ML18003B129

From kanterella
Jump to navigation Jump to search
Package: Surry Independent Spent Fuel Storage Installation - Temporary Modification of Implementation of U.S. Nuclear Regulatory Commission Order EA-02-104
Date released: 01/11/2018 Download: ML18003B129


Letter to D. Stoddard Surry Independent Spent Fuel Storage Installation - Temporary Modification of Implementation of U.S. Nuclear Regulatory Commission Order EA-02-104
ML18003B131
Person / Time
Site: 07200002
Issue date: 01/03/2018
From: Dapas M
Office of Nuclear Material Safety and Safeguards
To: Stoddard D
Virginia Electric & Power Co (VEPCO)
Chen Y J
References
EA-02-104
Download: ML18003B131 (2)
Incoming Letter Virginia Electric and Power Company Surry Power Station ISFSI Temporary Modification of Interim Compensatory Measures for Order EA-02-104
ML18003B130
Person / Time
Site: 07200002
Issue date: 01/03/2018
From: Stoddard D
Virginia Electric & Power Co (VEPCO)
To:
Document Control Desk, Office of Nuclear Material Safety and Safeguards
Chen Y J
References
18-002, EA-02-104
Download: ML18003B130 (3)