Docket Nos.:
50-250 and 50-251 November 17, 1992 LICENSEE:
FLORIDA POWER AND LIGHT COMPANY FACILITY:
TURKEY POINT, UNITS 3
& 4
SUBJECT:
SUMMARY
OF NOVEMBER 16I 1992 MEETING On November 16,
- 1992, NRR and Region II staffs held a meeting with Florida Power and Light Company (the licensee) representatives at the Turkey Point site, in Florida City, Florida to discuss issues relating to restart of Turkey Point Unit 3 following Hurricane Andrew and the Cycle 13 refueling outage.
Enclosure 1 lists the meeting attendees and Enclosure 2
is a copy of visual material presented at the meeting.
The licensee presented details of the restoration plan to restart Unit 3 and the current status of its restart activities.
Based on the licensee's presentation, the staff agreed with the licensee's restart actions.
The licensee indicated that it' restart, activities are on schedule and the reactor is expected to reach criticality on November 25, 1992.
The staff also toured the plant to review the progress of the restart activities.
Prior to achieving criticality, the licensee will inform the staff of its readiness to restart the unit.
Enclosures
- 1. List of Attendees
- 2. Presentation Summary cc w/encls See next page Distribution 0~O028 See next page L. Raghavan, Project Manager Project Directorate II-2 Division of Reactor Projects -I/II Office of Nuclear Reactor Regulation IIII'IIggkjlIEii'a G~>>>
OFC NAME DATE LA:PDII2 E. TANA~7
// / /7/92 PM:PDII2 L. RAGH II /I
/92
- SI LE
/
/
GC No PL.
/
/
D'PDII2 H.B 0 / 17/92 921209025i 92iii7 PDR ADOCK 05000250,,
P PDR
l f
4 s t H
(
'L
~
Florida Power and Light Company Turkey Point Plant CC:
Harold F. Reis, Esquire Newman and Holtzinger, P.C.
1615 L Street, N.W.
Washington, DC 20036 Jack Shreve, Public Counsel Office of the Public Counsel c/o The Florida Legislature 111 West Madison Avenue, Room 812 Tallahassee, Florida 32399-1400 John T. Butler, Esquire
- Steel, Hector and Davis 4000 Southeast Financial Center Miami, Florida 33131-,2398 Mr. Thomas F. Plunkett, Site Vice President Turkey Point Nuclear Plant Florida Power and Light Company P.O.
Box 029100 Miami, Florida 33102 Joaquin Avino County Manager of Metropolitan Dade County 111 NW 1st Street, 29th Floor Miami, Florida 33128 Senior Resident Inspector Turkey Point Nuclear Generating Station UPS. Nuclear Regulatory Commission P.O.
Box 1448 Homestead, Florida 33090 Mr. Jacob Daniel Nash Office of Radiation Control Department of Health and Rehabilitative Services 1317 Winewood Blvd.
Tallahassee, Florida 32399-0700 Mr. Robert G. Nave, Director Emergency Management Department of Community Affairs 2740 Centerview Drive Tallahassee, Florida 32399-2100 Administrator Department of Environmental Regulation Power Plant Siting Section State of Florida 2600 Blair Stone Road Tallahassee, Florida 32301 Regional Administrator, Region II U.S. Nuclear Regulatory Commission 101 Marietta Street, N.W. Suite 2900 Atlanta, Georgia 30323 Attorney General Department of Legal Affairs The Capitol Tallahassee, Florida 32304 Plant Manager Turkey Point Nuclear Plant Florida Power and Light Company P.O.
Box 029100 Miami, Florida 33102 Mr. R.
E. Grazio Director, Nuclear Licensing Florida Power and Light Company P.O.
Box 14000 Juno
- Beach, Florida 33408-0420 Mr. J.
