ML17349A267

From kanterella
Jump to navigation Jump to search
Notice of Violation from Insp on 920404-0501.Violation Noted:Licensee Failed to Follow Procedure 3-PMI-062.1
ML17349A267
Person / Time
Site: Turkey Point  
Issue date: 05/29/1992
From:
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
To:
Shared Package
ML17349A266 List:
References
50-250-92-10, 50-251-92-10, NUDOCS 9206150052
Download: ML17349A267 (3)


Text

ENCLOSURE NOTICE OF VIOLATION

.Florida Power and Light Company Turkey Point, Units 3 and 4

Docket Nos.

50-250, 50-251 License Nos.

DPR 31, DPR-41 During an NRC inspection conducted on April 4 through May 1, 1992, violations of NRC requirements were identified.

In accordance with the "General Statement of Policy and Procedure for NRC Enforcement Actions",

10 CFR Part 2, Appendix C, the violations are listed below:

A.

Technical Specification (TS) 6.8. 1 requires, that written procedures, be established, implemented, and maintained covering the activities.

referenced in Appendix A of Regulatory Guide 1.33, Revision 2, February 1978.

Paragraph 8.b(l) of Regulatory Guide 1.33, Appendix A,

Revision 2,

February

1978, recommends that implementing procedures be written for each calibration listed in the TSs.

Item (ff) of this paragraph specifies procedures for water storage tank level instrument calibrations.

Procedure 3-PNI-062. 1, Refueling Water Storage Tank Level Instrumentation Channels LT-6583A/B Calibration, 'satisfies the calibration requi rements of TS 4.3.3-3, Table 4.3-4, Item 20, Refueling Water Storage Tank. It provides the instructions and the necessary data to ensure proper calibra-tion and functional testing of the process control instrumentation associated with the Refueling Water Storage Tank (RWST) level indicating system.

Contrary to the above, the licensee failed to follow procedure 3-PMI-062.1 in that during the calibration of the Unit 3, Channel B,

RWST level transmitter on April 2, 1992, the Unit 4, Channel A,

RWST level transmit-ter was removed from service instead of the Unit 3, Channel B,

RWST level transmitter.

This is a Severity Level IV violation (Supplement 1).

B.

TS 6.8. 1 requires written procedures be established, implemented, and maintained covering the activities recommended in Appendix A of Regulatory Guide 1.33, Revision 2, February

1978, and Sections
5. 1 and 5.3-of ANSI N18.7"1972.

Paragraph 3 of Regulatory Guide 1.33, Appendix A, Revision 2,

February

1978, recommends the establishment of procedures, for the operation of safety-related systems.

Section

5. 1.2 of ANSI N18.7-1972 requires that procedures be followed.

920gf 005 00250 2 920529 PDR Q

1 Florida Power and Light Company 2

Turkey Point, Units 3 and 4

Docket Nos. 50-250, 50-251 License Nos. DPR-31, DPR-41 Procedure O-ADM-201, Upgrade Operations Procedure

Usage, paragraph 5.1, Procedural Adherence
Policy, states in part that procedures shall be present during performance of tasks for which verification is documented by initial or signature.

Procedure 3-0P-072, Main Steam

System, paragraphs 7.1 and 7.2, define the steps required to place the Main Steam Isolation Valve backup nitrogen bottles in service and/or in standby.

These steps require initials for operator and second verification.

Contrary to the above, on April 20,

1992, a turbine operator replaced the in-service Unit 3

A and B main steam isolation valve backup-nitrogen bottles with standby backup-nitrogen bottles without following the

'rocedure and without the required second verification.

This resulted in the misalignment of valves and isolation of the nitrogen backup system for the 3A and B main steam isolation valves.

This is a Severity Level IV violation (Supplement 1).

Pursuant to the provisions of 10 CFR 2.201, Florida Power and Light Company is hereby required to submit a written statement or explanation to the U.S.

Nuclear Regulatory Commission, ATTN:

Document Control

Desk, Washington, D.C.

20555, with a copy to the Regional Administrator, Region II, and a copy to the NRC Resident Inspector at the facility that is the subject of this notice, within 30 days of the date of the letter transmitting this Notice of Violation (Notice).

This reply should be clearly marked as a "Reply to a Notice of Violation" and should include for each violation:

(1) the reason for the violation, or, if contested, the basis for disputing the violation, (2) the corrective steps that have been taken and the results

achieved, (3) the corrective steps that will be taken to avoid further violations, and (4) the date, when full compliance will be achieved.

If an adequate reply is not received within the time specified in this Notice, an order or demand for information may -be issued as to why the license should not be

modified, suspended, or revoked, or why such other action as may be proper should not be taken.

Where good cause is shown, consideration will be given to extending the response time.

Dated at Atlanta, Georgia, this 29th day of'May 1992.