. The designs are listed on this slide along 18 with the power level and technology being pursued.

19 Our most significant recent interactions have been 20 with Oklo. We are continuing pre-application interactions with them, 21 including the review of a quality assurance program report and 22 technical reports they submitted on core design, risk assessment and 23 source term.

24 For Oklo, we are implementing the flexible and staged 25 regulatory review process described in our regulatory roadmap. We 26 use this to align industry resources with the needs of the developer.

27 We are using a core review team concept to provide

23 1 stability and consistency in the Oklo review while ensuring efficient 2 and agile use of the available NRC resources.

3 The NRC's core review team is a group of staff 4 dedicated to addressing non-light water reactors issues. It is 5 comprised of staff from the Office of New Reactors, Nuclear Reactor 6 Regulation, Nuclear Regulatory Research, Nuclear Security and 7 Incident Response and the Office of the General Counsel.

8 This approach has been working successfully for the 9 Oklo pre-application review and we plan to continue this approach to 10 support future regulatory interactions with non-light water reactor 11 developers.

12 Next slide, please?

13 Vital to our success in updating our regulatory 14 framework is interacting with and seeking stakeholder feedback at all 15 steps along the way.

16 We held three workshops jointly with the Department 17 of Energy, the most recent one being last April in which we reached a 18 wide variety of stakeholders.

19 We have now transitioned to periodic stakeholder 20 meetings about every six weeks to discuss ongoing activities and to 21 facilitate stakeholder input.

22 We see these meetings extending indefinitely given 23 the broad number and range of readiness activities we have planned.

24 We're all supporting the Department of Energy's 25 gateway for accelerated innovation and nuclear initiative. We 26 communicate frequently with DOE to keep them apprised of our 27 activities and to get information to inform our plans.

24 1 Lastly, we continue to engage with international 2 stakeholders. For example, the NRC chairs the group of the Safety 3 of Advanced Reactors through the Nuclear Energy Agency.

4 In this forum, we share information on non-light water 5 reactor safety and regulatory issues with other international regulators.

6 We also keep apprised of the activities of the 7 Generation for International Forum.

8 This completes my remarks. Tim McGinty will now 9 provide a presentation of NRC's construction inspection program.

10 MR. MCGINTY: Thanks, John.

11 Good morning. I'll cover four main areas today.

12 First will be enhancements to the operator licensing program.

13 Next, I'll update you on how we are implementing 14 improvements in our processing of ITAAC Closures Notices, or ICNs.

15 Then, I'll discuss the transition to operations and 16 describe what we are doing to have the Agency ready for oversight as 17 the plants under construction become operating plants.

18 And finally, I'll discuss the safety benefits being added 19 by the Agency's vendor inspection program and changes to the 20 vendor inspection center or expertise organizational structure.

21 Next slide, please?

22 As an overview, I want to emphasize that we are 23 focused on executing on schedule and using our resources wisely.

24 We are paying appropriate attention to project schedules and focusing 25 on adjusting our emphasis and expertise to support those schedules.

26 We are aiming for the early resolution of policy issues 27 that ultimately supports timely decision making.

25 1 We also solicit, consider and value external feedback, 2 external stakeholder feedback as an essential part of our work 3 processes.

4 Next slide, please?

5 As you will recall, lessons were learned from the cold 6 licensing efforts at the AP1000 projects for VC Summer and Vogtle, 7 including the processes for licensees to apply for Commission 8 approved simulator status.

9 We have embarked on an important team effort to 10 address operating licensing and plant reference simulator issues 11 guided by two light cold licensing charters.

12 I'll note that part of the focus, at this point, is to ensure 13 that the program will be improved for future new designs. This is a 14 highly collaborative effort with NRO, Region II and NRR in 15 consultation with OGC.

16 It also includes vital engagement with external 17 stakeholders.

18 The charters are resolving lessons learned captured 19 during the initial operating licensing activities with the AP1000 20 licensees related to examination development, experience 21 requirements, proficiency training and simulator readiness.

22 One charter involves near-term actions necessary for 23 the NRC to issue operating licenses to applicants at Vogtle as well as 24 translating the experience and insights gained from completed 25 activities at Vogtle and VC Summer into durable guidance for future 26 cold licensing activities.

27 The second charter specifically relates to licensee and

26 1 NRC staff interactions to classify, declare and approve plant reference 2 simulators and Commission approved simulators to support operator 3 licensing, training and examinations.

4 The picture on the top is the AP1000 simulator.

5 Recommendations for the near-term tasks were proposed by the staff 6 within the last month. Recommendations in response to generic 7 long-term tasks are scheduled for May of 2018.

8 Together, the overall goal of our teamwork on both 9 charters is to establish interim guidance and the steps necessary to 10 improve the framework and structure of the cold licensing process for 11 future use.

12 For example, we have actively engaged with NuScale 13 to determine how to develop, administer and evaluate operator 14 licensing examinations for SMRs.

15 The picture on the bottom shows NRO, Region II and 16 TTC staff at NuScale's control room simulator during a visit in August 17 of 2017 where we discussed the development of knowledge and 18 abilities catalogues for NuScale SMR technology and made a 19 preliminary assessment of the operator licensing process.

20 Next slide, please?

21 As you would expect, the number of ICNs received for 22 Vogtle's Units 3 and 4 have increased since our last briefing. As of 23 the end of calendar year 2017, we have verified 123 ICNs for Vogtle.

24 Those are shown as conditionally verified and 25 unconditionally verified slices of the pie chart.

26 Also, at the end of calendar year 2017, we had eight 27 ICNs under the review process.

27 1 Note that the gray area in the above pie chart signifies 2 ITAAC notifications that have not been received yet. And, is by far, 3 the largest segment. I'll speak to that a little more later in my 4 presentation.

5 Also, note that the number of ITAAC per unit is being 6 further evaluated by an ongoing ITAAC consolidation license 7 amendment.

8 Last year, we discussed the implementation of 9 reviewing early uncompleted ITAAC notification, or UIN submittals.

10 We began official reviews of UINs in October of 2016 11 and have found that the UNI review process provides earlier 12 communication to public stakeholders and allows for prompt 13 identification of potential issues related to ITAAC completion.

14 Also, is reflected in this pie chart, at the end of 15 calendar year 2017, 157 UINs have been accepted to date and we 16 had 12 UINs under review.

17 In an effort to make the ICN reviews more timely, the 18 staff is implementing a streamlined feedback process to resolve 19 issues with ITAAC notifications during a weekly public meeting with 20 licensees and interested stakeholders.

21 Next slide, please?

22 In the spring of 2017, the ITAAC team conducted a 23 demonstration project to evaluate the readiness and reliability of the 24 ITAAC inspection and verification processes in preparation for the 25 large number of ITAAC notifications expected towards the end of 26 construction.

27 The final report from the demonstration project which

28 1 was issued in 2017 included recommendations for enhancing external 2 stakeholder interactions, improving NRC process guidance and the 3 creation of performance monitoring information dashboards.

4 We then issued an action plan on September 29th of 5 2017 with deliverable milestones to implement these 6 recommendations. Of course, as we continue to work through the 7 action planning and complete the recommendations, we'll continue to 8 identify new issues and challenges and we'll focus on resolving them.

9 One efficiency that I will highlight is that, in 10 anticipation of a potential increase in ICNs submitted near the end of 11 construction, several additional NRO staff have successfully 12 completed and are maintaining cross qualification as ICN reviewers.

13 Should the notification submitted exceed the review 14 capacity of the core review team, the additional review staff will be 15 ready and available to meet the challenge.

16 More recently, on December 12th of 2017, we held a 17 public ITAAC tabletop with Southern Nuclear Company to discuss the 18 status of the actions that came out of the demonstration project, 19 provide a better understanding of the NRC's ITAAC review and 20 inspection processes by focusing on specific and complex ITAAC 21 scenarios.

22 And our processing of the ICNs and engage on the 23 full suite of steps associated with the staff's 10 CFR 52.103(g) finding 24 which will occur once all ITAAC have been verified as completed.

25 Moving forward, we expect the rate of submittals to 26 steadily increase for both units at Vogtle and we are prepared by 27 having the necessary resources, processes and procedures in place.

29 1 We are going to be highly engaged this year and next 2 as Vogtle recently informed us that they plan to submit all ITAACs 3 either as ICNs or UINs by the end of calendar year 2018.