H. Goldberg President - Nuclear Division Florida Power and Light Company P.O.
Box 14000 Juno
- Beach, Florida 33408-0420
MEETING
SUMMARY
DATED November 16 1992 DISTRIBUTION
[~oaket' i:le NRC and Local PDRs PDII-2 RF T. Murley/F. Miraglia J. Partlow W. Russell J. Richardson A. Thadani C. Rossi F. Congel S. Varga G. Lainas H. Berkow L. Raghavan E.
Tana M. Sinkule, RII OGC ACRS (10)
L. Plisco, EDO
'l
/
~.4
'I r
~iR,~y
~s~~
'99 2
pm >A~
c5t~
't lMS~S
~~WI~YL0+
we~ /m~w
/Vkc. /'p~+
LIc. /PPc-....
FPl /Fag
~ ac /gPC-Se4r, ~ //-~<
lf54l~ <~
Til D~P g~,
rP~
Pg &m fPlqr u~ y~miWWg<
@5'C.
oi so@, <a~/
XoY-lent>
3e 5. >+4Qo Qh -64K<
Sos dgd-7~83 3os'
</4-4s'~f
)of-~r I-5 s oc g~-g yc - s 9'3 V g~~=gc-Qpo K-z-w-cQl
(>as) gq.5-7(C,R.
\\
E,gcL& su FLORIDA.POWER 8r, LIGHT COMPANY QD A
Turkey Point Nuclear Plant UNIT 3 RESTART READINESS November 16, 1992
0
FPL/NRC MEETING AGENDA 8:30 A.M., NOVEMBER 16, 1992 o
INTRODUCTION o
OVERVIEW OF DAMAGE ASSESSMENT PROCESS RESULTS L. W. PEARCE R. S. KUNDALKAR o
RESTORATION OF UNIT 4 AND COMMON EQUIPMENT PRIOR TO UNIT4 RESTART R. S. KUNDALKAR o
UNIT 3 REPAIRS REMAININGTO BE PERFORMED R. S. KUNDALKAR o
RESTART ACTIVITIESREQUIRED D. E. JERNIGAN FOR PLANT STARTUP NORMALSURVEILLANCES SURVEILLANCES DUE TO HURRICANE DAMAGE o
EMERGENCY PLANNING/SECURITY D. R. POWELL o
QA OVERSIGHT o
CLOSING T. V. ABBATIELLO L. W. PEARCE
PTN RESTART DAMAGEASSESSMENT PROGRAM BILLPEARCE OUTAGE MGIVIT.
P. HIGGINS CONSTRUCTION J. MARCHESE MAINTENANCE M. WAYLAND TECH STAFF/ENG.
ERNIGAN/KUNDALKA TEAM COORDINATION PERFORMED BY OUTAGE MGMT.
P. HIGGINS/J. WEBB ENG/CONST/MAINT/TECHSTAFF DAMAGEASSESSMENT DAMAGE RESOLUTION
DAMAGEASSESSMENT PLAN o
FORMED TEAMS OF EXPERIENCED ENGINEERS (ENGINEERING/TECHNICALSTAFF) o PRIORITIZED SYSTEMS o
WALKEDDOWN SYSTEMS USING PLANT DRAWINGS.
o DOCUMENTED WALKDOWNS GENERATED WALKDOWNFORMS RECORDED ON VIDEO TAPE o
ENGINEERS GENERATED PWOs o
DETERMINED PCM PACKAGES REQUIRED
ASSESSMENT OF RESULTS o
- PLANT, OPERATIONS, MAINTENANCE, ENGINEERING, TECHNICALSTAFF REVIEWED PWO POPULATION o
PRIORITIZED PWO WORKOFF PWOs REQUIRED FOR RESTART
'180 FOR UNIT4 AND COMMON 20 FOR UNIT 3 o
GENERATED 16 PCMs
SUMMARY
OF REPAIRS TO COMMON EQUIPMENT COMPLETED IN SUPPORT OF UNIT4 RESTART o
APPROXIMATELY180 COMMON AND UNIT 4 PRIORITY I PWOs CLOSED o
METEOROLOGICALTOWER RESTORED o
OFFSITE SIRENS RESTORED o
OFFSITE POWERLINES - 6 OF 8 RESTORED o
HIGH TOWER DEBRIS REMOVED o
RADIATIONMONITORING STACK RESTORED o
UNIT 1 CHIMNEYDEMOLISHED UNIT2 CHIMNEYEVALUATEDACCEPTABLE o
SECURITY SYSTEM RESTORED o
INTERIM FIRE PROTECTION SYSTEM ESTABLISHED o
RESTART PLAN IMPLEMENTED
REPAIRS REMAININGTO BE PERFORMED FOR UNIT 3 RESTART o
COMPLETION OF FIRE PROTECTION SYSTEM RESTORATION TO ORIGINAI DESIGN o
UNIT 3 RESTART PWOs - STATUS
HURRICANE ANDREW PUNCH LIST FOR UNIT 3 RESTART Item Description System No.
Status Air Intake/Exhaust for 3D Switchgear Room EDG Building A/C Unit 79 79 Complete Conipiete Valve Leaking Rod Hanger Off Unistrut Support Valve Yoke Bent 30 72 Complete (no leak)
Complete Working Exciter Voltage Regulator Enclosure Turning Gear Doghouse and Enclosure S.W. Intercept Switch Box Overhead Bushings Broken North Lighting Arresters/
HV Terminal Connections 90 89 89 92 92 Working Working Working Complete Complete Broken Gauge CCW Tank Monitor Possible Regulator Damage Water in Switch 19 67 10 19 Complete Working Complete Complete Replace 3A EDG Turbocharger 23 Complete
REV. 11/I2I92 20 15 m
O Q.
0- 10 Ill Kl 0
TURKEYPOINT UNIT3 CYCLE 13 REFUELING OUTAGE PLANTCHANGE MODIFICATION(PCM'S)
SYSTEM ACCEPTANCE TURNOVER SHEET (SATS) COMPLETION S
S 90.261 C
'894854 92-150$
89.1 824l 91-1 66C 91-1 084'(
9249l4 91-1 57C 6900(4(
9243OE P.92466-E 92-1694 90 262C 90-296 C 90-260C 92-127C 92-1 3)C 92440CIR 924664 SM28C St-(SSC 11/22 11/29 10/25 10/18 11/01 11/08 WEEK ENDING 11/15 IMPLEMENTEDBY:
8
~ SERVIcfs R
~ RELAYOfPARTMfNT E
~ PLAIT ELEcttilcAL I
PLANT ILC M
~ PLAN1 IIECHANCAL RX
~ REACTOR fIICDIEfRIND C
~ COrIstaucteN NOT TURNED OVER PARTIALTURNOVER COMPLETE ACTIVITY (N) e TOP 20 ~
'6742l.l 604000 80 162-M 60401 4I
'604601 604600 6061&0 00 1034 002 4OC 002674 00 2614 002624 00 2064 000014 00320C 003001 00416M 00l014 006074 01 100 RX 01.120C 0'I-13OC 01 (601 Dt 1674 01.1664
'll 1674 DI 1074
~ 1.1 06C DI 1004 024204 024331 02436 E 024ISC 024624 024674 0246OE 0246l-E 02466M 024764 02477-E 0246132 0240l-E 02.1174 02 12OS 02.1274 02.1301 02 130C 02.16 I E 02.16OE 02.161-8 02.167-E 02-140.1 02.160 S 02-1601
