Responds to Generic Ltr 88-20, Initiation of Individual Plant Exams for Severe Accident Vulnerabilities. Containment Performance Analysis Will Also Be Performed, Following Guidance of App 1 to Generic Ltr 88-20
ML17347B400
Person / Time
Site: Saint Lucie, Turkey Point, 05000000
Issue date: 10/31/1989
From: Goldberg J
FLORIDA POWER & LIGHT CO.
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
References
GL-88-20, NUDOCS 8911080276
Download: ML17347B400 (13)


Text

ACCELERATED DI UTION DEMONSTPA.TION SYSTEM 1'

\

REGULATORY INFORMATION DISTRIBUTION SYSTEM (RIDS)

ACCESSION NBR:8911080276 DOC.DATE: 89/10/31 NOTARIZED: YES DOCKET FACIL:50-000 Generic Docket 05000000 50-250 Turkey Point Plant, Unit 3, Florida Power and Light C 05000250 50-251 Turkey Point Plant, Unit 4, Florida Power and Light C 05000251 50-335 St. Lucie Plant, Unit 1, Florida Power & Light, Co. 05000335 50-389 St. Lucie Plant, Unit 2, Florida Power & Light Co. 05000389 AUTH. NAME AUTHOR AFFILIATION GOLDBERG,J.H. Florida Power & Light Co.

RECIP.NAME RECIPIENT AFFILIATION Document Control Branch (Document Control Desk)

SUBJECT:

Responds to Generic Ltr 88-20, "Initiation of Individual Plant Exams for Severe Accident Vulnerabilities."

DISTRIBUTION CODE: AOOID TITLE: OR COPIES RECEIVED:LTR Submittal: General Distribution

~ ENCL L SIZE: 5 NOTES RECIPIENT COPIES RECIPIENT COPIES ID CODE/NAME LTTR ENCL ID CODE/NAME LTTR ENCL PD2-2 LA 1 1 PD2-2 PD 1 1 EDISON,G 5 5 NORRIS,J 5 5 INTERNAL: ACRS 6 6 NRR/DEST/ADS 7E 1 1 NRR/DEST/ESB 8D 1 1 NRR/DEST/ICSB 1 1 NRR/DEST/MTB 9H NRR/DOEA/TSB OC/LFM ll 1 1

1 1

1 0

NRR/DEST/RSB 8E NUDOCS-ABSTRACT OGC/HDS2 1

1 1

1 1

0 E LE 0 1 1 RES/DSIR/EIB 1 1 EXTERNAL: LPDR 2 2 NRC PDR 1 1 NSIC 1 1 NOTE TO ALL "RIDS" RECIPIENTS:

PLEASE HELP US TO REDUCE WAS'ONTACT THE DOCUMENT CONTROL DESK, ROOM Pl-37 (EXT. 20079) TO ELIMINATEYOUR NAME FROM DISTRIBUTION LISTS FOR DOCUMENTS YOU DON'T NEED!

TOTAL NUMBER OF COPIES REQUIRED: LTTR 33 ENCL 31

0 f K g

P.O. Box14000,Juno Beach,FL 33408-0420 OCTOBER 3 1 1989 L-89-389 10 CFR 50.54(f)

U. S. Nuclear Regulatory Commission Attn: Document Control Desk Washington, D. C. 20555 Gentlemen:

Re: Turkey Point Units 3 and 4 Docket Nos. 50-250 and 50-251 St. Lucie Units 1 and 2 Docket Nos. 50-335 and 50-389 Individual Plant Examinations for Severe Accident Vulnerabilities, Generic Letter 88-20 By Generic Letter (GL) 88-20, dated November 23, 1988, the NRC requested licensees to perform an Individual Plant Examination (IPE) to assess severe accident vulnerabilities for each licensee plant and submit the results of the IPE to the NRC. By Federal Register notice dated September 1, 1989, the NRC announced the availability of NUREG-1335, "Individual Plant Examinations'.

Submittal Guidance" and the initiation of the IPE process.

Licensees are requested to submit, by October 31, 1989, proposed programs for completing IPEs. As requested by GL 88-20, attached is the FPL IPE Program Plan for Turkey Point Units 3 and 4 and St.

Lucie Units 1 and 2.

Should you have any questions on this information, please contact us ~

Very truly yours, J. H. Goldberg Executive Vice President JHG/WFK/gp Attachments ceo Stewart D. Ebneter, Regional Administrator, Region II, USNRC Senior Resident Inspector,-USNRC, Turkey Point Plant Senior Resident Inspector, USNRC, St. Lucie Plant S91031 891 1080276 CK 05000250 pO PDR PDC P

an FPL Group company

ATTACHMENT 1 IPE PROGRAM PLAN TURKEY POINT UNITS 3 AND 4 ST ~ LUCIE UNITS 1 AND 2 1~ NRC RE UEST Identify the method and approach selected for performing the IPE.

FPL RESPONSE FPL will perform a Level 1 Probabilistic Risk Assessment (PRA) for Turkey Point Units 3 and 4 and St. Lucie Units 1 and 2.

A containment performance analysis will also be done, following the guidance of Appendix 1 to GL 88-20.

