Responds to Re Relief Requests (RR) 6,14,15,16 & 17.RR 6 Withdrawn,Rr 16 Previously Approved,Rrs 14 & 15 Granted & RR 17 Denied.Se & Technical Ltr Rept Encl
ML17354A355
Person / Time
Site: Turkey Point  NextEra Energy icon.png
Issue date: 12/04/1996
From: Hebdon F
NRC (Affiliation Not Assigned)
To: Plunkett T
FLORIDA POWER & LIGHT CO.
Shared Package
ML17354A357 List:
References
TAC-M94326, TAC-M94327, NUDOCS 9612090283
Download: ML17354A355 (3)


Text

'M,". T.

F. Plunkett President - Nuclear

.ision Florida Power and Light Company P.O.

Box 14000 Juno

Beach, Florida 33408-0420 December 1996

SUBJECT:

REVIEW OF INSERVICE INSPECTION PROGRAM RELIEF REQUESTS 6, 14, 15, 16, AND 17 TURKEY POINT UNITS 3 AND 4 (TAC NOS.

M94326 AND M94327)

'I,

Dear Mr. Plunkett:

In a letter dated December 14,

1995, you submitted several relief requests pertaining to the Inservice Inspection Prog'ram at Turkey Point Units 3 and 4.

Relief Requests 14 and 15 were revised and additional',information was provided by letter dated August 8, 1996.

With technical-assista'nce from our contractor, the Idaho National Engineering Laborato'ry',(INEL') w'eahaye r'eviewed the submittal against the requirements of,Se'ction XIhof<the American Society of Mechanical Engineers Boiler and Pressure Vessel Code pursuant to'Scot'ion 50.55a of Part 50 to Title 10 of the Code of Federal Re 'ulations'(CFR)o.",

The results of our review are provided in, the enclosed. safety-:evaluation, (SE)q'and technical letter report.

Relief Request 6 was withdrawn by letter dated 'Novwember 13, 1996,and Relief Request 16 was previously approved by letter dated <Maorch 11,"1996.

Relief Requests 14 and 15 involved relief, from"the required code examination area during volumetric and surface examination of welds during'.1994, inspections.

The code requirements could not'e met since portions of the, areas were inaccessible due to permanent physical obstructions, some welds could be examined from only one side due to the configuration of the

~.

component, and/or high attenuation of the ultrasonic sound.

To obtain complete volumetric coverage, modifications oV replacement of the-subject components would be required to perform the code examinations.'herefore, relief is granted, pursuant to 10 CFR 50.55a(g)(6)(i).

Relief Request 17 involved deviating from reexamination of the initially-selected components (Unit 4 steam generator welds in this case) over the service lifetime of the components.

We have concluded that the minimal burden associated with the examinations is insufficient to justify not examining the subject welds on the "A" Steam Generator and the licensee's proposed alternative contained in its relief is denied.

mWhig Pgg C~

Docket Nos.

50-250 and 50-251

Enclosures:

As stated cc w/enclosures:

See next page

'Pbi2090283 96i204 PDR ADQCK 05000250 P-'DR Document Name:

A: TP94326.ISI Sincerely, Oriqinal signed by Frederick J.

Hebdon, Director Project Directorate II-3 Division of Reactor Projects I/II Office of Nuclear Reactor Regulation DISTRIBUTION:

Docket File PUBLIC Turkey r/f SVarga ACRS JZwolinski GTnacy JJohnson Q GHill (4)

THarris[TLH3] (Ltr/SE see revious concurrence OFFICE PM: PDI I-3 LA:PDI OGC D: PDI I-3 EMGB NAME RCrotea BCl n

EHoller 4 FHebdon GBa chi

  • DATE Z. ~

96

~ 96 11/27 96 l~

96 ll 21 96 COPY Yes Yes No OFFICIAL RECORD COPY es No;,

Yes/No

2' l

~

y I

ll J

1 I

I hl 1

ll H

IIs h

1 ()'

E h

H

.i N

Mr. T. F. Plunkett Florida Power and Light Company TURKEY POINT PLANT CC:

M. S.

Ross, Attorney Florida Power

& Light 11770 US Highway 1

North Palm Beach, FL 33408 John T. Butler, Esquire

Steel, Hector and Davis 4000 Southeast Financial Center Miami, Florida 33131-2398 Mr. Robert J.

Hovey, Site Vice President Turkey Point Nuclear Plant Florida Power and Light Company P.O.

Box 029100 Miami, Florida 33102 Armando Vidal County Manager Metropolitan Dade County ill NW 1 Street, 29th Floor Miami, Florida 33128 Senior Resident Inspector Turkey Point Nuclear Generating Station U.S. Nuclear Regulatory Commission P.O.

Box 1448 Homestead, Florida 33090 Mr. Bill Passetti Office of Radiat'ion Control Department of Health and Rehabilitative Services 1317 Winewood Blvd.

Tallahassee, Florida 32399-0700 Mr. Joe Myers, Director Division of Emergency Preparedness Department of Community Affairs 2740 Centerview Drive Tallahassee, Florida 32399-2100 Regional Administrator, Region II U.S. Nuclear Regulatory Commission 101 Marietta Street, N.W. Suite 2900 Atlanta, Georgia 30323 Attorney General Department of Legal Affairs The Capitol Tallahassee, Florida 32304 Plant Manager Turkey Point Nuclear Plant Florida Power and Light Company P.O.

Box 029100

Miami, Fl orida 33102 Mr. H.N. Paduano, Manager Licensing

& Special Programs Florida Power and Light Company P.O.

Box 14000 Juno

Beach, Florida 33408-0420 Mr. Gary E. Hollinger Licensing Manager Turkey Point Nuclear Plant P.O.

Box 4332 Princeton, Florida 33023-4332 Mr. Kerry Landis U.S. Nuclear Regulatory Commission 101 Marietta Street, N.W. Suite 2900 Atlanta, Georgia 30323-0199