'COHTIHQEHCYONLY CNIMTSIAIPOIILEVELCONVERTER REPL CONTROL ROOM RECORDER REPLACE RETADDNQBLOCKSWD8 FDWTRCKVLVANDROTAtlONPDIS SAMPLE VALVEUMITSWITCHOVef STM DIAIPHANWAUTOSTATKDI CONTA061ENT SPRAY SUPPORT APP. R BYPASS SWITCHLOVEIN(16)
SJAE SPNQ CONT SQBD SUPPORT REPASIS (10)
CONT Sl SVPPORT8 (0)
AUXFEED NCRS REPL SPEEDOMAX RECORDERS (17)
WB61T MOO (4) 3A FEED PUMP (16)
NIS RECORDER CHANSELECTOR SW Mov4n2m REPLACE SV416 REPLACE SV.1169 RELOAD U3 CYCLE 13 W CSCVIT RTLAYS(11)
RIIIR12 (6)
REPLACE OUTPUT MODISTE FVSEB CONTROL IXLQUARD PIPE SEALTAIX.EFlmNOS (6)
POSlllONER PCV~66 AAB REPLACE P.16. P 63 VLVS(10) klTAXEBEAMS(20)
PRZR SURD E UNE (16)
CVCS SPISNQ CAN SEOVENCER MODS (2)
MOV EIAIANCEMENT (ll)
REVERSE POWER-RACEWAYIRELAY6(3)
PLANTPACE EVALOF AIROPERATED VALVES THERMALREUEF VALVE(12) 39 RCP CLXX.ER(13)
MOVENIANCEMENT (H)
PRTR SPRAY VLVBELLOWS CONOSEAL REILACEMENT (I)
TURB CONTROL VLVPOSH NO ESCAPE HATCH CREASE FITTNQS SOFP MOTOR 0(SIAATION MS REUEF RESTRADIT MOO.
LC 6 SWOR AICSYS DOWNORADE OEN EXCITERVOLT.RELLAICSYS POWER SUPPLY REPLACEMENT O'IDINICIATORPANEL SQF P MOTOR. TURB DECK DTTERFERENCE EOO EXCITERTRANSFORM6R RELOCATE QRONO 38 EDO H 11 HANDER DITERFERENCE 6160V 39 SWOR WDIINQMOD RPI POLARITYCHANCE REPLACEMENTOF SNI88ER MOOD RIIIR12 PUSH BUTTONREORIENTATINI FLE:Q.VIATAVLFLES4MOCYCI3PCM.DRW
PURPOSE THE UNIT3 STARTUP READINESS PROGRAM VERIFIES THATWORK HAS BEEN COMPLETED AND OPERABILITY REQUIREMENTS HAVE BEEN MET TO SUPPORT STARTUP FOLLOWING HURRICANE ANDREW AND REFUELING OUTAGE ACTIVITIES.
SCOPE THE STARTUP READINESS PROGRAM REQUIREMENTS APPLY TO SPECIFIED KEY SAFETY RELATED AND POWER GENERATION SYSTEMS ANDTO MODE CHANGES PRIOR TO MODE 4 AND MODE 2.
INADDITION,THE PROGRAM ASSURES THATREPAIR OF HURRICANE ANDREW CAUSED DEFICIENCIES, WHICH ARE REQUIRED TO SUPPORT UNIT OPERATION, ARE ALSO COMPLETED.
h
PROGRAM ELEMENT o
SYSTEM READINESS CHECKLIST o
MODE CHANGE CHECKLIST MODE 4 MODE 2 o
SYSTEM READINESS TESTS o
HURRICANE ANDREW PUNCHLIST SYSTEM CHECKLISTS PRIOR TO 200 DEGREES MODE 4:
MAINSTEAM CONDENSATE FEEDWATER RESIDUAL HEAT REMOVAL INTAKECOOLING WATER COMPONENT COOLING WATER SAFETY INJECTION CHARGING AND LETDOWN REACTOR PROTECTION SYSTEM EMERGENCY DIESEL GENERATORS 4160 VOLT DISTRIBUTION 480 VOLT LOAD CENTERS AND MOTOR CONTROL CENTERS PRIOR TO CRITICAL MODE 2 ROD CONTROL MAINTURBINE TURBINE LUBE OIL AUXILIARYFEEDWATER MAINAND AUXILIARY TRANSFORMER MODE CHANGE CHECKLIST o
PLANT CLEANLINESS o
FIRE PROTECTION IMPAIRMENTSAND EQUIPMENT o
LICENSING ACTIVITIES o
SYSTEMS RESTORATION o
PC/M TESTING, TURNOVER, AND TRAINING o
SURVEILLANCECOMPLETION o
HURRICANE ANDREW PUNCHLIST WORK COMPLETION o
SCAFFOLD REMOVAL o
INSPECTION OF AFFECTED OUTDOOR MOTORS AND TERMINALBOXES o
TEMPORARY SYSTEM ALTERATIONS o
CONDITION REPORTS o
PWO CLOSURE FOR RESTART WORK YSTEMS READINESS CHECKLIST o
CLEARANGES o
SYSTEM LINEUPS o
EQUIPMENT OUT OF SERVICE LOG o
SYSTEM WALKDOWNS READINESS TESTS o
AUXILIARYFEEDWATER o
COMPONENT COOLING WATER o
INTAKECOOLING WATER o
TURBINE LUBE Oli o
CONDENSATE EMERGENCY PREPAREDNE S
o BASED ON, PRA INFORMATION, SIGNIFICANTLY ENHANCED NATURAL EMERGENCY IMPLEMENTING PROCEDURE PRIOR TO HURRICANE SEASON TO COPE WITH CATEGORY 5 HURRICANES.
o DEMONSTRATED QUALITY AND FLEXIBILITY OF EMERGENCY PLANS AND PROCEDURES DURINGlAFTER HURRICANE ANDREW.
o ADDED UHF AND VHF RADIO SYSTEMS TO THE PRESENT COMMUNICATIONSCAPABILITIES. ANTENNASDESIGNED FOR HIGHER WIND SPEEDS (175 MPH) AND SPARES ARE READILYAVAILABLEON-SITE.
o FURTHER COMMUNICATIONSSYSTEMS IMPROVEMENTS-MORE "HURRICANE PROOF".
PHONE LINES TO SITE HAVE BEEN BURIED.
HF-ALE RADIO SYSTEM TO BE INSTALLEDBY JANUARY, 5993.
o FURTHER ENHANCE IMPLEMENTING PROCEDURE EPIP-201 06, "NATURALEMERGENCIES".
SECURITY o
MAJOR PORTIONS OF SECURITY EQUIPMENT SURVIVED HURRICANE ANDREWALLOWINGUS TO MAINTAINVITAL AREA ACCESS CONTROL THROUGHOUT THE EVENT.
o SECURITY VITALAREA BARRIER GRATINGALSO PROVED VERY EFFECTIVE FOR VITAL EQUIPMENT MISSILE PROTECTION DURING THE HURRICANE.
o REINSTITUTED "T)GER TEAM" TO ADDRESS SECURITY SYSTEM RESTORATION.
o ENGINEERING PROVIDED A
STRONG INTERFACE PROVIDING VERY POSITIVE ASSISTANCE IN SYSTEM RESTORATION.
o CONTINUINGTO RESTORE ZONES.
UNIT RESTART INDEPENDENT ASSESSMENT o
POST HURRICANE REVIEWS UNIT 1 CHIMNEYDEMOLITIONSAFETY EVALUATION SERVICE WATER/FIREPROTECTION MODIFICATIONS HP ACTIVITIES MATERIALCONTROL ISSUES EMERGENCY PREPAREDNESS SECURITY SYSTEMS READINESS o
ON-SHIFT QA COVERAGE UNIT4 RESTART AFTER HURRICANE ANDREW UNIT 3
RESTART (PLANNED)
SELECTED EVOLUTIONS o
QC INVOLVEDIN MODE CHANGE CHECKLIST SIGNOFFS o
INVOLVEMENT BY THE COMPANY NUCLEAR REVIEW BOARD (CNRB)
REVIEW FPL RESTART PROGRAMS POST-HURRICANE ANDREW RESTART SUPPORTED BY ISEG NEAR TERM UNIT 3 MEETING PRIOR TO RESTART