The current scope of the Turkey Point study includes the internal flooding and fire events and hurricane external event.

Science Applications International Corporation is supporting FPL in the conduct of the Turkey Point IPE. Approximately fifty percent of the analysis will be conducted by FPL personnel.

PRA technology transfer is a major objective of the Turkey Point study. FPL s goal is to be in a position to conduct the St. Lucie IPE with a minimum reliance on a contractor. This goal is reflected in the milestone schedule discussed below.

2 ~ NRC RE UEST Describe the method to be used, submitted for staff review.

if it has not been previously FPL RESPONSE Since FPL has selected the PRA approach to satisfy the GL 88-20 request, we will employ current PRA methods and information as discussed in Section 4.1 of GL 88-20.

The Turkey Point Plant is in the process of a number of major upgrades. These modifications will impact the assumptions and models of the IPE.

(con't)

For Turkey Point, a cut-off date of November 30, 1990, has been established. Modifications implemented (completed and turned over to the plant operations department) by this date will be included in the IPE submittal. Modifications implemented after this date will be included in later revisions to the PRA. Major planned modifications such as the Emergency Power System upgrade, which are not in place as of November 30, 1990, will not be included in the IPE submittal.

This is necessary in order to meet the existing NRC schedule.

A similar philosophy will be used for the St. Lucie IPE.

3. NRC RE VEST Identify the milestones and schedules for performing the IPE and submitting the results to the NRC.

FPL RESPONSE FPL will perform the plant examinations for Turkey Point and St. Lucie consecutively beginning with the Turkey Point units.

The milestones for performing these examinations and for submitting the results are indicated in Attachment 2. A formal, independent review by FPL engineers will be performed on the documentation packages and at several milestones in the examination to validate the process and the results.

ATTACHMENT 2 IPE PROGRAM PLAN TURKEY POINT UNITS 3 AND 4 ST LUCIE UNITS 1 AND 2 MILESTONE DATE s Commence Turkey Point, IPE August, 1989 (underway)

Detailed Planning for St. Lucie IPE May, 1990 November, 1990 Finalize Turkey Point PRA Configuration November, 1990 Complete, Submit Turkey Point IPE June, 1991 Commence St. Lucie IPE July, 1991 Finalize St. Lucie PRA Configuration June, 1993 Complete, Submit St. Lucie IPE December, 1993

r ~ A STATE OF FLORIDA COUNTY OF PALM BEACH )

)

) st J. H. Goldber being first duly sworn, deposes and says:

That he is Executive Vice President, of Florida Power and Light Company, the Licensee herein; That he has executed the foregoing document; that the statements made in this document are true and correct to the best of his knowledge, information and belief, and that he is authorized to execute the document on behalf of said Licensee.

J. H. Goldberg Subscribed and sworn to before me this day of QM b

>>>> A

.I 1I N TARY PUBLIC, in and for the County of Palm Beach, State of Florida FlORIDA>>

NOTARY PUBLlC> STATE OF COMMISSION EXPIRES: AUG. Sp l 993, UNOERWRITCRR Commission expires RcNoRR <<<<No~R<<

NOTARY I>>UOLIC My

I II

We regret any inconvenience these additional delays may have caused. If you have any questions or require additional information, please do not hesitate to contact us.

Sincerely, Attachment cc: R. A. Burricelli, Public Service Electric & Gas T. M. Gerusky, Commonwealth of Pennsylvania T. P. Johnson, USNRC Senior Resident Inspector T. E. Magette, State of Maryland W. T. Russell, Administrator, Region I, USNRC H. C. Schwemm, Atlantic Electric J. Urban, Oelmarva Power

A ATTACHMENT

1. Ori inal Commitment A video tape training module will be made by July 15, 1988. The tape will emphasize the various panel sensitivities, consequences of improper care, and techniques to be exercise when working near, opening, closing or working in the panels. Training will be conducted for selected personnel and will be completed by September 2, 1988.

Previous Schedule Revision 1 31 89 This commitment schedule was revised to indicate completion of the video tape by June 30, 1989 and completion of training for selected personnel by September 30, 1989.

Current Schedule The video tape will be completed by January 1990. The training for selected personnel will be completed by April 1990.

2. Ori inal Commitment Appropriate plant personnel, as designated by the various Plant Superintendents, will be trained in a "mock-up" of a control panel to become familiar with performing tests and troubleshooting under various conditions to improve their ability to avoid potential grounding situations. This training will be incorporated into the technical staff and management training program, and the continuing training program for the designated plant personnel. This training will commence by December 1, 1988.

Ori inal Commitment For new plant staff personnel who will be assigned duties which involve work in critical control panels, there will be an established and structured training program. The training will include techniques and requirements for tightening and checking terminations, electrical separation, continuity testing, electrical safety, etc., and panel familiarity. This program will be developed by August 19, 1988 and will become a part of job orientation training.

Previous Status Revision 1 31 89 These commitment schedules were revised to indicate expected availability of the mockup panel by May 5, 1989 and completion of the training by 7/31/89 Current Schedule The panel is expected to be delivered to the site in November 1989.

Training materials will be developed by March 1, 1990 and presented to the above site personnel by April 1, 1990.