ML18019A268
| ML18019A268 | |
| Person / Time | |
|---|---|
| Site: | Harris |
| Issue date: | 06/17/1985 |
| From: | Blake J, Hallstrom G NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II) |
| To: | |
| Shared Package | |
| ML18019A266 | List: |
| References | |
| 50-400-85-22, NUDOCS 8507110805 | |
| Download: ML18019A268 (18) | |
See also: IR 05000400/1985022
Text
gp,g REGS,
(4
tp0
Cy
C
O
Cy
Yg
>>w*w+
UNITED STATES
NUCLEAR REGULATORY COMMISSION
REGION
11
101 MARIETTASTREET, N.W. pi
ATLANTA,GEORGIA 30323
Report No.:
50-400/85-22
Licensee:
Carolina
Power and Light Company
411 Fayetteville Street
Raleigh,
NC
27602
Docket No.:
50-400
Facility Name:
Shearon
Harris
Inspection
Conducted:
May 28 31,
1985
License No.:
CPPR-158
Inspector:
G. A.
H
s
Approved by:
~
~
J.
e, Sect
o
ng
ring Branc
Oiv s on of Rea
o
Safety
SUMMARY
ate Signed
Scope:
This routine,
unannounced
inspection entailed
38 inspector-hours
on site
in the
areas
of construction
progress,
licensee
action
on previous
enforcement
matters,
safety-related
piping
procedures,
safety-related
structures,
and
licensee identified items (50.55(e)).
Results:
Two violations
were identified
"Inadequate
Procedure
for Welding
Stainless
Steel
Piping", - paragraph
6.b,
and "Failure to Follow Procedure
for
Control of Welding Consumables"
paragraph
7.g.
8>>~ii 0805 8506i9
R
ADOCK 08000000
6
PDR'I
7
~
1
I
Cr
A
1
't
REPORT DETAILS
Persons
Contacted
Licensee
Employees
"R. A. Watson,
Vice President,
Harris Project
"R.'. Parsons,
Project General
Manager,
Completion Assurance
- N. J. Chiangi,
Manager of Quality Assurance/Quality
Control
(QA/QC)
Harris Plant
- R. Hanford,
Manager,
Welding
- D. A. McGaw, Superintendent,
~A. H. Rager,
Manager
Construction
Inspection (CI)
P.
Cook, Senior
QA/QC Specialist (Central Control)
E.
C. Mitchell, Resident
Engineer - Second Shift
J. Evatt, Welding Engineering
Superintendent
Second Shift
- E. L. Betz,
QC Supervisor
- M. D. Vernon, Superintendent - QC
- L. P.
Capps,
Superintendent
Materials
- K. A. Douglas,
QA/QC Specialist
"C. K. Wright, Regulatory Compliance Specialist
Other
licensee
employees
contacted
included
construction
craftsmen,
engineers,
technicians,
and office personnel.
Other Organization
- J.
P. Kirk, Project Administrator, Daniel Construction
Company
NRC Resident
Inspector
- R. L. Prevatte
"Attended exit interview
Exit Interview
The inspection
scope
and findings
were
summarized
on
May 31,
1985, with
those
persons
indicated
in paragraph
1 above.
The inspector described
the
areas
inspected
and
discussed
in detail
the
inspection
findings listed
below.
No di ssenting
comments
were received
from the licensee.
(Open)
Inspector
Followup Item 400/85-22-01,
Housekeeping
in Cable Trays-
paragraph
5.
(Open)
Violation 400/85-22-02,
Inadequate
Procedure
for Welding Stainless
Steel
Piping
paragraph
6.b.
(Open)
Inspector
Followup
Item 400/85-22-03,
Documentation
on
HVAC Duct
Welds - paragraph 7.d.(2).
(Open) Violation 400/85-22-04,
Failure to Follow Procedure
for Control of
Welding Consumables
- paragraph
7.g.
The licensee
did not identify as proprietary any of the materials
provided
to or reviewed by the inspector during this inspection.
3.
Licensee Action on Previous
Enforcement Natters
a.
(Closed)
Unresolved
Item 400/83-25-08,
Potentially
Inadequate
Field
Change
Request
(FCR)
This
item
concerned
the
adequacy
of welding
acceptance
criteria
established
by FCR-H-979,
Revision
3 versus
compliance
with require-
ments of the
AWS Dl. 1 structural
welding code.
The inspector
had previously reviewed background
information concerning
NRC approval
of welding visual
acceptance
criteria
incorporated
in
CAR-2165-A-003,
Revi sion
10
(Inspection
Reports
Nos.
400/84-19,
400/84-35,
and 400/85-01).
The inspector
reviewed background
documentation
and acceptance
criteria
of FCR-H-979 in comparison
to the
AWS Dl. 1
Code
and
CAR-2165-A-003.
The inspector
concluded that
no criteria involved was less
stringent
than established
by CAR-2165-A-003.
This item is considered
closed.
b.
(Open)
Unresolved
Item 400/85-12-01,
Adequacy of Corrective Action to
Protect
Permanent
Plant Equipment
This item concerns
adequacy of corrective actions to protect permanent
plant
equipment.
During
an earlier
inspection
the
inspector
noted
damage to the cooling fins of HVAC Air Handler
No.
1AH-4 at elevation
286
on
Unit
1
containment.
This
damage
was
apparently
due
to
unauthorized
climbing
on
permanent
plant
equipment
by construction
craftsmen
who were completing piping weldments
on top of air handler
The
inspector
had
been
informed that
climbing
on
permanent
plant
equipment
was
considered
an
unauthorized
live construction
load
and
prohibited
by paragraph
3. 10 of WP-48
"Temporary
Construction
Loads
Supported
from Permanent
Plant Components"
unless
the responsible
area
engineer
granted
a construction
load release.
Also, that
an earlier
gA
Surveillance
had
identified
unauthorized
application
of temporary
construction
loads (including unauthorized
climbing on
permanent
plant
equipment)
as
the
root
cause
of
damage
to other
permanent
plant
equipment.
Supporting
documentation
included written notification to
~
~
!'
all site personnel
prohibiting unauthorized
climbing on equipment which
was
issued
by the Daniel Project
General
Manager
on October 3,
1984,
and
Nonconformance
Report
(NCR)
No.
85-0490
issued
February
22,
1985,
which identified continuing problems in this area.
0'ognizant
licensee
personnel
informed
the
inspector
that
No.
85-0946
had
been
issued
on April 4,
1985,
and identified several
instances
of temporary
or live construction
loads
being
applied
to
permanent
plant
equipment
without proper
authorization.
Damage
to
equipment
had resulted
in one instance.
Corrective actions
included
modifications to WP-48 to improve its effectiveness
(each discipline is
now responsible
for issuing
load
releases
pertinent
to its work);
followup training of all
area
engineers
to
WP-48
requirements,
and
followup written notification
to all
site
personnel
prohibiting
unauthorized
climbing on permanent plant equipment.
Cognizant licensee
personnel
informed the inspector that all corrective
actions
of
No. 85-0946
were considered
complete,
The inspector
responded
that
a
construction
craftsman
had
been
observed
climbing
on
permanent
plant
equipment
without
proper
authorization
during this
inspection
as
reported in paragraph
5.
Cognizant licensee
personnel
stated that this
could be viewed as
an isolated
example
when considering
an overview of
corrective
actions
accomplished.
The inspector
informed the licensee
that this item will remain
open
pending
reassessment
of adequacy
of
corrective actions during
a future inspection.
4.
Unresolved
Items
Unresolved
items were not identified during this inspection.
5.
Independent
Inspection
(92706)
Construction
Progress
The inspector
conducted
a general
inspection of the Unit 1 containment
and
reactor
power block outside containment to observe construction
progress
and
construction
activities
such
as
welding,
material
handling
and control,
housekeeping
and storage.
During the
above
inspection,
the
inspector
observed
a
HVAC construction
craftsman climbing on appurtenances
of exhaust
fan E-ll-1-4B-NNS in the fuel
handling building.
