February 13, 1979 Office of the General Counsel U.S. Nuclear Regulatory Commission Washington, DC 20555 In the thatter of Carolina Power and Light Company (Shearon Harris Nuclear Power Plant, Units 1, 2, 3 and 4)

Docket Nos. 50-400, 50-401, 50-"402, 50-403 Gentlemen:

  • The captioned construction permit proceeding is now pending before the Comission except for the issue of, the management capability of the Applicant to design, constru'jt and operate the proposed facility which has been remanded to the Licensing Board to take further evidence.

George F. Trowbridge, Esq.

Dennis P.

Vgers Atomic Safety and Licensing Board Panel Atomic Safety and Licensing Appeal Board Docketing and Service Section cc w/encl:

Alan S. Rosenthal, Esq.

Dr. John H. Buck Michael C. Farrar, Esq.

Ivan W. Smith, Esq.

l1r. Glenn 0. Bright Dr. J.

V. Leeds, Jr.

Richard E. Jones, Esq.

Thomas Erwin, Esq..

Wake County Public Library 78o366 Q 95)'e have previously transmitted to you, for information purpose only, several memoranda from NRR regarding faulting at the site.

Enclosed for your further information are two additional NRR memoranda relating to faults at the site (January 25, 1979 and February 6, 1979). If further information discloses any possibility of these faults constituting serious

matters, we will promptly inform you.

There have been' number of faults discovered at the facility site, and to date, none of them have proven to be capable as defined in 10 CFR Part 100.

Dist Sincerely NRC Central Reis FF(2)

LPDR Chron(2)

Paton Shapar/Engelhardt DVassallo Christenbury/Sci'nto HSmith Charles A. Barth Barth Counsel for NRC Staff Cutchin SMiner

Enclosures:

As Stated.

OParr SBajwa WRegan OELD B"arri/'dmr"""'""'/iw/79 SURNAM29 ForIR hZC.318 (Rev. 9.33) hXCM 0240 OELD

'""R'e'i's""."""'

'//2/.7,9 V, $, OOVCRNMENT RRINTINO ORRICCI 1924 d2S 1dd

H

>> 3f~rz,('."QQ' 1

JAN 25 1979 Docket Nos; 50-400, 50-401, 50-402 and 50-403 Distribution Docket File LWR P3 File S. Niner H. Rushbrook F.

T. Cardone B. Jackson MEMORANDUM FOR:

Olan D. Parr, Chief, Light Water Reactors Branch No.. 3 Division of Project Management FROM:

Sydney Miner, Project Manager, Light Water Reactors Branch No. 3, Division of Project Management

SUBJECT:

FAULTS AT THE SHEARON HARRIS SITE On January 19, 1979 Hr. Bob Black phoned to report that from their investi-gations into the dam area faulting they identi.fied two additional faults.

As a result of mapping in the core trench on the downstream site a fault 4'as identified in core trench floor.'at,stations'+90 to 3+00.

This fault has been designated as Fault A-2.

In addition a fault that had initially been thought to be an extension of previously discovered Fault C (Fault C

was reported in Memo from S. Miner to 0. Parr dated November 21, 1970) was found to be a separate faul't.

This fault has been designated as Fault A-3.

,Based on,.the'i.r i,nvestigatiow,to date the,qppli,cant.concludes that both these faults are non capable within the. meaning of Appendix A to, 10 CFR-100.

Based on the information presented on this and the other faults in the dam area=we agree with the applicant that these faults are probably non capable.

A staff geologist will visit the site ta investigate the faults.

I recommend that the board be informed of these two faults.

t,~igip.'.iP<<'">

gyti~ey @iieet Sydney Miner, Pe.oject Hanager Light Water Reactors Branch flo. 3 Division of Project Management OfflCC~

OVIIMANK+

OATS+

LWR g3'LP SHiner:ch OPa rr" 1/ 2g /79 1/ LP /79

UNITED 51 ATES NUCLEAR REGUL'ATORY COMMISSION WASHINGTON. D. C. 20555 FE~ ('6 579 Docket Nos.

50-400.

50-401, 50-402 and 50-403 NOTE TO:

0.

Parr S. Miner F. William T. Cardone FROM:

A. Dromerick, Project Manager, Light"Water Reactors Branch No. 3, DPM

SUBJECT:

ADVISED OF FAULT FOUND AT SHEARON HARRIS On February 2, 1979, Mr. Black of Carolina Power 5 Light called to advise tha't they found a small fault and identified it as Fault F-2.

They believe this fault is not capable.

The= fault extends from Station 1 plus 97 to 2-plus 20 and terminates within the floor of the main dam.core trench.

The applicant will provide a formal report.

By copy of this memo I request that F. Williams notify OELD for Board Notification.

Q~C~~~~.pi:

A.

Dr omerick, 'Project Manager Light Water Reactors Branch No.

3 Division of Project Management cc:

D. Vassallo-