ML17353A520

From kanterella
Jump to navigation Jump to search
Refueling Outage ISI Rept.
ML17353A520
Person / Time
Site: Turkey Point NextEra Energy icon.png
Issue date: 01/03/1996
From:
FLORIDA POWER & LIGHT CO.
To:
Shared Package
ML17353A519 List:
References
NUDOCS 9601110201
Download: ML17353A520 (12)


Text

TURKEY POINT UNIT 3 1995 REFUELING OUTAGE INSERVICE INSPECTION REPORT Executive Summary The remaining scheduled ISI examinations for the first period were performed during the Turkey Point Unit 3 outage.

1004 of the A, B, and C steam generator tubes were eddy current tested. Two tubes were plugged during this outage.

The NIS-1 summary report includes an explanation of Reactor Coolant piping branch connection welds examined for a "set in" rather than a "set-on" configuration. The final examinations were performed to satisfy the corrective action on this issue.

The NIS-2 forms discuss the repairs and replacements which took place since the previous Unit 3 submittal and during the 1995 refueling/ maintenance outage.

Visual examination and functional testing of snubbers was completed in accordance with ASME Section XI and Technical Specifications. Visual examinations did not reveal any failures.

There were no snubber failures in the functional test sample.

The inservice inspection summary tables detail the class 1 and class 2 examinations performed during the second outage of the first period of the third ten-year interval.

Selected class 1 and class 2 vessels, piping and supports were examined with surface, volumetric, and visual examination techniques in accordance with Section XI of the ASME Boiler and Pressure Vessel Code and the Turkey Point Units 3 and 4 ISI Program.

960iif020i 960f03 PDR ADQCK 05000250 6 PDR

TURKEY POZNT UNZT 3 1995 REFUEL1NG OUTAGE Form NZS-1 Ownersl Data Report for Znserv9.ce Znspeetions

FORM NIS-1 OWNERS'ATA REPORT FOR INSERVICE INSPECTIONS Page 1 of 8

1. Owner: Florida Power and Light Company, 700 Universe Blvd. Juno Beach, Florida 33408
2. Plant: Florida Power & Light Company, Turkey Point Nuclear Power Plant, P.O. Box 4332, Princeton, Florida 33032 3 ~ Plant Unit:

Owner Certificate of Authorization (if required) 5 ~ Commercial 8ervice Date 6~ National Board Number for Unit:

7 ~ Components Inspected:

Component or Manufacturer Manufacturer State or Nat'l Appurtenance or Installer or Installer Serial Province Board No No. No.

Reactor Pressure Babcock and 3PSRV1 N/A N-160 Vessel Wilcox Steam Generator A Westinghouse 16A-5885-1 N/A N-740 FSGT-3001 3E2110A Steam Generator B Westinghouse 16A-5885-2 N/A N-742 FSGT-3002 3E2110B Steam Generator C Westinghouse 16A-5885-3 N/A N-744 FSGT-3003 3E2110C Pressurizer Westinghouse 3T200 N/A N-720 Reactor Coolant Pump Westinghouse 3P200C N/A N/A C

Regenerative Heat Westinghouse 3E200 N/A N/A Exchan er Reactor Coolant Bechtel N/A N/A N/A S stem Safety Injection Bechtel N/A N/A N/A S stem Chemical and Volume Bechtel N/A N/A N/A Control S stem

NIS-1 Report (continued) Page 2 of 8 1 ~ Owner: Florida Power & Light ComPany, 700 Universe Blvd. Juno Beach, Florida 3340B Plant: Turkey Point Nuclear Power Plant, P.O. Box 4332, Princeton, Florida 33032 2o 3.

4~

Plant Unit: ~

Owner Certificate of Authorization (if required)

5. Coamercial Service Date :
6. National Board Number for Unit:

Component or Manufacturer State or Nat'l Appurtenance or Installer Serial Province Board No No. No.

Residual Heat Bechtel N/A N/A N/A Removal Main Feedwater Bechtel N/A N/A N/A System Main Steam System Bechtel N/A N A N/A

8. Examination Dates  : Fro to
9. Inspection Period Identification  : First Period
10. Inspection Interval Identification: Third Interval, from
11. Applicable Edition of Section XI ~~ Addenda ~~
12. Date/Revision of Inspection Plan:
13. Abstract of examinations and test. Include a list of examinations and tests and a statement concerning status of work required for the inspection plan.

An Inservice Examination of selected Class 1, 2, and 3 components and piping systems of Florida Power and Light's Turkey Point Unit 3 was performed during the 1995 Refueling outage. This outage began on August 28, 1995, and ended on October 8, 1995. This was the second outage of the first period of the third ten year interval.

The components and piping systems examined were selected in accordance with the Turkey Point Third Ten Year Inservice Inspection Program, which was prepared in accordance with the requirements of the ASME Section XI, 1989 Edition.