Cognizant licensee
personnel
informed the inspector that
a WP-48 load release
had not been
issued.
The inspector
reviewed documenta-
tion indicating that the craftsman
involved had
been
aware of restrictions
regarding live and temporary
construction
loads
on permanent
plant equip-
ment.
This item is further discussed
in paragraph
3.b.
During the above inspection,
the inspector
observed
a 2"x 12" x 8'caffold
board
on top of installed cable in cable tray no.
EGB-31 at column 33 and JV
line and approximate elevation
276 in the reactor auxiliary building (RAB).
After investigation,
cognizant
licensee
personnel
informed
the
inspector
that
no safety-related
cables
were
involved
and
no
damage
to installed
cables
had been identified.
However, that the condition observed
was not in
conformance with general
housekeeping
procedure
AP-X-02 and design drawing
No.
B060 sheet
16.
The inspector
stated that
NRC concern
in this area will
be identified as inspector followup item 400/85-22-01"
Housekeeping
in Cable
Trays
6.
Safety-Related
Piping Procedures
(Unit 1)(55161)
The
inspector
reviewed
welding
procedure
specifications
and
quality
assurance
procedures
for safety-related
piping
as
described
below to
determine whether applicable
code
and procedure
requirements
were being met.
The
applicable
code
for safety-related
piping is the
BLPV Code,
Section III, Subsections
NC and
ND, 1974 edition with Addenda through Winter
1976
(74W76).
Non-nuclear
safety-related
high energy piping identified as
seismic
Category
1 is fabricated
to ANSI B31.1
(73S73)
and post-weld
heat
treated
when required to ANSI B31. 1 (77W77).
a.
Welding
Procedure
Speci.fications
(WPSs)
applicable
to
current
production welds were selected
for review and comparison with the
Code
as follows:
WPS
Process
1/ 2/ 3/
~PR
1BA5, Rev.
15
8B2,
Rev.
15
8B4,
Rev.
9
8BA6, Rev.
6
8BA7, Rev.
9
lA4, Rev.
11
1B1,
Rev.
13
GTAW/SMAW
GTAW
GTAW/SMAW
GTAW/SMAW
1, 5, 28B,
28C
6,
6A, 6B,
6C
7
8
54
1, 66,
66A
5,
5A
1/GTAW Gas Tungsten Arc-Welding
2/SMAW Shielded
Metal Arc-Welding
The
above
WPSs
and their supporting
Procedure
gualification
Records
(PgRs)
were
reviewed
to ascertain
whether
essential,
supplementary
and/or
nonessential
variables,
including
thermal
treatment,
were
consist'ent
with
Code
requirements;
whether
the
WPSs
were
properly
qualified
and their supporting
PgRs
were
accurate
and retrievable;
whether all
required
mechanical
tests
had
been
performed
and
the
results
met
the
minimum
requirements;
whether
the
PgRs
had
been
reviewed
and certified
by appropriate
personnel
and;
whether
any
revisions
and/or
changes
to nonessential
variables
were
noted.
WPSs
are qualified in accordance
with ASME Section
IX, the latest edition
and addenda
at the time of qualification.
b.
The
below listed
documents
were
reviewed
to ascertain
whether
the
welding program for safety-related
piping
had
been
approved
by the
licensee
and whether adequate
plans
and procedures
had
been established
to assure
that welding would be controlled
and accomplished
consistent
with commitments
and regulatory requirements.
Documents
No.
Title
Rev.
18
Rev.
14
Rev.
19
Rev.
13
Qualification of Welding and
Brazing Procedures
Qualification of Welders
and
Welding Operators
Welding Material Control
Procedure for Post-Meld Heat
Treatment
Rev.
18
General
Welding Procedure for
and Alloy Steel
Pipe
Rev.
19
General
Welding Procedure for
Stainless
Steel,
Nickel Base
and Nonferrous Weldments
Rev.
11
Procedure for Welding Equipment
Control
Rev.
14
Procedure for Repair of Base
Materials
and Weldment
MP-ll, Rev.
11
No. 030,
Rev.
