Forwards IE Insp Repts 50-259/79-42,50-260/79-42 & 50-296/79-42 on 791126-27 & Notice of Violation
ML18024B456
Person / Time
Site: Browns Ferry  Tennessee Valley Authority icon.png
Issue date: 01/02/1980
From: Murphy C
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
To: Parris H
TENNESSEE VALLEY AUTHORITY
Shared Package
ML18024B454 List:
References
NUDOCS 8004040185
Download: ML18024B456 (4)


See also: IR 05000259/1979042

Text

)

0

I

C

tO0

+~

~O

++*++

In Reply Refer To:

RII:IM

50-259/79"42

50-260/79-42

50-296/79"42

UNITEDSTATES

NUCLEAR REGULATORYCOMMISSION

REGION II

101 MARIETTAST., N.W., SUITE 3100

ATLANTA,G EORG IA30303

NN

2 SSO

Tennessee

Valley Authority

ATTN:

H.

G. Parris

Manager of Power

500A Chestnut Street

Tower II

Chattanooga,

TN

37401

Gentlemen:

This refers to the inspection

conducted

by L. Modenos of this office on

November 26-27,

1979, of activities authorized

by NRC Operating License Nos.

DPR-33,

DPR-52 and DPR-68 for the Browns Ferry Nuclear facility, and to the

discussion of our findings held with H. L. Abercrombie at the conclusion of the

inspection.

Areas

examined during the inspection

and our findings are discussed

in the

enclosed

inspection report.

Within these

areas,

the inspection consisted of

selective

examinations of procedures

and representative

records,

interviews with

personnel,

and observations

by the inspector.

During the inspection, it was found that certain activities under your license

appear to be in noncompliance with NRC requirements.

This item and references

to pertinent requirements

are listed in the Notice of Violation enclosed

here-

with as Appendix A.

This notice is sent to you pursuant to the provisions of

Section 2.201 of the NRC's "Rules of Practice," Part 2, Title 10,

Code of Federal

Regulations.

Section 2.201 requires

you to submit to this office, within 20

days of your receipt of this notice,

a written statement

or explanation in reply

including:

(1) corrective steps

which have been taken by you and the results

achieved;

(2) corrective steps

which will be taken to avoid further noncom-

pliance;

and (3) the date

when full compliance will be achieved.

In accordance

with Section 2.790 of the NRC's "Rules of Practice," Part 2,

Title 10,

Code of Federal Regulations,

a copy of this letter and the enclosed

inspection report will be placed in the NRC's Public Document Room. If this

report contains

any information that you (or your contractor) believe to be

proprietary, it is necessary

that you make

a written application within 20 days

to this office to withhold such information from public disclosure.

Any such

application must include

a full statement

of the reasons

on the basis of which

it is claimed that the information is proprietary,

and should be prepared

so

that proprietary information identified in the application is contained in a

separate

part of the document.

If we do not hear from you in this regard within

the specified period, the report will be placed in the Public Document Room.

S

0

0

Tennessee

Valley Authority

I

Shoul'd you have any questions

concerning this letter,

we will be glad to discuss

them with you.

Sincerely,

C. E.

Mu

hy,

Ch ef

Reactor Construction

and Engineering

Support Branch

Enclosures:

1.

Appendix A, Notice of Violation

2.

Inspection Report Nos. 50-259/79-42,

50-260/79-42

and 50-296/79-42

cc w/encl:

H. L. Abercrombie

Plant Superintendent

P. 0.

Box 2000

Decatur,

AL

35602

D. E. McCloud, Project Engineer

l

400 Chestnut Street

Tower II

Chattanooga,

TN

37401