4 Next slide, please?

5 To highlight another element of our action plan, a 6 performance dashboard has been developed to support our ITAAC 7 closure verification program.

8 The dashboard depicts performance measures for 9 ongoing ICN and UIN reviews for different aspects of the process.

10 Our performance monitoring allows for the early 11 identification of potential problem areas.

12 I will note that close coordination with the Vogtle 13 construction schedule and the completion of inspection activities is 14 crucial for overall timely ICN review completions.

15 For transparency, key enhancements to the public 16 websites for the Vogtle units under construction have also been 17 completed. And, they now provide a convenient portal for 18 stakeholders to find ITAAC hearing related information for any 19 particular unit, including the ITAAC hearing procedures, licensing 20 activities and updates to the ITAAC status report which provide 21 information on the status of the staff's review for each ITAAC with 22 links to all relevant information for that ITAAC.

23 Next slide, please?

24 We were also focusing on making sure that we are 25 ready for the next phases of construction and the transition from 26 construction to operations.

27 Previously, the staff published a report which

30 1 identified and assessed 21 readiness issues necessary to support the 2 transition of new reactors from construction to operation.

3 We developed an implementation plan, considered 4 stakeholder comments and we issued the plan on November 24th of 5 2017. The implementation plan integrates all of the readiness issues 6 and describes the various points in time that the transition of licensing 7 and regulatory oversight functions will occur.

8 It also clarifies new reactor operational regulatory 9 oversight and licensing responsibilities through the transfer from NRO 10 to NRR and includes considerations for the future NRR/NRO merger 11 and the issuance of 10 CFR 52.103(g) implementing procedures.

12 Next slide, please?

13 The vendor inspection program continues to meet our 14 safety and programmatic objectives. We continue to verify the 15 effective implementation of vendor quality assurance programs.

16 We are verifying that licensees are providing effective 17 oversight of their supply chain and we continue to focus on the 18 adequacy of commercial grade dedication of safety related 19 components.

20 Our metric for the number of vendor inspections last 21 year was 35, which we exceeded as we completed 37.

22 We focused on effectiveness and identifying which 23 vendors to inspect, such as those supplying the most safety significant 24 AP1000 components and vendors performing activities that are 25 performed as part of ITAAC closure.

26 We also carefully chose our inspection teams to help 27 ensure that the efficient use of resources. For example, many

31 1 inspection teams consisted of qualified vendor inspectors 2 supplemented by subject matter experts.

3 We also made a point of leveraging Region II staff 4 and inspections of vendors performing ITAAC related work.

5 The vendor inspections center of expertise also 6 supports the operating reactor program. And, in 2017 included 7 inspections as part of SONGS lessons learned and of the carbon 8 segregation issue for forging manufactured by AREVA Creusot Forge 9 and supplied to U.S. nuclear power plants.

10 I will note that as an outcome of the AREVA Creusot 11 Forge inspection, we did not identify any information that challenged 12 the overall determination that the safety significance of this issue to 13 the U.S. fleet appears to be negligible.

14 Next slide, please?

15 Finally, I will cover how we are adapting to the 16 decrease in new reactor fabrication and construction activities on the 17 vendor inspection COE.

18 We performed a methodical evaluation of the current 19 and future slowdown and fabrication and construction activities 20 including the SCANA announcement to cease construction on VC 21 Summer Units 2 and 3.

22 And, as a result, we are implementing the following 23 program changes.

24 The number of planned vendor inspections has been 25 reduced from 35 in fiscal year '17 to 25 in fiscal year '18 and 20 in 26 fiscal year '19.

27 This will return us to the inspection planning level that

32 1 we were at prior to the start of new reactor construction.

2 We implemented associated reductions in vacancies 3 and staffing levels in NRO.

4 And, we are reducing the number of branches that 5 make up the vendor inspection COE from three down to two.

6 I am confident that these changes will allow us to 7 continue to meet our safety and programmatic objectives.

8 That is my presentation and I will now turn it over to 9 my colleague in Region II, Bill Jones.

10 MR. JONES: Thank you, Tim.

11 Good morning, Chairman, Commissioners.

12 The goals of the NRC inspection program are to 13 ensure that the inspections at the Vogtle site are timely, with respect 14 to the licensee's construction schedule, are coordinated with the 15 licensee's ITAAC closure notices and that we take advantage of 16 opportunities to move inspection activities forward to mitigate potential 17 high inspection demand periods.

18 Today, I will tell you how we are meeting these goals.

19 In addition, we are prepared for the initial test 20 program inspections, particularly with the digital instrumentation and 21 control and first plant only and first three plant only testing.

22 We continue to support vendor inspection activities 23 and inspect ITAAC related items occurring at a vendor facility.

24 We remain very active in international activities 25 including support of multinational vendor inspection and the inspector 26 exchange rotations to the SEM and AP1000 site.

27 Next slide, please?

33 1 There was a prompt assessment of the NRC"s, and in 2 this case, the Division of Construction Oversight's inspection 3 resources needed to implement the construction inspection program 4 following the July 31st announcement that Summer Units 2 and 3 5 construction would not be continued.

6 The resource projections were informed by the 7 inspection schedule for Vogtle Units 3 and 4 construction activities.

8 This assessment identified a reduction of 16 9 inspection staff and two supervisors. The experienced staff needed 10 to implement the construction program remain in the Division of 11 Construction Oversight.

12 Although some inspectors have moved to other 13 divisions in Region II, we continue to utilize these resources as 14 needed.

15 The lead inspector -- the lead test inspector has 16 extensive construction and operational experience, including as the 17 Senior Resident Inspector at Watts Barr Unit 2 during the transition 18 period from construction through the initial test program and as the 19 Senior Resident Inspector at Summer Units 2 and 3.

20 Having the right individuals with the right skills at the 21 right time is a carryover lessons learned from the Watts Barr Unit 2 22 construction oversight as being incorporated in our current 23 organization.

24 Lastly, those inspectors who took positions outside 25 the New Reactor Business Line will maintain their qualifications and 26 will be available to support any future surge of inspection activities.

27 The Division of Construction Oversight continues to

34 1 identify efficiencies and incorporate lessons learned into our 2 inspection program.

3 Prior to cancellation of VC Summer construction, the 4 NRC had been using one-for-four inspection approach where feasible.

5 For example, we inspected the reactor vessel 6 hardness documentation, are able to close that inspection for all four 7 units.

8 We are now using a similar approach, we're using the 9 one-for-two inspections at the Vogtle site.

10 The incorporation of lessons learned by the licensee, 11 sequencing of work and design certainty has allowed the licensee to 12 gain efficiencies.

13 The picture in this slide is of the Vogtle Unit 3 shield 14 building. This is an example where the licensee construction has 15 been accelerated and, as such, the NRC inspections are being 16 brought forward commensurate with the licensee's construction.

17 The NRC has also incorporated lessons learned from 18 the Unit 3 inspections into our inspection plans and procedures which 19 typically result in less inspection hours being expended on the second 20 unit without a loss of effectiveness.

21 Next slide, please?

22 The NRC's construction inspection program 23 completion rate for both Vogtle units are approximately 37 percent for 24 ITAAC inspections and 21 percent for operational program 25 inspections.

26 As with any complex project, the NRC staff continues 27 to adapt to the dynamic construction environment through planned

35 1 ITAAC and programmatic inspections which includes all facets of 2 inspection, ITAAC closure and coordination with NRO, NRR, and 3 NSIR for activities to support operations.

4 The NRC ITAAC inspections conducted during this 5 last year included the construction of the nuclear island and the 6 fabrication of primary containment and structural modules.

7 Operational programs, including emergency 8 preparedness, cybersecurity and physical security inspections.

9 We are proactively working with the other business 10 lines on the AP1000 program development. For example, last 11 summer, Chris Miller, who has responsibility for the reactor operating 12 -- for the operating reactor inspection program, accompanied me at 13 the Vogtle station to assess the plant configuration and systems to 14 inform the development of the reactor oversight program at the 15 AP1000 units.

16 We have proactively developed -- next slide, I'm sorry.

17 We have proactively developed an inspection 18 program with the majority of the inspections completed prior to the 19 ICN submittal.

20 The NRC conducted two public meetings in 2017 21 regarding the ITAAC closure and verification demonstration project.

22 One of the objectives was to ensure an integrated 23 management understanding of activities associated with ITAAC 24 closure including the required inspections.

25 Associated with this effort, Region II and NRO have 26 worked together to establish metrics to represent the different aspects 27 of the inspection program and communications that are occurring.

36 1 The inspection metrics are both performance-based 2 and anticipatory to allow for early management attention and to assist 3 in discussions with the licensee.

4 Inspection metrics track performance, reinforce 5 accountability and communicate issues needing attention at the 6 appropriate management levels, both internal and external to the 7 NRC.

8 As listed in this slide, there are five metrics being 9 developed. Two of these examples are, first, the inspection 10 scheduling metric tracks required inspections associated with the 11 anticipated ICN submittals and highlights any inspection that will not 12 be completed within 60 days following the licensee submitting their 13 ITAAC closure notification.

14 This allows for early identification of inspection 15 resources and, if necessary, timely interactions with the licensee on 16 supporting the inspections.

17 A second metric tracks the timeliness of completing 18 technical assistance requests and unresolved items.

19 Each technical assistance request may be requested 20 from Region II to NRO to resolve technical issues related to ITAAC or 21 programs or from NRO to Region II to request inspection of ITAAC or 22 programs.

23 These metrics enhance early engagement of NRO 24 and Region II management and provide a leading indicator for 25 inspection status. These metrics are key communication tools 26 between the staff and also with the licensee.

27 Next slide, please?

37 1 The NRC staff utilizes the licensee's construction 2 schedule to link with our inspection plans and to schedule inspections.

3 Through this scheduling, the NRC ensures that inspections are timely 4 and are completed prior to the licensee submitting their ITAAC closure 5 notice.

6 This close coordination with the licensee provides the 7 opportunity for the NRC to adjust our inspection schedule as well as 8 for the licensee to determine when and what they need to complete to 9 support the ITAAC inspections.

10 This strategy was effective during this last year.

11 However, more effective communication with the licensee 12 management was needed to ensure that inspection support activities 13 from the licensee were being implemented on a time line with their 14 management's understanding.

15 The inspection scheduling metric described as part of 16 the previous slide is used to inform these discussions.

17 We conduct numerous ITAAC and program -- we 18 conducted numerous ITAAC and program inspections this last year.

19 These inspections included digital I&C as part of the initial test 20 program and the piping design acceptance criteria program.

21 For the digital I&C, the NRC inspection strategy is a 22 combination of inspection at the Westinghouse facility and the Vogtle 23 site with coordination of digital I&C experts from headquarters and 24 Region II to ensure that the right inspection is performed at the right 25 time with the right people.

26 To support the digital testing inspection activities, 27 detailed test procedure reviews will be performed by inspectors with

38 1 the necessary technical skills prior to testing.

2 This allows for a broader use of inspection staff to 3 support the actual test observations.

4 Next slide, please?

5 We continue to support inspector exchange rotations 6 to the Sanmen and AP1000 construction site in China to leverage their 7 construction experience and to exercise and improve our inspection 8 procedures.

9 Recently, we had three inspectors in China as part of 10 the exchange rotation, Tom Dunn, a licensed examiner from Region I, 11 Scott Egli from the Technical Training Center and Lisa Castelli, one of 12 the initial test program inspectors in the Division of Construction 13 Oversight.

14 These individuals experiences add to our firsthand 15 knowledge with the as-built configuration of the AP1000 and their 16 experiences, along with their predecessors, are being carried over into 17 our training at the Technical Training Center.

18 In 2017, NRC managers and staff supported 19 multinational vendor inspections and the National Nuclear Safety 20 Administration of China Steering Committee meeting that was held in 21 China.

22 The NRC has hosted numerous international 23 representatives with Region II hosting individuals from Poland, China 24 and Japan.

25 Lastly, to summarize the construction program for 26 you, we have established processes for planning and scheduling of 27 inspection activities that account for the inherently dynamic nature of

39 1 large construction projects.

2 This leadership team is committed to the success of 3 our oversight program. And, as I started out with, we are ensuring 4 the inspections at the Vogtle site are timely, are coordinated with the 5 licensee's ITAAC closure schedule and that we are taking advantage 6 of opportunities to move inspection activities forward in our schedule 7 to mitigate potential high inspection demand periods.

8 That concludes my remarks, I'll turn it back over to Mr.

9 Johnson.

10 MR. JOHNSON: Thank you, Bill.

11 So, to summarize, we are pleased with the 12 accomplishments of the new reactors program during the past year.

13 Our demonstrated agility and successfully adjusting to 14 a significant workload change, our effort focused on preparing that 15 we're ready, ensuring that we're prepared to license new technologies 16 and our use of enhanced processes, we think will support the Agency 17 in meeting our mission to enable the safe use of nuclear power and 18 meeting the nation's future energy needs.

19 This concludes our presentation and we're ready to 20 take your questions.

21 CHAIRMAN SVINICKI: Thank you all for those 22 presentations.

23 We'll begin the Commission questions with 24 Commissioner Burns.

25 COMMISSIONER BURNS: Thank you, Chairman.

26 And, I thank the staff for the comprehensive 27 presentations, the overview of activities in this business line that range

40 1 from overseeing the construction and implementation of decisions on 2 licensing at the sites that continues the ongoing licensing under Part 3 52 for both combined license, ESPs and design certifications. And 4 then, the look forward to advanced reactors.

5 Let me throw a bit of vinegar in the punch bowl 6 because I want to start out with sort of a contrast in what we often 7 read.

8 Staff today use the terms agile, efficient, effective.

9 Some antonyms I read sort of in the press are sclerotic, pusillanimous, 10 I think those are more like for the national spelling bee than the news.

11 I read that -- I read on some sites on organizations 12 that we have to interact with that one titled Innovation Not Wanted 13 Here, meaning the United States.

14 And, part of that that's thrown at the foot of the 15 regulator. We received a letter yesterday, and nothing really new, but 16 from the Nuclear Innovation Alliance, NEI and the Nuclear 17 Infrastructure Council talking about four areas where they think NRC 18 needs reform.

19 And, you all did, you know, to be fair, and as I say, I'm 20 just throwing a little vinegar in there, I think you've addressed a 21 number of these through your presentation, but I'd like to focus on a 22 couple of them.

23 But, the four were reversing the trend of increasing 24 regulatory costs and increasing and excessively long reviews, aligning 25 the regulatory framework for advanced reactors with their inherent 26 enhanced safety, defining licensing options clearly including options 27 for staged applications and approval and providing additional flexibility

41 1 for changes during construction.

2 Now, I'm not going to have time to ask you questions 3 about all these areas, but maybe two we could talk about.

4 What is -- what would the staff's response be to this 5 notion that there has been a trend of increasing regulatory costs and 6 excessively long review?

7 In other words, the reviews in Part 52 start at one 8 point as we began but the accusation is that we haven't really 9 efficiency, that they still continue to spread out.

10 I'll leave that to you and let you respond.

11 MR. JOHNSON: Thank you, Chairman, I'll start and 12 then I think Frank and Vonna will want to weigh in as well.

13 So, can I just step back for a second and talk about 14 the letter that you point to?

15 COMMISSIONER BURNS: Absolutely.

16 MR. JOHNSON: So, as a -- I actually opened with 17 the statement that is, we just received the letter and we are digesting 18 the letter.

19 And, there's much I think to be used that is contained 20 within that letter.

21 I actually liked the last paragraph of that letter that 22 notes the industry statement about their commitment to safety, 23 continue to share commitment to safety. I think that's very helpful 24 and we share, obviously, that commitment.

25 They -- I would say, personally, I don't agree with 26 maybe every aspect of every view that is raised, but certainly, there 27 are things that are pointed to in that letter that we're not surprised by,

42 1 that we've been working on, as you point out, and we're -- I believe 2 we're beginning to make progress on including the length of our 3 licensing reviews.

4 And so, for example, the work that we did with respect 5 to establishing the APR1400 schedule of 42 months, the work that we 6 did in looking at the enhanced safety focus review and scheduling, the 7 Nuscale review, all of that recognized that we had previous reviews 8 that were longer, that maybe looked at aspects that didn't need to be 9 looked at and we are tailoring those reviews to be more appropriate, 10 innovated, yet incremental way.

11 And, I want to leave you with, and there's more to be 12 done. We recognize there's more to be done.

13 One of the things that -- one of the fundamentals 14 about this letter that I think we all align with is that, as it relates to 15 embracing new technologies, we've got to find a way to do that better.