10
SS No. 031,
Rev.
9
WP-102,
Rev.
13
WP-112,
Rev.
10
Training and Qualification of
Metallurgy/Welding Engineering
and Support Personnel
Field Fabrication
and Erection of
Power Piping
Requirements
for field welding of
Category
1, 2,
and 3, or Code
Classes,
1, 2,
and
3 piping
components,
systems at the
SHNPP Project
Installation of Piping
Control of Materials
and Equipment
that
may be harmful to stainless
steel
~
~
CQC-19,
Rev.
14
CQC-20,
Rev.
3
Weld Control
Post-Weld
Heat Treatment
During the
above
inspection,
the inspector
noted that
Rev.
19
was deficient
due to omission
of the
1.0
percent
maximum
requirement
of upper-tier specification
No.
031.
This requirement
is imposed to ensure
adequate
backpurge
when making butt welds with the
GTAW process.
Cognizant licensee
personnel
informed the inspector that
the deficiency was due to a typographical
error in paragraph
4.7.2. 1 of
'evision
19,
which was
issued
on
March 22,
1985.
Further, that as of
December
29,
1983,
a hold point had been established
requiring that
inspectors
check purge
gas at fitup for all open butt stainless
steel
joints.
Further, that
even
though
CQC-19 referenced
MP-07 to enforce
this requirement,
QC inspectors
involved were knowledgeable
of and had
enforced
the
1 '
percent
maximum
oxygen 'equirement.
The inspector
noted that this matter was
a lack of conformance to 10
CFR, Appendix B,
Criterion V,
and
would
be
identified
as
violation
400/85-22-02
"Inadequate
Procedure for Welding Stainless
Steel Piping."
7.
Safety-Related
Structures
(Unit 1)
The
inspector
observed
welding activities for safety-related
structural
steel
and
HVAC ductwork, located inside containment,
and Seismic
1 supports
(pipe,
instrumentation,
and cable tray),
located
inside containment
and in
the reactor auxiliary building,
as
described
below to determine
whether
applicable
code
and procedure
requirements
were being met.
The applicable
code for structural
steel
and Seismic
1 supports is the
AWS D1.1 Structural
Welding
Code,
1975 revision.
The applicable
code for HVAC ductwork is the
AWS D1.3 Structural
Welding Code for Sheet Steel,
1978 revision.
a
0
Welding
Procedure
Specifications
and
Quality
Assurance
Procedures
(55151)
(1)
The
WPS
Review
documented
in paragraph
6.a for safety-related
piping
is
also
applicable
to
safety-related
structures.
Additional
WPSs
applicable
to the
weld joints listed in para-
graph 7.d.
were selected for review and
comparison
with the
Code
and
AWS Dl.3 as follows:
WPS
1Fl,
Rev.
11
1F2,
Rev.
2
525M1,
Rev.
3
525M2,
Rev.
3
Process
1/ 2/
= FCAW
FCAW
GMAW
~PR
63,
63A
63,
131
62A, 62B,
62C,
62D
86, 86A, 86B
1/
FCAW - Flux cored arc - welding
2/
GMAW Gas metal arc
welding
The
above
WPSs,
and their
supporting
Procedure
Qualification
Records
(PQRs)
were
reviewed
to
ascertain
whether
essential,
supplementary
and/or
nonessential
variables,
including
thermal
treatment,
were
consistent
with
Code
requirements;
whether
the
WPSs
were
properly qualified
and their
supporting
were
accurate
and retrievable;
whether all required
mechanical
tests
had
been
performed
and the results
met the minimum requirements;
whether
the
had
been
reviewed
and certified by appropriate
personnel
and;
whether
any
revisions
and/or
changes
to
nonessential
variables
were noted.
WPSs
1Fl and
1F2 are qualified
in accordance
with ASME Section
IX, the latest edition and addenda
at the time of qualification.
WPSs
525M1
and
525M2 are qualified in accordance
with
AWS D1.3,
1978 Revision.
(2)
The
quality
assurance
procedures
review
documented
in
para-
graph 6.b for safety-related
piping is also applicable to safety-
related
structures.
