ML18025B622

From kanterella
Jump to navigation Jump to search
Forwards IE Insp Repts 50-259/81-21,50-260/81-21 & 50-296/81-21 on 810803-07.No Noncompliance Noted
ML18025B622
Person / Time
Site: Browns Ferry  
Issue date: 08/20/1981
From: Robert Lewis
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
To: Parris H
TENNESSEE VALLEY AUTHORITY
Shared Package
ML18025B624 List:
References
NUDOCS 8109090329
Download: ML18025B622 (4)


See also: IR 05000259/1981021

Text

AUG 8 0 1981

g~//OLd

ZE Sg Z~~0gg

Tennessee

Val 1 ey Authority

ATTN:

Mr. H. G. Parri s

Manager of Power

500A Chestnut Street Tower II

Chattanooga,

TN

37401

gyp O9 l981

Gentlemen:

Subject:

Report Nos. 50-259/81-2

50-260/81-21

and 50-296/81-21

This refers to the routine safety inspection

conducted

by Mr. G. A. Belisle and

others

of this office

on August 3-7,

1981,

of activities

authorized

by

NRC

Operating

License

Nos.

DPR-33,

DPR-52 and

DPR-68 for the

Browns

Ferry facility

and to the discussion

of our findings held with Mr.

H.

L. Abercrombie,

Plant

Superintendent,

at the conclusion of the inspection.

Areas

examined

during

the

inspection

and

our findings

are

discussed

in the

enclosed

inspection

report.

within these

areas,

the inspection

consisted

of

.selective

examinations

of procedures

and representative

records,

interviews with

personnel,

and observations

by the inspectors.

Within the scope of this inspection,

no violations or deviations were disclosed.

Me have

examined

actions

you

have

taken with regard

to previously identified

enforcement matters.

These are discussed

in the enclosed

inspection report.

In accordance

with 10 CFR 2.790 of the Commission's

regulations,

a copy of this

letter

and the enclosed

report will be placed in the

NRC's Public Document

Room.

If the report contains

any information that you believe to

be

exempt

from dis-

closure

under

10 CFR 9.5(a)(4), it is necessary

that you:

(a) notify this office

by telephone within ten days

from the date of this letter of your intention to

file a request for withholding; and (b) submit within twenty-five days

from the

date of this letter

a written application to this office to withhold such infor-

mation.

If your receipt of this letter

has

been

delayed

such that less

than

seven

days are available for your review, please notify this office promptly so

that

a

new

due

date

may

be established.

Consistent

with section

2.790(b)(1),

such application must be accompanied

by an affidavit, executed

by the owner of the

information which identifies the document or part thereof

sought to be withheld,

and

a full statement

of the reasons

on the basis of which it is claimed that the

information

should

be withheld

from public disclosure.

This section

further

requires

the statement

to address

with specificity the considerations

listed in

10 CFR 2.790(b)(4).

The information sought to be withheld shall

be incorporated

as far as possible into a separate

part of the affidavit. If we do not hear

from

you in this regard within the specified periods

noted above,

the report will be

placed in the Public Document

Room.

Si09090329

Si0820

PDR

ADOCK 05000259

G

PDR

~/PI

fig

It

I'

l

AUG 2 0 198>

Tennessee

Valley Authority

Should you have

any questions

concerning this letter,

we will be glad to discuss

them with you.

R.

C. Lewis, Chief

Reactor Projects

Branch

1

Division of Resident

and

Reactor Project Inspection

Enclosure:

Inspection Report Nos. 50-259/81-21,

50-260/81-21

and 50-296/81-21

cc w/encl:

H. J.

Green, Director of Nuclear Power

H. L. Abercrombie, Plant Superintendent

R.

E. Rogers, Project Engineer

H. N. Culver, Chief, Nuclear Safety

Review Staff

t

bcc w/encl:

NRC Resident Inspector

Document Management

Branch

State of Alabama

RI

RII

RI

RI

GBeli le:ht

CMUp i ht

CEMurphy

.

AFgi

son

8/($ /81

8/I)/81

8/)$ /81

8r( /81

PTaylor

8/S.O/81

RI

R Lewis

8/ y'81

~

~

'