16 And, we've begun that activity, the EDO issued a 17 letter in early January, as you're aware. We're standing up an activity 18 to look about how we can transform and make even greater gains in a 19 way that, again, doesn't undermine our ability to meet our safety 20 mission, but that is more efficient to address the concern that you just 21 raised actually that is captured in that letter.

22 COMMISSIONER BURNS: But, let me move on to 23 the one other area, because I think this is another place where -- and 24 John touched on it, but, you know, the problem, and frankly, in the 25 overview, it's an overview, so sometimes we can't delve through.

26 Let's try to delve deeper on the flexible licensing 27 issue. If we could bring up slide 15 from the staff's presentation?

43 1 And, actually, your slide -- I think it's slide 14 -- oh, 2 actually go -- yes, this is a good one, but I want to talk about the next 3 one, the slide 16.

4 Clarify a flexible review process. Now, the interesting 5 thing, the way this picture, this diagram shows, it says many paths are 6 available.

7 And, I think one of the things, you know, again, what I 8 hear, and I think the staff, in fairness to the staff, I think the staff, you 9 address this to an extent in the presentation here this morning. But, 10 where those paths are going.

11 So, one of the things you hear in terms of what you're 12 reading, for example, we've had a lot of, and I've spent some time this 13 summer looking at this, into the Canadian vendor design review and 14 the United Kingdom's ONR, Office for Nuclear Regulation, that's what 15 they call it -- Office for Nuclear Regulations of general design 16 approval.

17 Now, what they don't do, neither of those are a design 18 certification a la Part 52 because a design certification was always 19 designed as a legally binding determination.

20 To what extent do you think that the standard -- can 21 we leave the slide up, please?

22 To what extent do you believe that the standard 23 design approval, which is provided for under Part 52, matches with 24 those concepts that have been offered to us as something that we 25 ought to be looking at or embracing?

26 And, maybe if there are -- if you have thought about, 27 where do you see areas where we might learn from our Canadian and

44 1 British colleagues with respect to the processes there?

2 MR. MONNINGER: So, thank you for the question.

3 So, first off with regards to NRC's flexible regulatory 4 review process, I think first you've got to think about it with regards to 5 stakeholders and their interests.

6 They have indicated an interest in proceeding under 7 the current framework as opposed to maybe a Part 53 process or 8 something, you know, started from scratch.

9 So, near-term applicants, near-term developers, 10 nuclear industry has indicated that they want to proceed under the 11 current framework.

12 COMMISSIONER BURNS: Meaning --

13 MR. MONNINGER: Meaning, not wholesale 14 revisions to regulatory processes, meaning not wholesale revisions to 15 regulations.

16 Changes to some regulations, but not a grounds up 17 approach to do that.

18 So, we've developed the near-term, mid-term and 19 long-term. And once we gain experience, we have thought about or 20 proposed potentially in the long-term to do some type of fundamental 21 rewriting of the regulations.

22 COMMISSIONER BURNS: Now, let me, just for 23 clarification, because I think I know what you mean, but I think on 24 that side, John, you're talking primarily in terms of looking at, for 25 example, the general design criteria or it's what I'll call the substance 26 of the review versus the -- what I'll call the process.

27 Because there's a mix of things. Part 52 has a

45 1 particular process. What they're looking -- part of what they're 2 looking at is this something less like, it's, you know, the sniff test. It's 3 the thing that can make -- that satisfied investors.

4 It's the thing that says I can get it, you know, I can get 5 it going.

6 MR. MONNINGER: So, that's --

7 COMMISSIONER BURNS: If you could talk to that.

8 MR. MONNINGER: Yes, yes.

9 So, the standard design and approval process has a 10 level of finality in terms of the staff's review. So, it is in excess of or 11 beyond, for example, the Canadian Phase 1 vendor design review.

12 You know, the terms of regulatory certainty that the 13 NRC will provide is beyond that, is beyond what would be provided.

14 If you were to look at what is required for the SDA 15 process, it could be a complete design or it could be major aspects of 16 the design.

17 One of the trade groups out there, Nuclear Innovation 18 Alliance recently sending guidance with regards to how to 19 appropriately classify major portions.

20 It would not have to be an entire nuclear power plant, 21 you could focus on the reactor. You could focus on subsets of the 22 reactor.

23 You know, so that would be a defined process that 24 would provide certainty.

25 And, what I'll go to is, for example, the feedback that a 26 design may get from the Canadian regulator, an applicant or 27 developer could come in with what we call a regulatory engagement

46 1 plan to say we are looking for NRC feedback in the following areas.

2 We're going to submit the six -- the following six 3 technical and topical reports.

4 This is the feedback we want and this is the schedule 5 and this is the resources.

6 You could -- they could put together a proposal, put 7 together a plan if they wanted to that was akin to, you know, anything 8 out there.

9 So, with regards to having a, you know, there's Path 10 1, 2 or 3. To a certain extent, it's more of a smorgasbord that 11 applicants could, you know.

12 COMMISSIONER BURNS: Yes, and I think I wanted 13 to sort of end that and to use your smorgasbord, I think we have to -- I 14 think what our responsibility is, is to make the menu clear about where 15 -- what the choices are.

16 And, I appreciate -- I think you all are doing that.

17 And, I know there's some other work to be done.

18 For example, on prototypes, we haven't done that. I 19 mean, we -- in terms of our licensing history, we haven't really done 20 that as NRC.

21 So, but that, looking at that is a potential path, looking 22 at what is the standard design approval made?

23 And, again, I think what you get from the literature, 24 you know, the commentaries out there is the issue about transparency 25 in terms of what does it mean for me to take this path and, of course, 26 the other transparency is also about what's it going to cost me?

27 Because, ultimately, they're going to have to pay for it.

47 1 My time's up. If I could, I want to just -- I want to 2 compliment the staff, particularly in the ITAAC area. ITAAC, again, 3 here's the thing, 30 years later, we're finally applying. Thirty years 4 after, maybe not quite, but I think the proposed rule was out 30 years 5 ago, on Part 52.

6 But, I really think the staff is to be commended with 7 respect to these tabletops and thinking through this issue.

8 Because, ITAAC as it is, was not -- is not solely 9 something of our invention. We got congressional help in the Energy 10 Policy Act in 1992 with respect to the time lines and things like that.

11 But, I think you're doing a good job in there.

12 My final thought, because I've been spending a lot of 13 time actually thinking and reviewing and looking at the history of 14 licensing process, it's actually 60 years ago that we also earned the 15 mandatory hearing provisions.

16 And, that was because the AEC was not transparent 17 about some of its licensing.

18 But, there has been this constant back and forth, give 19 and take between the Agency, whether AEC or NRC and the industry 20 about, you know, idealizing and finding the right path to achieve our 21 safety and security objectives and assuring that innovation can go 22 forward.

23 So, I appreciate your continued work on that.

24 Thank you.

25 CHAIRMAN SVINICKI: Thank you, Commissioner 26 Burns.

27 And, I might platform off a little bit of that. I was

48 1 going to identify some things that I think are very commendable and 2 praiseworthy by the staff in areas where I'm residing a lot of optimism 3 about the future on our ability to move forward.

4 Yes, there is a lot of complexity here. I view -- I know 5 this is a business line meeting, but a lot of this is about the Office of 6 New Reactors and we've heard a lot about the status of activities.

7 I want to communicate how impressed I am that, as 8 the Office of New Reactors has had a diminishment in the number of 9 discrete activities, they have also been challenged to have a vast 10 expansion of what I term their bandwidth.

11 So, they have had to go from a long activity list where 12 I think there were a lot of more routine matters that were very familiar 13 to the NRC.

14 And so, as they have completed and that work has 15 narrowed, some of it fell away, but a lot of it has just simply been 16 pushed across the finish line which is very praiseworthy in my view.

17 But, now, they have to pivot to areas that require us to 18 really expand the bandwidth, not only in SMRs, it's kind of good if you 19 look at it as kind of a crawl, walk, run that we're having an SMR review 20 for the NuScale review.

21 I think that's allowing us to do more forward looking 22 issue resolution and requiring us to do it with a strong activity-based 23 schedule. So that's good.

24 And then, we've also got to be continuing this 25 substantial engagement with the advanced reactor community.

26 I'm not often accused of being overly optimistic, but 27 my broad reaction to the white paper or non-paper that NRC received

49 1 from NEI and the Nuclear Innovation Alliance and the Nuclear 2 Infrastructure Council.

3 I thought it was encouraging that there is so much 4 identified from these groups communicated to us that are areas not 5 only that we've already identified, but they are areas that, for some 6 years now, we have been at least elbow deep if not deeper with 7 external participants in identifying what goes on there.

8 As John Monninger put up in his presentation, not 9 only do we have a vision, we have implementation plans. And, 10 beneath those, we have strategies and then activities.

11 I know that sounds like a lot of buzz words, but in 12 John's example of picking two strategies, talking about the activities.

13 Those activities, we don't sit here and dream those up 14 on our own. Those are an outgrowth of all of the engagement that 15 you all have talked about.

16 I know that the report or white paper was a little bit 17 critical of what advanced reactor applicants are saying about our 18 process.

19 I have to say as a counterpoint, as I have been at 20 technical conferences and meetings I've had, I won't name names, but 21 some of them have pulled me aside and been very complimentary of 22 our willingness to look at, as John calls it, kind of a regulatory 23 engagement plan.

24 But, what do you need? How are you moving 25 through your technology development, moving through the 26 development of your design? What, from a regulatory standpoint, 27 would be meaningful to you at what stages? A lot of interest in

50 1 topical reports.

2 And, I share the view of Commissioner Burns that, we 3 get asked a lot as Members of the Commission about, hey, the 4 Canadians are doing this, the Brits are doing this, why don't you have 5 something similar?

6 In truth, Congress was so wise in the Atomic Energy 7 Act they actually gave us something that is a foreshadowing of the 8 kind of authority, and my colleague is too humble to mention, his law 9 article that he recently published which talks about the history of 10 development of Part 52, but also foreshadows that we have a lot of 11 organic statutory authorities that would allow us, in the absence of 12 even any legislative changes, there's quite a bit we can do.

13 I know the staff is always engaged with many 14 international counterparts. But, right now, is looking closely at work 15 with our Canadian and British colleagues.

16 And, I think it's also meaningful where countries might 17 have the same design under review, regulators could do a lot of --

18 Because, I think we can talk in generalities, but when 19 we get to saying, here's a design, it manifests these safety issues.

20 How, as independent regulators do we come at that?

21 And, I think that that's where we can share a lot of 22 learning. And, the good news is, we have the authority to do it now.

23 The staff is already engaging it.

24 And so, again, glass half full, glass half empty. We 25 appreciate the feedback. We don't in any way take critical feedback 26 with resistance.

27 But, I think -- and we'll look at that feedback where

51 1 they present counters to say you need to do a whole lot better on this.

2 The other thing, my other reactor was, when people 3 talk about prolonged reviews and the cost of them, this isn't anything 4 that we don't know.

5 So, that's the other encouraging thing about the 6 report. Where we might have a slightly different characterization, we 7 at least are well aware of the terrain of the issues.

8 And, the truth is, and I asked about this at one of the 9 large light water reactor mandatory hearings, I don't remember which 10 one, when we look at the number of staff hours between the 11 environmental and safety reviews for those, it is a little bit of a scatter 12 plot.

13 So, I think we, ourselves, are intrigued about why 14 hasn't it been a linear progression? We know we're getting 15 efficiencies, why doesn't that show up in the data?

16 We know the reviews and we can surmise, I think this 17 one got hung up on this issue and we know kind of what it is, but we 18 haven't done a systematic look at why it hasn't been a linear 19 improvement and efficiency.

20 So, overall, I think that is NRO approaches its 21 eventual joining with the Office of Nuclear Reactor Regulation, a lot of 22 organizations would lose focus and not finish.

23 And, again, it's some time out, but I'm just really 24 impressed with -- and it started, I think, under Glenn Tracy. It's been 25 continued under two Directors.

26 And, Vonna, I appreciate your time in continuing that 27 focus of continuing to push issues to closure. So, I thank you for that.

52 1 Even as the Summer 2 and 3 project was 2 discontinued and fell away, I'm impressed with the reorientation 3 towards providing the most effective oversight of Vogtle construction.

4 I think every time something changes, I'm impressed 5 with how the staff takes an opportunity to refocus.

6 Because when you're doing multiple sites, have 7 construction oversight, I think you set up one structure. When it falls 8 away to one project, you've reanalyzed, how can we have a real 9 consistency of focus? Should we have dedicated, you know, legal?

10 Should we get the same team of people on it? And, 11 even the support functions to it.

12 I think that that's -- if that isn't agility, I don't know 13 what is. That looks like agility to me.

14 And so, I do appreciate all of that.

15 And then, I think we've got the discrete items. As my 16 colleague mentioned with the ITAAC. I appreciate the focus on that.

17 Also, transition to ops, I think, is very, very important 18 for Vogtle 3 and 4. So, I appreciate that what is happening on the 19 ground out there, that we heard some about today, I think that'll be 20 interesting.

21 You showed the picture of the control room and it is 22 interesting to go to that digital control room for the AP1000.

23 And so, I know that's going to present some novelty 24 for us as we move forward.

25 I don't -- hearing all that, is there -- I know we've got a 26 focus on resolution of issues. So, again, we have this finishing strong 27 with large light water reactors and Vogtle 3 and 4.

53 1 Should it be that that might be, you know, the last of a 2 kind of U.S. construction and then it'll go into a little bit of a dormancy 3 period as SMRs and advanced reactors move forward.

4 I appreciate also, though, that we're expanding that 5 bandwidth.

6 And with, I'll close with Mike Johnson's 7 acknowledgment that lot more to do. Because, it was funny, I was 8 testifying before Congress answering this same question on advanced 9 reactors. How is NRC getting its act together? Are you going to be, 10 you know, a long pole in the tent here?

11 And, I said, I talked about the vision and I talked 12 about the action plans. And, I said, but you know, we have more to 13 do. And, the response I got was, you have a lot more to do.

14 So, we do have a lot more to do. But maybe I'll just 15 let Vonna or Mike, do you want to add anything to that?

16 MS. ORDAZ: I would just offer, thank you for the 17 feedback and the comments for the whole team here.

18 We do look forward to the feedback from the industry.

19 We've had it in many public meetings. So, the NEI letter, we 20 appreciated that feedback as well.

21 We look forward to you seeing a Commission paper 22 that will be coming up shortly in the next week or so to the 23 Commission on advanced reactors. And, I think it lays out nicely 24 some of the points that you raised, Commissioner Burns.

25 And, followed by a Commission meeting on advanced 26 reactors in the spring.

27 So, looking forward to interacting further on that.

54 1 CHAIRMAN SVINICKI: Thank you.

2 And, I think as well, the Agency soon to be launched 3 innovation forum, the transformation initiative that EDO Victor McCree 4 has kicked off.

5 You know, I hope others are as excited as I am. I 6 think that there's tremendous opportunity space.

7 And, again, you know, we know this. We know this 8 stuff. We know it well. And, I think if we unleash our problem 9 solving abilities, they are as good as or better than anybody's because 10 regulatory is our expertise. It's our domain.

11 And, I think that we've got a lot of people that are 12 looking to bring their creativity forward in those areas.

13 You know, one of the engagements I had with the 14 advanced reactor community, I synthesized their feedback in this way, 15 it's saying that, you know, brevity is appreciated in terms of reviews of 16 things and if we can do things efficiently and fast, brevity is 17 appreciated, but certainty is essential.

18 And, this goes back to Commissioner Burns' point, 19 they can't hold together a project if they don't --

20 So, I said to them, you know, are you telling me that, 21 if I told you you could maybe have a 24 month review but it might take 22 48 and I can't tell you? Or, would you rather have me say, it's going 23 to take 48 months and you ought to plan on that?

24 They said, we will take Option B every time.

25 And so, I appreciate that we're trying to get 26 efficiencies, but I think that Commissioner Burns made a really point 27 and it was in John's slide, there's a lot of paths, but I think they want

55 1 us to guide them through the paths and we need to lay that out with 2 clarity because these are technology developers going to finance 3 communities.

4 And they said, you know, if I can just make a business 5 case for a 48 month review and you can deliver on that, I'm almost not 6 going to want to have you distract yourself with a 24 month review.

7 Let's just focus on what needs to be done here.

8 So, again, they would appreciate brevity, but certainty 9 is essential. And, I appreciate the staff's work on that.

10 And, with that, I will turn over to Commissioner Baran.

11 COMMISSIONER BARAN: Thank you for your 12 presentations. There's a lot here to ask about.

13 I wanted to start with Tim and ask about ITAAC a little 14 bit.

15 You mentioned that Southern recently informed us 16 that all of the ITAAC closure notifications or uncompleted notifications 17 would be submitted by the end of this year.

18 Based on your pie chart, it looked like about today 26 19 percent had been submitted. So that would mean I guess the 20 remaining 74 percent would be submitted all in calendar year 2018?

21 Is that a change from what we had been expecting?

22 And, are we prepared for that many submittals in one calendar year?

23 MR. MCGINTY: So, that's a great question.

24 It is a change and it's an outcome of our 25 demonstration project interactions.

26 So, we had previously identified that -- and 27 established a process of working on UINs which is, you know, in

56 1 advance of actual ICN submittals.

2 And, in the course of the past year and in the 3 outcomes from the demonstration projects, we encouraged and 4 Southern Nuclear embraced the idea that, getting more UINs in earlier 5 would provide more regulatory certainty and reliability in our 6 performance.

7 And, they embraced it so much that, when we were 8 down at the quarterly site executive meeting recently, Mark 9 Rauckhorst conveyed that they intend to submit all ICNs in the form 10 of, you know, UINs or ICNs by the end of this fiscal year.

11 So, previously, we have been focused on a surge 12 right near the end of construction. That moves that up and a lot of 13 the work that we do on processing the notification now gets moved up 14 into the end of the year.

15 It is a large effort on the part of Southern Nuclear to 16 get that to us this year. But we are prepared to address it. We do 17 have the adequate resources and a surge capacity availability to turn 18 it around in a timely way.

19 It's a -- I am very encouraged by this commitment by 20 Southern Nuclear to move that forward.

21 COMMISSIONER BARAN: Good, I'm glad to hear 22 that.

23 As part of the SONGS lessons learned effort, the staff 24 initiated a pilot design inspection program at vendor facilities for the 25 fabrication of components used in major plant modifications.

26 Can someone just give us a brief update on that 27 initiative, where that stands?

57 1 MR. MCGINTY: I can.

2 So, as part of the lessons learned, we conducted a 3 pilot inspection program at three facilities, Ensa over in Spain on the 4 steam generators, AMETEK on invertors and Konecranes for 5 containment for all three units at Palo Verde.

6 We are currently going to issue our recommendation 7 in this regard. And so, it's still being developed.

8 But, I can tell you that, as a result of those 9 inspections, we didn't find enough issues in the area of analytical 10 code. So, we brought along technical expertise.

11 To warrant changing our baseline inspection program 12 for vendors to include a significant increase in these types of 13 inspections.

14 I would say that, moving forward, for discrete issues 15 and interacting with NRR and our colleagues, if you had a major 16 vendor facility that was going to fabricate components that we hadn't 17 been to before, we hadn't been to in a long time, I can see us on a 18 sampling basis going out to ensure that components are being 19 manufactured in accordance with the requirements of Appendix B.

20 Perhaps bringing along technical expertise to make 21 sure that we have a full understanding of the types of findings for 22 those situations.

23 Accident tolerant fuel fabrication in the future would 24 be another area that I would anticipate that that could be beneficial.

25 COMMISSIONER BARAN: Okay, well, thanks for 26 that update. I look forward to reading about the results of the pilot.

27 Frank, you mentioned that there's some risk of the

58 1 schedule slipping on KHNP, the design certification review.

2 It's my understanding is that that involved the late 3 submittal of probabilistic risk assessment information from the 4 applicant.

5 Can you just take a minute to walk us through that?

6 What's the nature of the potential delay there and where do things 7 stand?

8 MR. AKSTULEWICZ: Thank you, Commissioner.

9 So, the challenges associated with KHNP do surface 10 around some of late, I don't want to call them late, delayed submittals 11 of information supporting the closeout of open items related to their 12 PRA.

13 So, we've been working with them quite extensively to 14 try to mitigate as much as we can the impact. In fact, we have -- we 15 recently received a letter from them that outlined the most recent 16 strategy for supporting the staff.

17 Their strong interest in completing the 42 month 18 schedule on time.

19 We have looked at what it would take to do that. It's 20 going to be difficult. It will take resourcefulness on the part of both 21 parties to be successful. But, it is within reach.

22 And, as I've said in my talk, we think it is achievable.

23 It's going to require close attention on the part of both management 24 teams and the KHNP organization that's sitting up there behind me 25 having met with us just this morning and reiterated their commitment 26 to achieving the outcome that was expected.

27 It's equally important to them to be successful on the

59 1 schedule as it is for us. And so, they're committed to doing whatever 2 it takes.

3 COMMISSIONER BARAN: Okay.

4 John, you discussed the staff's pre-application 5 interaction with several advanced non-light water reactor developers.

6 Based on the conversations you all have had so far 7 with vendors, do we have a sense of whether they plan to use Part 50 8 or Part 52?

9 MR. MONNINGER: So, maybe I'll come back to the 10 smorgasbord analogy.

11 So, we've had responses to our 2016 RIS. And, if 12 you were to look at those, they're proprietary, generally proprietary 13 submittals.

14 There's a range of interest between Part 50 and Part 15 52. There's notions that some designs may originally come in with a 16 test reactor. They could subsequently use the experience from that 17 test reactor to use that information for a DC or a COL within Part 52 or 18 they could perceive from that test reactor to some type of COL within 19 a Part 50.

20 So, they've expressed an interest in all the options out 21 there, including SDAs and all the way up to a manufacturing license.

22 So, there's a very broad range of interest.

23 COMMISSIONER BARAN: Okay.

24 And, it sounds like, at least, one or more, though, are 25 potentially considering going down the Part 50 path of a construction 26 permit?

27 MR. MONNINGER: Yes, sir, yes.

60 1 COMMISSIONER BARAN: A while back, the 2 Commission approved a rulemaking to update the Part 50 process to 3 basically incorporate some of the requirements post-TMI and other 4 things that had been over time dropped into Part 52.

5 But, I think maybe because people didn't think Part 50 6 was going to get used, weren't being put into Part 50.

7 The current rulemaking schedule that was, you know, 8 I saw in the material we got has the proposed rule coming to the 9 Commission in 2019 and then the final rule in 2020.

10 Is that -- is work underway on that rule and what is the 11 latest thinking about the timing of that rule and how it marries up with 12 the plans of some vendors who might use Part 50?

13 MR. MONNINGER: So, thank you for the questions.

14 So, you know, my understanding is we've prioritized 15 that as a medium priority rule in accordance with the comment 16 prioritization process.

17 The staff would begin the rulemaking efforts in fiscal 18 year 2019. So, the actual date to complete the rulemaking has not 19 been fully pulled together yet. So, it is a rulemaking yet to being with 20 the staff.

21 And the schedule for those efforts are associated with 22 a medium priority.

23 With regards to the question to the underlying 24 technical requirements, be it the PRA, be it the TMI action items, et 25 cetera, you know, the Commission, if you look at back in the 1980s 26 the Severe Accident and Policy Statement, the proposed approach to 27 resolution of severe accidents for new reactors, for advanced reactors,

61 1 for anything coming down the road, fundamental, the Commission 2 said, you shall do. It's a policy statement versus regulation.

3 But, you shall do the PRA. You shall resolve, you 4 know, the technical applicable TMI action items, et cetera.

5 So, even before Part 52 was in place, you had 6 designs such as the ABWR prior to Part 52 proceeding down this 7 path.

8 COMMISSIONER BARAN: Well, I guess in terms of, 9 and I know it's hard because there are a lot of moving parts here, but 10 do we have a sense of whether, you know, the rulemaking to have 11 these actually be regulatory requirements in our regulations, which I 12 think everyone agrees makes sense to have them there, it's kind of, I 13 think, an oversight that they weren't there.

14 But, is that -- is the timing of that rulemaking, is that 15 work for the time, you know, when we think vendors would come in or 16 applicants would come in under Part 50?

17 MR. MONNINGER: Yes, unfortunately, there's two 18 responses to that question.

19 The first question is -- the first response is NRC's 20 planning and our vision and strategy and the work we propose to do, 21 we linked it with the Department of Energy that discuss potential 22 construction in the 2030 time such that NRC would be fully prepared 23 by 2025.

24 So, you know, it would be fully consistent with a 2025 25 type licensing or even prior to that.

26 The challenges would come in if there was an early 27 applicant -- an early license application within the next year or two and

62 1 we would, of course, engage with the Commission.

2 Right now, you know, we do have some interest in 3 early applications. With that said, the question is, how much certainty 4 do you place in that?

