Forwards SER & SAIC-86/3074, Technical Evaluation of Supplemental Summary Rept of Dcrdr of Turkey Point Nuclear Power Plant,Units 3 & 4, Accepting Util 860401 Rept Re TMI Item I.D.1, Dcrdr
ML17347A215
Person / Time
Site: Turkey Point  
Issue date: 12/15/1986
From: Mcdonald D
Office of Nuclear Reactor Regulation
To: Woody C
FLORIDA POWER & LIGHT CO.
Shared Package
ML17347A217 List:
References
RTR-NUREG-0737, RTR-NUREG-737, TASK-1.D.1, TASK-TM TAC-59176, TAC-59177, NUDOCS 8612240303
Download: ML17347A215 (6)


Text

December 15, 1986 Docket.Nos.

50-250 and 50-251 Mr. C. 0.

Moody, Group Vice President Nuclear Energy Department Florida Power and Light Company Post Office Box 14000 Juno Beach, Florida 33408

Dear Mr. kloody:

DISTRIBUTION g

oc et>s. ex NRC PDR Local PDR PAD¹2 Rdg T. Novak OGC-Bethesda E. Jordan B. Grimes J. Partlow N. Thompson, D. McDonald D. Miller ACRS (10)

Tech Branch Gray File J.

Kramer DHFT

Subject:

NUREG-0737, Item 1.0.1 Detailed Control Room Design Review (DCRDR)-

Turkey Point Plant Units 3 and 4

Reference:

TAC Numbers 59176 and 59177 By letters dated May 20,

1983, and November 1, 1983, you submitted your responses to Supplement 1 to NUREG-0737, Item 1.D.l "Control Room Design Reviews," for the Turkey Point Plant.

The staff reviewed your submittals and documented the results in a draft Safety Evaluation (SE) dated February 2, 1984.

The draft SE identified areas of concern, additional information needed and recommended that a pre-implementation audit be conducted at the Turkey Point Plant site.

The audit was conducted during April 2-6, 1984.

Results of the audit were transmitted to you by letter dated May 10, 1984, indicating the need for a Supplemental Summary Report to address our.concerns identified during the audit.

You submitted this report on April 1, 1986.

The staff, with the assistance of our contractor, Science 'Applications International Corporation (SAIC); reviewed your Supplemental Summary Report and the additional information provided in letters dated September 3 and Dec'ember 11, 1986.

Based on our review, we have concluded that you have-conducted a comprehensive DCRDR program for the Turkey Point Facility which satisfies the requirements of Supplement 1 to NUREG-'0737, Item 1.D.l and is therefore, acceptable.

Me have,,

documented the details of our review in the enclosed SE and the supporting SAIC Technical Evaluation Report.

--~ ggg~iS AQOG pgg

&12>F030 05oP02'5 P

8 I

III

Mr. C. 0.

Woody This concludes our actions related to the above referenced TAC numbers.

Sincerely,

/s/

Enclosures:

As stated Daniel G. McDonald, Senior Project Manager PWR Project Directorate ¹2 Division of PWR Licensing-A Office of Nuclear Reactor Regulation cc w/enclosures:

See next page L:

¹2 12/

/86

¹2 DMcDopald:hc 12/g/86 PD:PAD¹2 LRubenstein 12/l~/86

7g II 1'~

1 Mr. C. 0.

Woody Florida Power and Light Company Turkey Point Plant CC:

Harold F. Reis, Esquire Newman and Holtzinger, P.C.

1615 L Street, N.W.

Washington, DC 20036 Mr. Jack Shreve Office of the Public Counsel Room 4, Holland Building Tallahassee, Florida

'-32304 Norman A. Coll, Esquire

Steel, Hector and Davis 4000 Southeast Financial Center Miami, Florida 33131-2398 Mr. C.

M. Wethy, Vice President Turkey Point Nuclear Plant Florida Power and Light Company P.O.

Box 0?9100 Miami, Florida 33102 Mr. M. R. