Discusses 810426 Appeals Meeting.Items Requiring Further Discussion Include Interim Purge Valve Qualification,Wetwell Spray Automatic Actuation & High Pressure Drywell/Wetwell Steam Bypass
ML18030A244
Person / Time
Site: Susquehanna  Talen Energy icon.png
Issue date: 03/31/1981
From: Curtis N
PENNSYLVANIA POWER & LIGHT CO.
To: Youngblood B
Office of Nuclear Reactor Regulation
References
NUDOCS 8104060445
Download: ML18030A244 (2)


Text

REGULATO INFORMATION DISTRIBUTION TEM (RIDS)

ACCESSION NSR; 8104060445 DOC ~ DATE! 81/03/31 NOTARIZED:

NO DOCKET ¹ FACIL:50~387 Susquehanna Steam Electric Statianr Unit 1> Pennsylva 05000387 50 388 Susauehanna Steam K'lectric Stationr Unit 2r pennsylva 050'005 8

AUTH'AME AUTHOR AFFILIATION CURTISr N ~ W ~'

Pennsyl vania Power 8, Light Co ~

REC IP s NAME-RECIPIENT AFFILIATION YOUNGBLOODi 8 ~ J'.

Licensing Sr anch 1

SUBJECTS Discusses 810426 appeals meeting. Items r equir ing fur ther'iscussion include interim pur ge val ve qual,i fication<wetwel l-.

spr ay automatic actuation 8 high pr assur e drywel 1/wetwel l steam bypass.

DISTRIBUTION COOK!

R001S COPIES RECEIVED!LTR g ENCL~

TITLE: PSAR/FSAR AMDTS and Related Cor'r espondence NOTES!Send ILE 3 cop)es FSAR 8 all

amends, Send ILE 3 copies FSAR 8 all amends'IZE:

05000387 05000388 RFCIP IENT IO CODE/NAME ACTIONS A/D LICENSNG RUSHBROOKrM ~

INTERNAL! ACCID KVAL SR26'HEM ENG BR*

08 CORE PERF BR 10 EMERG PREP 22:

GKOSC IENCES 14 HYO/GEO BR 15 IaK:

06 LIC QUAL SR MECH ENG BR 18 NRC POR 02'P LIC SR PROC/TST REV 20 R

0

. BS BR22 EG FILE 01 RU ENG BR25 COPIES LTTR KN L 1

1 RECIPIENT IO CODE/NAME YOUNGBLOODtB STARK,R, 04 AUX SYS BR 07 CONT SYS BR 09 EFF TR SYS BR12'QUIP QUAL BR13 HUM FACT ENG SR ISC SYS'R 16 LIC GUID BR MATL ENG SR 17

/PA OEI D PONER SYS BR 19 QA SR 21 REAC SYS BR 23 SIT ANAL BR 24 SYS INTERAC BR COPIES LTTR KNCL 1

1 1

1 3

1 1

1 1

1 1

1 1

1 EXTERNALS ACRS NSIC 27 05 16 1

LPDR 03 1

1

~

0 TOTAL NUMBER OF COPIES REQUIRED ~

LTTR 5'7 ENCL

PPaL TWO NORTH NINTH STREET, ALLENTOWN, PA. 18101 PHONE t215) 770-5151 NORMAN W. CURTIS Vice President-Engineering 8 Construction-Nuclear 7705381 March 31, 1981 Mr. B. J. Youngblood, Chief Licensing Projects Branch Il Division of Project Management U. S. Nuclear Regulatory Commission Washington, D.C.

20555 APPEALS MEETING MINUTES APRIL 26, 1981

Dear Mr. Youngblood:

Six (6) items were scheduled for appeal.

Two (2) items were resolved prior to the meeting.

PPGL will perform air tests for the feedwater system and use 1 gpm leak rate acceptance criteria for hydrostatic tests.

Isolation of RWCU and MSZV on high drywell pressure will,be, addressed generically.

Three (3) items require further NRC/PPGL discussion and documentation:

(1)

Interim purge valve qualifications will be implemented prior to fuel load.

PPaL made commitment to meet NRC qualification requirements before first refueling outage.

(2)'etwell spray automatic actuation will not be required if NRC finds 27 minute operator action calculation acceptable.

(3)

High pressure drywell/wetwell steam bypass may be addressed by a test, which is run at the highest downcomer submergence pressure available, or some other alternative.

One item was appealed for NRC decision.

NRC is to decide if low pressure drywell/wetwell bypass test frequency should be performed at ZLRT or every refueling outage.

Very tzuly yours, N.

W. Curtis Vice President-Engineering ll'onstruction-Nuclear P OO/

i/0 PHH:mcb PENNSYLVANIA POWER a LIGHT COPAPANY 104080QLLg