5 You know, in the past, we've also had interest in 6 applications that, for one reason, the other had been delayed.

7 But, it, you know, would not be limited to just the 8 50.52 rulemaking, there could be other changes that the Commission 9 could want the staff to proceed in terms of rules to support early 10 applicants.

11 COMMISSIONER BARAN: Let me ask just one 12 more thing. I'm kind of over on my time already.

13 But, I -- on advanced reactors, you know, as you 14 mentioned in your presentation, we want to front load some of these 15 advanced reactor technical and policy decisions.

16 And, obviously, for us to do that as an Agency, we 17 have to have the right technical expertise on the staff to be really 18 ready to engage on those issues.

19 What's your assessment of where we are now on 20 advanced reactor technical expertise within the staff? Do we have 21 what we need for the designs we expect to see in the coming years?

22 And, if it's not entirely there, what's our -- I know this 23 kind of falls under Strategy 1 or that bucket, what's our plan for 24 making sure we have the expertise we need? Is it largely about 25 identifying skills we already have on the staff and training? Is it 26 external hiring? Is it contractor support? Is it a combination of those 27 things?

63 1 MR. MONNINGER: So as you mentioned, it's within 2 IEP Strategy One. And when you bump it up a level, you know, one 3 of our strategic goals was technical readiness. That's staff technical 4 readiness via -- whether it's the bodies in seats, number of seats, 5 knowledge management, training, familiarity with the design -- so that 6 is all encompassed within technical readiness and IEP Strategy One 7 as you indicated. Our early efforts in working with OCHCO, our 8 Office of the Chief Human Capital Officer, have been associated with 9 strategic work for planning and with our competency modeling. And 10 so we've done efforts in that area.

11 You know, these -- you know, they have to step back 12 and say, yes, these designs are different. Now what does that mean 13 to our staff? The Commission actually has a very experienced, highly 14 competent staff. A lot of nuclear engineers, a lot of electrical 15 engineers, chemical engineers, et cetera. We routinely move them 16 from office to office, to project to project. So the question is, what is 17 the difference with some of these designs?

18 A lot of the technical disciplines, the staff -- you know, 19 is within the current capabilities of the staff. The uniqueness comes 20 in when you get very close to the reactor and when you get associated 21 with some of the materials. You know, and then when you get very 22 close the reactor, the nuclear engineers we believe, with appropriate 23 training -- you know, within the staff -- it's within their capabilities. Of 24 course, we have to have the staff there and train them, et cetera.

25 But, you know, the bandwidth -- it's within the capabilities.

26 Certain areas if you were to go, for example, like 27 molten salt chemistry. We don't have that expertise within the staff.

64 1 So whether we were to go out and recruit for it or rely upon the -- rely 2 upon contractors, you know, we'd have to make that -- that decision.

3 But it's very important for us to have the technical readiness. You 4 know, this past year we conducted a training on molten salt reactor 5 technology for approximately 100 staff. This coming year we're 6 having training for the staff on high temperature gas reactors, and 7 we're having training on sodium fast reactors. With that a lot more 8 has to be done. And they're just elementary, basic courses, you 9 know, for the staff. But, you know, if you go across the disciplines, 10 you know -- seismic -- you know, meteorology. You know, nothing is 11 going to change in terms of the seismology of the earth with regards to 12 a non-light water reactor. So we have the expertise. So you have to 13 really narrow down to where are the critical skills going to be different?

14 And where of the existing staff do we just --

15 COMMISSIONER BARAN: And you're satisfied for 16 these more near-term actions -- you know -- setting up policy or 17 technical issues to be resolved early, we have what we need to do 18 that?

19 MR. MONNINGER: To address the near-term policy 20 issues, you know, yes.

21 COMMISSIONER BARAN: All right, thank you.

22 CHAIRMAN SVINICKI: All right, thank you. I was --

23 I had -- well, just one additional question. So I was going to turn to 24 Commissioner Burns. Did you have anything else that you wanted to 25 ask? It's a lightening round. We'll just go fast. Thank you.

26 COMMISSIONER BURNS: You see, we're 27 demonstrating our agility.

65 1 CHAIRMAN SVINICKI: Yes.

2 COMMISSIONER BURNS: There we go. Actually, 3 a follow-up on the -- on the question this 52 - 50, you know, 4 harmonization, whatever. The interesting thing about it is it strikes 5 me, just as, I think, what the staff is having to do in terms of looking at 6 -- you know, looking at existing framework -- how does that fit or not fit 7 say, for example, the GDC? The work that was done through DOE 8 and then -- we have it -- you know, work done on the draft reg guide.

9 And I guess we're coming up on potentially final -- we've had the 10 comment period on the reg guide?

11 MR. MONNINGER: Yes.

12 COMMISSIONER BURNS: And/or coming up on 13 that. But -- so my question would be is -- it -- and don't get me 14 wrong. I think ultimately you would want to do that rule, but it strikes 15 me is it may be more a nice to do because -- it sounds like to me 16 you've communicated -- is, John, you noted the old policy. Granted, 17 it's a policy statement, but, you know -- you want the license, you 18 need to address the -- you know, address those types of things. So I 19 presume that's communicated to these potential applicants in the 20 advance reactor area.

21 MR. MONNINGER: So with regards to PRA, you 22 know -- not to throw out numbers, but I have a 99.9 percent certainty 23 that advanced non-light water reactors are -- are going to do this. I 24 mean, not only is it historically been a Commission policy and we have 25 the requirements out there for Part 52, but their design approach for 26 many of them will be a highly -- will highly use the PRA. There's a 27 thing called the licensing basis event selection. So if they were to

66 1 use that, regardless of a requirement for a PRA or not, if they come in 2 using a PRA-based licensing basis event selection, the staff has 3 sufficient authority to go in and -- and review and look at that PRA.

4 COMMISSIONER BURNS: Yes. And in fact if I'd --

5 I'd say the latter, which we -- we talked about a little bit. In a sense if 6 -- there's a provision in there that really talks about the more 7 probabilistic and -- risk analysis and looking at the types of things that 8 you describe.

9 MR. MONNINGER: Yes.

10 COMMISSIONER BURNS: Thank you.

11 CHAIRMAN SVINICKI: Well, thank you for that.

12 And I noted as both of my colleagues were talking about advanced 13 reactor technologies, there's a great curiosity that everything old is 14 new again. The United States, if we look at the atomic history of our 15 country and our atomic programs -- now it's very -- maybe the best 16 thing is not training for the staff. If we could invent a time machine, it 17 would be great. Because we could send them back to when people 18 were demonstrating these types of reactor technologies. So I know 19 at least one advanced reactor applicant had told me -- or not -- yet, 20 not yet an applicant, but designer -- said that they're actually working 21 on just archival data from experimental programs in, like, the '60s and 22 '70s. And what would be a validation to give a pedigree to that data 23 so that it could be cite-able in something before the NRC in the 24 modern age? So I think that that's an interesting curiosity. And I 25 don't doubt that some of our staff studies that history as well and 26 probably brings some awareness.

27 But my question had to do with design certification

67 1 renewals, which I don't think has come up today, but is part of this 2 business line. And speaking of, the fact that you reach a stage where 3 you're finally doing ITAAC, we've got a number of design certification 4 renewals in front of us. And the agency has brought so much 5 attention to operating reactor license renewals and said, is there 6 clarity? Is there a clear understanding of the requirements? I am 7 not aware necessarily that we've had the same kind of focus on 8 renewals of design certifications. And so what would the -- how 9 would the staff characterize the level of stability in terms of that 10 process? And as policy issues arise, how are those being handled in 11 terms of design certification renewals? It looks like Frank wants to 12 respond.

13 MR. AKSTULEWICZ: So, thank you for that 14 question. How would I characterize it? Well, there is a draft of 15 guidance out there about what would be considered appropriate for 16 renewal. I would not say it has advanced beyond the proposal. And 17 definitely need to go back and finish it now that we're actually almost 18 done with the ABWR -- in terms of looking at how that guidance was 19 applied, whether we need to change the guidance in some fashion or 20 another to reflect the review.

21 Other than that, the -- the policy questions are an 22 interesting one. We have exercised the back-fit rule extensively in 23 looking at what would be the appropriate level of review for the 24 ABWR. We -- the initial discussions between GEH and the staff were 25 we think these are the issues that you -- we would like you to consider 26 during the renewal. You've identified a set, we think the set is bigger.