Additional procedures
reviewed to ascertain
whether the welding program for safety-related
structures
had
been
approved
by the licensee
and whether adequate
plans
and procedures
had
been
established
to assure
that welding would be controlled
and
accomplished
consistent
with
commitments
and
regulatory
requirements
were
as follows:
Document
No.
Title
Rev.
10
Rev.
6
General
Welding Procedure for
Structural
Steel
(Seismic,
Non-seismic)
and Hangers
General
Welding Procedure
for
HVAC Duct Systems
(Seismic,
Non-seismic)
WP-110,
Rev.
12
WP-139,
Rev.
2
WP-140,
Rev.
1
CQC-18,
Rev.
1
Installation of Q and
Non-Q
Pipe Hangers
and Support
Seismic
Pipe Hanger Work
Package
Preparation
Field Engineering
Review of
Documentation of Seismic
Pipe
Hangers
and Supports
Weld Control for Seismic
Class
1 and Seismically
Designed
Structural
(Reg.
Guide 1.29)
QCI-18.2,
Rev.
0
CAR-2165-A-003,
Rev.
10
Seismic
Pipe Hanger Inspection
Documentation
System
Weld Inspection Criteria
SS No. 033,
Rev.
9
Structural
Welding for
Permanent
Plant Construction
b.
Observation of Work Within Containment
(55153)
The
below
listed
were
examined
in-process
to verify work
conducted
in
accordan'ce
with traveler,
welder identification
and
location,
welding
procedures,
WPS
assignment,
welding technique
and
sequence,
materials identity, weld geometry, fit-up; temporary attach-
ments,
gas purging, preheat,
electrical characteristics,
shielding gas,
welding equipment condition, interpass
temperature,
interpass
cleaning,
process
control
systems,
qualifications of inspection
personnel,
and
weld history records.
Drawin
No.
Weld No.
Status
2166B060
SH56C
H1933
IS/1-CS-260
FCR-AS-6481
R/0
2168-G-198501
FCR-AS-4081
4 x 4 TS to
Embed
FW-3
(2 x 2 angle to 3 x 3 TS)
2166-B-060
SH53
(B52 unistrut to TS)
Fill passes
First pass
First pass
C.
Observation of Work Outside Containment
(55154)
The
below
listed
wel ds
were
examined
in-process
to verify work
conducted
in
accordance
with traveler,
welder
identification
and
location,
welding
procedures,
WPS
assignment,
welding technique
and
sequence,
materials identity, weld geometry, fit-up; temporary attach-
ments,
gas purging, preheat,
electrical characteristics,
shielding gas,
welding
equipment
condition,
interpass,
temperature,
interpass
cleaning,
process
control
systems,
qualifications
of
inspection
personnel,
and weld history records.
Drawin
No.
Weld No.
Status
A"2-236-1-CW-H-558
R/2C mod 4
A-7-261-1-PDH-4302
R/OA mod
3
A-2-236-1-CW-H-294
R/1B Mod
1
FJ1
FJ2
FJ3
FJl
FJ2
FJ4
FJ5
Fill passes
Fitup/tacks
Fitup/tacks
Fill passes
Fill passes
Fill passes
Fill passes
~
~
~
~
~
F-2"216-1-4-FP-H-1112
R/5F mod
1
FJ2
First Pass
A-5-26-1-PD-H-4286
CC-236-1 "CC-H-1473
FJ4
FJ3
FJ4
First Pass
Fit-up tacks
Fir st Pass
d.
Visual Inspection of Welds (55155)
The inspector visually examined
completed
as described
below to
determine
whether applicable
code
and procedure
requirements
were being
met.
(1)
The below listed welds
were
examined relative to the following:
location,
length,
size,
and
shape;
surface
finish
and
appearance;
transitions
between different wall thicknesses;
reinforcement height
and
appearance;
joint configurations
on
permanent
attachments
and
structural
supports;
removal
of
temporary
attachments,
arc
strikes
and
spatter;
finish-
grinding or machining of weld surface,
surface finish and
absence
of wall thinning; surface defects,
cracks,
laps,
lack of penetra-
tion, lack of fashion,
porosity,
slag,
oxide film and
undercut
exceeding
prescribed limits.