Manual ultrasonic, radiographic, visual, magnetic particle, and liquid penetrant non-destructive techniques were used to examine components, piping, and their supports. The examinations were performed by FPL personnel, supported by examiners supplied by

NIS-1 Report (continued) Page 3 of 8 1 ~ Owner: Florida Power 8 Light Company, 700 Universe Blvd. Juno Beach, Florida 33408 Plant: Turkey Point Nuclear Po~er Plant, P.O. Box 4332, Princeton, Florida 33032 2.

3.

4.

Plant Unit: ~

Owner Certificate of Authorization (if required)

5. Comnercial Service Date :
6. National Board Number for Unit:

Raytheon Engineers and Constructors. A listing of examinations performed is attached to this summary.

Eddy Current examinations on Steam Generators A, B, and C were conducted by FPL personnel from September 14, 1995, through September 19, 1995. A total of 9576 tubes were examined. 2 tubes were plugged in Steam Generator B during this outage. See the attached NIS-BB report for the summary of examination results.

The Class 2 Feedwater Nozzle piping augmented examinations were conducted during this outage on all three Steam Generators. The entire area from the nozzle ramp to a point one pipe diameter out on the far side of the elbow was examined with ultrasonics. No reportable indications were found.

Snubber functional testing and visual examinations were conducted in accordance with Turkey Point Plant Technical Specifications.

Examination and testing services were supplied by Pacific Scientific, Inc. See the attached report for the summary of examination results.

System Pressure testing was conducted by the plant to applicable Plant Technical Specifications and Procedures.

The examinations performed for the first period meet. or exceed the requirements of Program B of Section XI.

14. Abstract of Results of Examinations and Tests.

One-third of the Reactor Pressure Vessel Closure Head studs, nuts, and washers were examined. No reportable indications were found.

NIS-1 Report (continued) Page 4 of 8 1 ~ thaM.r: Florida PoMer B Light Coo@any, 700 Universe Blvd. Jam Beach, Florida 33408 2.

3.

4~

Plant Unit: ~

Plant: Turkey Point Nuclear PoMer Plant, P.O. Box 4332, Princeton, Florida 33032 Owner Certificate of Authorization (if -required)

5. Camercial Service Date :
6. National Board Nwher for Unit:

The Inlet and Outlet manway bolting of all three steam generators were examined. The examinations were conducted at the request of the plant due to difficulty in removing the manway bolts from ICI generator. 28 of the ICI steam generator manway bolts were replaced. One bolt on IAI generator and 4 bolts on IBI generator were replaced. Baseline examinations were performed on new bolts. No reportable indications were found.

The upper shell to head weld and the adjoining longitudinal seam weld were volumetrically examined. No reportable indications were found.

The inner radius of the safety, relief, and spray lines were volumetrically examined. No reportable indications were found.

The Pressurizer support was visually examined. No reportable indications were found.

The bore and keyways of Reactor Coolant Pump 3C flywheel were volumetrically examined. No reportable indications were found.

A VT-3 examination was performed to look for accumulated boron crystals. A VT-2 exam was performed during plant startup in accordance with the approved relief request. The VT-2 and VT-3 examinations did not reveal any indications of leakage.

Reactor Coolant piping welds and supports were examined using surface, volumetric, and visual techniques. One linear indication was found using liquid penetrant techniques. The indication was determined to be a surface anomaly that had not been removed during construction. No reportable indications were found.

NIS-1 Report (continued) Page 5 of 8 1 ~ Owner: Flor ida Power 8 Light Company, 700 Universe Blvd. Juno Beach, Florida 33408 Plant: Turkey Point Nuclear Power Plant, P.O. Box 4332, Princeton, Florida 33032 20 3.

4~

Plant Unit: ~

Owner Certificate of Authorization (if required)

5. Coanercial Service Date :
6. National Board Hunber for Unit:

Chemical and Volume Control piping supports were examined using visual techniques. No reportable indications were found.

During the last Unit 3 refueling outage, FPL discovered that a number of Reactor Coolant branch connection welds were being examined incorrectly. The technique used during baseline examinations and previous outages was developed for a "set-in" branch connection configuration. Turkey Point's branch connections are of the "set-on" type. The ultrasonic technique used did not cover the Code required area.

FPL initiated a review of piping configurations as part of the corrective action. This review did not reveal any other types of weld configurations that had been misidentified. A second part of the corrective action was to reexamine the affected branch connections. During this outage, the remaining affected branch connections were examined, including the high stress Pressurizer surge line weld. Calibration blocks were borrowed from Prairie Island and Beaver Valley in order to properly examine the welds.

No reportable indications were noted. These examinations complete the corrective action initiated by FPL.