27 There's been exchanges of technical information between the two

68 1 parties that -- in fact, we're getting ready to issue a letter that says we 2 agree with your assessment that seven or eight of these topics don't 3 need to be discussed as part of the renewal because they don't hit the 4 threshold for adequate protection or reasonable assurance. And so 5 we're saying okay, yes. We've aligned on that and so that would be 6 reflected in the guidance going forward, that these are the areas that 7 the staff doesn't believe weighed to that magnitude where it's 8 something that would be essential to a renewal.

9 That being said, we are in the process of discussing 10 bringing to you an interesting dichotomy, if you will, of maybe an 11 unintended consequence of the renewal provisions of design 12 certification and some of the structure Part 50 -- and it gets into John's 13 area where you look at the need to assess the peak clad temperature.

14 And, you know -- the -- the standard for the renewal was that, you 15 know, you have to show demonstration that you were in compliance 16 with the rule at the time that you were certified. Well, that's nice.

17 And they did.

18 The challenge now is Part 50 tells you that when you 19 change, or when you identify a certain percent -- temperature change 20 over the course of a period of time, you know, then to bring that -- to 21 the agency for re-review and -- which, the question is, well what --

22 does that apply to a renewal? Because it's been sitting there for 15 23 years and accumulating these variances, but the standard is you've 24 already showed that you've complied with the rule earlier. Nothing's 25 changed except, as you continue to calculate the changes in PCT 26 over time, it's different. And it affects the reach and the reactor area 27 in some of the containment areas.

69 1 So, is the expectation that a renewal applicant now 2 would then have to go back and reassess a substantial portion of the 3 design associated with those types of changes which -- if you look at 4 the history, it was probably not the intent for a renewal. The idea 5 was, if you don't change anything, it's the same that you had. So --

6 so we're looking at -- at how we were going to bring that to the 7 Commission for -- for a decision. And whether we're going to do --

8 tell you this is how we intend to implement that provision, or whether 9 we're going to bring options to you and say here's what we 10 recommend and here's what we were considering. So it's one of 11 those little crazy subject areas where you stumble on it when you're in 12 the middle of the review.

13 CHAIRMAN SVINICKI: Well, I have a -- that 14 example is very helpful because it is -- this to me has a strong 15 resonance with the agency's history on operating reactor license 16 renewal in terms of what is the scope of it? The difference here is 17 that we may or may not -- the design certification license renewal, if 18 we've -- if the U.S. has never built that reactor, it becomes more of a --

19 it's more theoretical. And therefore I think it poses some novelty and 20 has some -- some questions about it.

21 But I think also we need to give meaning to the finality 22 of the design certification. And then there is a process for its renewal.

23 So I think some of your exploration of back fit is clearly appropriate 24 because we need to give meaning to the finality of the design 25 certification. Maybe -- you know, an interesting thought exercise is if 26 this -- if this design had been constructed in the U.S. and it was 27 operating, would we go back and require a re-analysis? Now, the

70 1 difference with a physical reactor that's been built and operating is that 2 you have all the operating experience and so one becomes a 3 computational exercise and one is something that we can put hands 4 on and eyes on. So I do think there's some novelty here and again, 5 as I've been hearing about some of this I have regretted that maybe it 6 hasn't had the same level of focus of bringing certainty to it prior to the 7 doing of it.

8 But I do appreciate, Frank, that it sounds like the staff, 9 as they get through the ABWR, is going to reflect on the -- the lessons 10 learned from that. And perhaps in addition to improving the 11 guidance, if necessary, come back to the Commission on some things 12 of first impression and say, this maybe wasn't intended -- or was it --

13 but we will let the Commission at least re-validate that that is an 14 expected outcome of the way the process works now. So with that, 15 Commissioner Baran, do you have anything else?

16 COMMISSIONER BARAN: Sure, I will go for one 17 more.

18 CHAIRMAN SVINICKI: Okay, sure.

19 COMMISSIONER BARAN: Back on advanced 20 reactors, you know, one of the -- one of the policy issues there is on 21 security. And I saw that the staff put out a draft white paper in 22 November -- potential changes to security requirements for advanced 23 reactors. And it's a pretty high -- it's not a really in-detail document.

24 It's a fairly high level and it lays out some options and one of which is 25 doing a rulemaking in this area that would move more towards 26 performance-based requirements and move away from the more 27 prescriptive requirements like having a minimum number of

71 1 responders on site.

2 Can someone briefly just talk about how far along the 3 staff is in its thinking about what performance-based requirements in 4 this area might look like? And this is again a little bit similar to the 5 question I was asking earlier on the other rulemaking. If it -- if it ends 6 up being a rulemaking-type option, how does the timing of that 7 rulemaking fit with the kind of design certification applications, or COL 8 applications, or Part 50 applications we think we are going to be 9 seeing in the advanced reactor space?

10 MR. MONNINGER: So I can take that. So -- so the 11 question is, you know, where are we in that deliverable to the 12 Commission? So we've had multiple interactions with a stakeholder.

13 We've gotten good feedback from stakeholders. We've had internal 14 alignment meetings. There will be various options within the paper of 15 -- the staff hasn't finalized on the one particular option. So, you 16 know, in the end whether it was rulemaking or some other approach 17 that would be the decision coming back, you know, from the 18 Commission. And we would then implement that decision.

19 You know, if you were to pontificate that it went down 20 the line of the rulemaking -- you know, there is the examples out there 21 for emergency planning. And, you know, some Commission direction 22 on -- on whether changes to EP should be considered early for 23 applicants through an exemption process or whatever. But that 24 would, you know, be dependent upon any decisions that Commission 25 would make with regards to the proposals, you know, coming forth.

26 There was a second half. But I forget -

27 COMMISSIONER BARAN: Just it related to -- well,

72 1 or it anticipating -- I know it's a little bit hard. We're -- in some cases 2 it may be years out. But anticipating in terms of submittals and -- you 3 know, does that kind of line up well? Or not so well?

4 MR. MONNINGER: So I think what we would do 5 within the paper that would come forth to the Commission would be to 6 discuss the potential implications and the options of applications under 7 review, near-term applications, et cetera. You know, we haven't 8 pulled all that together yet, but that would be presented to the 9 Commission.

10 PARTICIPANT: Yes -- go ahead.

11 MR. JOHNSON: I was just going to say, I think as a 12 -- as a general matter in the way that we are approaching this is, we 13 want to identify the policy issues and get them up, get Commission 14 direction associated with them. We recognize that some of these 15 applications are going to come in. They're going to need certainty as 16 they do their design in advance of the time that it would take us to do 17 a rulemaking. And so we'll want the -- we'll want the -- to identify the 18 answer, we'll want to identify the appropriate guidance associated with 19 that. And then we'll need to come back and -- and do the rulemaking, 20 I think, is how we've been approaching some of these issues for 21 near-term applicants.

22 COMMISSIONER BARAN: See that rulemaking as 23 the -- if it were rulemaking as the vehicle necessarily to provide the 24 answer -- the early answer to folks --

25 (Simultaneous speaking) 26 MR. JOHNSON: I would say ultimately it will be. It 27 is. But more importantly we need to get alignment from the

73 1 Commission with respect to where we are -- the Commission's desires 2 with respect to the outcome of the policy issue. And then that 3 enables us to begin moving even as we're doing the rulemaking.

4 MR. AKSTULEWICZ: So I am going to add one 5 more thought to that. I know we have been talking about the 6 advanced reactor arena as formative for some of this discussion. We 7 -- we can't lose perspective that the NuScale design is in a way the 8 path-building for some of this discussion. I mean, we have before us 9 proposed exemptions for emergency planning for an SMR PPE for 10 Clinch River. And so we'll be dealing with those types of questions --

11 what is the right structure for us to do those assessments? And what 12 does it mean? And then NuScale is also interested in looking at 13 performance-based security for the certification in terms of building in 14 the security design details -- so, going forward. So yes, it's important 15 for the advanced reactor arena, but some of that background is going 16 to be formative in the -- or, from the discussions on NuScale and 17 others.

18 COMMISSIONER BARAN: Thanks for that context.

19 Thank you.

20 CHAIRMAN SVINICKI: All right, there will be no third 21 round. The staff is going to be able to get to lunch. Well thank you 22 all again. I think it was great discussion and thank you all for the hard 23 work you are doing. And we are adjourned.

24 (Whereupon, the above-entitled matter went off the 25 record at 11:53 a.m.)