ML17347B327
| ML17347B327 | |
| Person / Time | |
|---|---|
| Site: | Turkey Point |
| Issue date: | 09/07/1989 |
| From: | Ebneter S NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II) |
| To: | Woody C FLORIDA POWER & LIGHT CO. |
| References | |
| NUDOCS 8909150086 | |
| Download: ML17347B327 (4) | |
Text
SEP O7 t98L Docket Nos. 50-250, 50-251 License Nos.
DPR-31, DPR-41 Florida Power and Light Company ATTN:
Mr. C. 0. Woody, Acting Senior Vice President - Nuclear P. 0.
Box 14000 Juno
- Beach, FL 33408-0420 Gentlemen:
SUBJECT:
MANAGEMENT MEETING - TURKEY POINT UNITS 3 AND 4 This letter confirms the conversation between Mr. G. Madden, Florida Power and Light Corporate Licensing, and Mr. P.
Madden of my staff on August 31,
- 1989, concerning a meeting to be held at the Turkey Point site on September 19, 1989, at 12:30 p.m.
The purpose of this meeting is to discuss significant programmatic issues.
A proposed agenda is enclosed.
Should you have any questions regarding these arrangements, we will be pleased to discuss them.
S'incerely, Original signed by
Enclosure:
Proposed Meeting Agenda cc w/encl:
K. N. Harris, Vice President Turkey Point Nuclear Plant J.
E. Cross, Plant Manager Turkey Point Nuclear Plant L.
W. Bladow, Plant gA Superintendent E. Lyons, Acting Regulatory and Compliance Supervisor State of Florida bcc w/encl:
(See page 2)
Stewart D. Ebneter Regional Administrator 8909i 0086 S90907 PDR ADOCK 05000250 P
ENCLOSURE PROPOSED MEETING AGENDA NRC/FPL SENIOR MANAGEMENT MEETING SEPTEMBER 19, 1989 TURKEY POINT SITE INTRODUCTION Highl ights of progress s ince last meeting Plant Status IMA PROGRESS UALITY ASSURANCE MAINTENANCE ENGINEERING SALP REVIEW SECURITY
Florida Power and Light Company SEP 07 198$
'cc w/encl:
G.
E. Edison, Project Manager, Project Directorate II-2, Division of Reactor
- Projects, NRR NRC Resident Inspector
- concurrences Document Control Desk RII
'a en 09/ Z/89 p
RII:
RCrl njak MSinkul e 09/4 /89 09/ ( /89 RI,I:gP L
yes 0 /( /89 RII:ORA BGr' 0
/89
"s