Component support RS-1 was not examined as scheduled. This support is located next to the pressurizer and was difficult to reach. Special scaffolding would have been required to obtain adequate access. Due to the high radiation in the area, this examination was canceled and another support will be chosen at a later date, if required.

Weld 4"-RC-1305-19 was not examined as scheduled. The weld was covered by a component support clamp. Due to the high radiation in the area, this examination was canceled and another weld will be chosen at a later date, if required.

The selection process to be used for substituted examination areas will follow Section XI rules.

NIS-1 Report (continued) Page 6 of 8

1. Owner: Florida Power & Light Company, 700 Universe Blvd. Juno Beach, Florida 33408 Plant: Turkey Point Nuclear PoMer Plant, P.O. Box 4332, Princeton, Florida 33032 2~
3. Plant Unit: ~

Omar Certificate of Authorization (if-required) 5~ CceNx.rcial Service Date :

6. National Board Number for Unit:

Steam Generator shell welds and inner radius sections were examined with the applicable surface and volumetric techniques.

Acceptable inclusions were found. No reportable indications were found.

Residual Heat Removal piping welds and supports were examined using surface, volumetric, and visual techniques. Inadequate thread engagement was found on one support. This was accepted as-is by engineering evaluation. No other reportable indications were found.

Main Steam piping welds were examined using surface techniques.

No reportable indications were found.

Main Feedwater piping welds and supports were examined using surface and volumetric techniques. No reportable indications were found.

Augmented examinations were performed on the piping off the Steam Generator Feedwater nozzles on all three loops. No reportable indications were found.

Safety Injection piping welds and supports were examined using surface, volumetric, and visual techniques. One support was found to have a bent integral attachment (examined under category F-A.) An engineering evaluation showed this integral attachment to have been welded into this position, possibly during construction, and was not a service related condition. No corrective action was required. A surface examination of the integral attachment was performed as part of the ISI plan. This

NIS-1 Report (continued) Page 7 of 8

1. Owner: Florida Power 8 Light Company, 700 Universe Blvd. Juno Beach, Florida 33408 Plant: Turkey Point Nuclear Po~er Plant, P.O. Box 4332, Princeton, Florida 33032 2~

3~

4, Plant Unit: ~

Owner Certificate of Authorization (if- required)

5. Camercial Service Date :
6. National Board Number for Unit:

examination showed numerous unacceptable indications. An expanded sample examination was performed. No reportable indications were found in that sample. No other reportable indications were found. The support was redesigned to eliminate the integral attachment and a new baseline examination was performed on the support.

The steam generator main steam nozzle to shell weld and the inner radius section were rescheduled for this outage. This was done to reduce future radiation exposure as the area was partially uncovered for other weld examinations. This substitution of exams meets the applicable Code requirements for Category C-B, Inspection Program B, and other applicable parts of Section XI.

15. Abstract of Corrective Measures The integral attachment with the surface examination indications found on the High Pressure Safety Injection line was removed.

The support, was redesigned to eliminate the integral attachments.

As part of the corrective action, the ISI group has been requested to examine additional supports and their integral attachments during the next outage.

No other corrective measures were required.

NIS-1 Report (continued) Page 8 of 8 1 ~ Owner: Florida Power 8 Light Cerpany, 700 Universe Blvd. Juno Beach, Florida 33408 Plant: Turkey Point Nuclear Power Plant, P.O. Box 4332, Princeton, Florida 33032 2.

3.

4.

Plant Unit: ~

Owner Certificate of Authorization (if required)

5. Comnercial Service Bate :
6. National Board Number for Unit:

We certify that a) the statements made in this report are correct, b) the examinations and tests meet the Inspection Plan as required by the ASME Code,Section XI, and c) corrective measures taken conform to the rules of the ASME Code,Section XI.

Certificate of Authorization No.

Expiration Date Date: l~ <8 Signed:

By CERTIFICATE OF INSERVICE INSPECTION I, the undersigned, holding a valid commission issued by the National Board of Boiler and Pressure Vessel Inspectors and the State or Province of Dade County, Florida, and employed by Arkwright Mutual Insurance Company of Norwood, Massachusetts, y 'BQIL have' inspected the components described in this Owner's Report best of my knowledge and belief, the Owner has performed examinations and tests and taken corrective measures described in the Owner's Data Report in accordance with the Inspection Plan and as required by the ASME Code,Section XI.

By signing this certificate, neither the inspector nor his employer makes any warranty, expressed or implied, concerning the examinations, tests, and corrective measures described in this Owner's Report. Furthermore, neither the Inspector nor his employer shall be liable in any manner for any personal injury or property damage or a loss of any kind arising from or connected with this inspection.

nspect r'ignature National Board, State, Province, and Endorsements Date:

I

'h E

~ ~

ll S <<)g yll, pc E E

"I