Reactor Auxiliary Building
Seismic
1 Han ers
PD"H-4312-FJ3
PD-H-4312-FJ4
PD-H-4312-FJ5
CW-H-294-FJ2
CW-H-294-FJ3
SW-H-558-FJ50*
SW-H-558-FJ52"
Unit
1 Containment
Structural
Steel
Re air Welds**
Dwg.
No. 2168-G-219
R/6
Dwg.
No. 2168-G-320
(NCR 85-1174)
Repair
weld No.
1 to A
Repair weld No.
1 to 3
Repair weld No.
2 to 3
10
Unit
1 Containment
HVAC Ductwork
Work Packa
e No.
PC Mk. No.
Weld No.
HV/1-G-519-503-006
HV/1-G-519-503-006
HV/1-G-519-503-006
41-1
41
42
Duct A to Duct A
Duct A to Duct A
Duct A to Duct A
" See
paragraph
7.g for report
on Stress
Relief Activities
- See
paragraph
7.h for report
on Repair Weld Activities
(2)
guality records for the above welds were examined relative to the
following:
records
covering
visual
and
dimensional
inspection
indicate that the specified inspection
were completed;
the records
reflect adequate
weld quality; history records
are adequate.
During the above examination cognizant licensee
personnel
informed
the inspector that quality data for the
be
located
during this inspection.
The
inspector
stated
that
pending
review of the quality data
involved this matter will be
identified as inspector followup item 400/85-22-03
"Documentation
on
Welding Filler Material Control (55152)
The
inspector
reviewed
the
CP8 L
program
for
control
of welding
materials
to
determine
whether
materials
were
being
purchased,
accepted,
stored
and
handled
in accordance
with
gA procedures
and
applicable
code
requirements.
The
following specific
areas
were
examined:
Purchasing,
receiving,
storing,
distributing
and
handling
procedures,
material
identification;
and
inspection
of welding
material
issuing stations.
Welding
material
purchasing
and
receiving
records
for
the
following materials
applicable
to
the
weld joints listed
on
paragraph 7.b., 7.c.,
and 7.d.
were reviewed for conformance with
applicable
procedures
and code requirements:
~Te
E7018
E7018
E7018
Size
1/8"
0-045"
3/32"
3/32"
Heat
Lot
Batch/No.'7425
21531
~
~
f.
We 1 der Qual ificati on (55157)
The inspector
reviewed the
CP&L program for qualification of welders
and welding operator for compliance
with QA procedures
and
ASME Code
requirements.
The
following welder qualification
status
records
and
"Records
of
Performance
Qualification Test"
were
reviewed relative to the
joints-listed in paragraph 7.b., 7.c.,
and 7.d.
Welder
S mbol
WPS
J-61
G-32
SA-19
I-91
F-45
J-24
J-69
G-72
I-48
SN-1
.
SB-56
I-7
J-7
1F2
1F2
1A4
1A4
1A4
1A4
1A4
1A4
lA4
1A4
1A4
1A4
1A4
lA4
g.
Weld Heat Treatment
(55156)
The inspector
observed
post-weld
heat
treatment activities for welds
listed below to determine
whether weld area is instrumented to provide
time-temperature
records for the duration of the entire heat
treatment
cycle;
temperature
monitoring
instruments
are
properly calibrated;
sufficient
temperature
measuring
devices
and
used;
post-weld
heat
treatment
(PWHT) temperature
and holding time is specified,
is adhered
to;
maximum initial temperature,
heat-up
and
cool-down
rates
are
specified
and
are
adhered
to;
temperature
records
being
generated
reflect adherence
to regulatory requirements.
Drawin
No.
Weld No.
A-3-216-2-SW-2-H-558
A-3-216-2-SW-2-H-558
FJ50
FJ52
During the
above
inspection,
the inspector
noted quality data
was in
error in that welding material
requisition
(WMR) form Nos.
326601
and
326602
had been incorrectly issued to welder J-24 to enable
attachment
of the thermocouples
for the post-weld heat treatment.
The
WMRs indi-
cated that the
WPS to
be
used
was the
FCAW procedure
1F2
even
though
welder J-24 is not qualified to procedure
1F2 and
E7018
SMAW electrodes
were issued.
Further this error was not identified by the
QC inspector
12
during inspection of the stress relief involved and preparation of the
QA/QC field report required
by CQC-20,
Rev.
3.
Therefore,
requirements
of
"Welding Material
Control"
had
not
been
met
by the craft
foreman in preparing the
WMR (MP-03 Section 4.5)
and the weld material
issue
station attendant
on issuing the
E7018 electrodes
(MP-03 Section
4.7).
After
investigation,
cognizant
licensee
personnel
informed
the
inspector
that
the
thermocouples
had
been
attached
using
WPS
No.
1A4 for which welder
J-24
is qualified
and
for which
E7018
electrodes
are specified.
Further that the
FCAW WPS No.
1F2 had been
used to weld the joints involved and the
WMR error had occurred
due to
the craft forman's misinterpretation
of paragraph
3. 12. 1 of the MP-04
procedure for post weld heat treatment.
The inspector
stated that this
matter was
a lack of conformance to
10 CFR 50, Appendix B, Criterion V,
and would
be identified as violation 400/85-22-04
"Failure 'to Follow
Procedure for Control of Welding Consumables."
h.
Special
Welding Activities (5515B)
The inspector
examined
special
welding activities including weld repair
as described
below to determine
whether applicable
code
and procedure
requirements
were being met.
The below listed repair welds were examined relative to the following:
welding procedure
used;
repair welding procedure
includes all pertinent
requirements;
repair
welding
procedure
qualification; repair welder
performance
qualifications
ANI witnessed
performance
qualification;
repair
area
does
not
exceed
limits;
base
and filler material
as
specified;
base material repairs
documented;
NDE performed,
and records
completed.
Drawin
No.
Weld No.
2168-G-219
R/6
2168-G-320
(NCR-85-1174)
Repair Weld No.
1 to A
Repair Weld No.
1 to 3
Repair Weld No.
2 to 3
Within the areas
examined
one violation was identified as reported
on
paragraph
7.g.
No deviations
were identified.
8.
Licensee Identified Items (92700)
Prior to the inspection,
the licensee identified the following items under
~
~
~
~
13
a.
(Open)
400/CDR 83-104,
Defective
on
480V Switchgear - (10 CFR 50.55(e))
One
March 4,
1983,
the licensee
notified Region II of a 50
F 55(e) item
concerning
vendor
weld deficiencies
in the
transformer
sections
of
seismically-designed
class
1E and
nonclass
1E switchgear
(transformers
lAl, 1CA2-SA,
1B1,
and
1B3-SB).
The final report
was
submitted
on March 28,
1985.
Corrective
actions
required
reinspection
by
the
vendor
and
the
licensee,
repair of weld defects,
correction to drawings/documentation,
and
engineering
analyses
to justify actions
taken.
On
review of
corrective
actions
the
inspector
questioned
the justification for
accepting
several
welds which were not reinspected
due to being covered
with
an
approximately
1/4
inch thick coating of shellac.
Cognizant
licensee
personnel
informed
the
inspector
that this
issue
would
be
addressed
and
a
supplement
to
the
final
report
transmitted
to
Region II.
This item remains
open.
(Open)
Item 400/CDR 83-127,
Weld Deficiencies
in Unit
1 Chilled Water
Valve (10 CFR 50.55(e)).
On April 7,
1983,
the
licensee
notified Region II of
a 50.55(e)
item
concerning
vendor
shop weld defects
in a
HVAC chi 1-led water valve.
The
final
report
was
submitted
on
October 31,
1983.
Due
to later
identification of shop weld deficiencies
on other
three-way chilled
water
valves
purchased
under
P.O.
NY-435176
the
licensee
informed
Region II on January
18,
1985, that this item was considered
re-opened
and supplemented
by new 50.55(e)
item 400/CDR 85-199.
C.
The inspector
requested
information on the status of this item and was
informed that corrective actions
were not complete.
This item remains
open.
(Open)
400/CFR
83-143,
Bus
Duct and Transformer
Weld Deficiencies
E
On
September
2,
1983,
the license notified Region II of a potential
50.55(e)
item concerning
vendor
weld deficiencies
in sections
of bus
duct nos.
CC-1 and
CC-2 and transforms
nos.
1Dl, 1D2,
1El and
1E2.
The
final report was submitted
on January
12,
1984,
and indicates that the
item was
evaluated
and considered
not-reportable.
Cognizant
licensee
personnel
informed the inspector that no rework was required
due to the
discrepancies
identified
since
engineering
analyses
had
established
considerably
greater
than required factor s of safety for
the joints involved with
no credit
taken for any
length
of weld
exhibiting deficiencies.
On
review of the engineering
analyses
the
inspector questioned
the acceptance
of the
PC P9 (box member)
assembly
for the transformers
involved since
a considerable
portion (up to 50%)
of the welds involved was not able to be inspected
due to configuration
of
the
fabrication.
Cognizant
licensee
personnel
informed
the
14
inspector that acceptance
of these
items
was additionally supported
by
seismic testing but that the test reports would not be available until
after the close of this inspection.
This item remains
open
pending
review of the test reports involved.
d.
(Closed)
Item
400/CDR
84-174,
Stainless
Steel
Olets
guestionable
Starting Material - (10 CFR 50.55(e)).
On
May 15,
1984,
the licensee
notified Region II of'
50.55(e)
item
concerning
vendor
supplied
stainless
steel
olets which
had not been
manufactured
from starting material
purchased
to ASME NCA-3800 require-
ments.
The final report was submitted
on June
14,
1984.
On review of
corrective
action
during
a
previous
inspection
(Report
No. 50-400/
84-30),
the
inspector
had
requested
a
review of potential
generic
significance in light of item 400/CDR 84-178
as
discussed
below.
The
inspector
reviewed
the
licensees
analysis
and
concluded
that all
potential similar discrepancies
had
been investigated.
None other than
those
reported
below
have
been
identified at
Plant
Harris.
The
fittings involved were returned to the vendor.
This item is considered
closed.
e.
(Closed)
Item
400/CDR
84-178,
Sockolets
and Meldolets
guestionable
Starting Material - (10 CFR 50.55(e)).
On June
19,
1984,
the license notified Region II of a 50.55(e)
item
concerning
vendor
supplied
stainless
steel
weldolets
and
sockolets
which had not been manufactured
from staring material
purchased
to ASME
NCA-3800 requirements,
The manufacturer of the weldolets
and sockolets
also manufactured
the deficient olets
reported
in
CDR 84-174.
Of the
139 fittings involved,
132 were returned to the vendor for performance
of the required
chemical
overchecks.
The inspector
examined acceptable
certified
material
test
reports
(CMTRs)
for the
seven
fittings
remaining on-site.
The final report
was submitted
on January
30,
1985.
The
report
has
been
reviewed
and
determined
to
be
acceptable
by
Region II.
The inspector
held discussions
with responsible
licensee
representatives,
reviewed
supporting
documentation,
and
observed
representatives
samples
of work to verify that the corrective actions
identified in the report have
been completed.
9.
Previously Identified Inspector
Followup Items
(Open) Inspector
Followup Item 400/85-12-02,
Arc Strikes
on Refueling Cavity
Liner Plate
3
This
item concerns
base-metal
arc strikes
on the refueling cavity liner
plate.
The
inspector
reviewed
modifications
to section
6.4.4 of
CgC-19
requiring
a final visual walkdown to verify that fuel pool liner plates
are
free from arc strikes,
dents,
scratches,
foreign materials,
etc.
Cognizant
licensee
personnel
informed the inspector that corrective
actions to repair
all base
metal arc strikes identified was not complete.
This item remains
open pending review of completed corrective action.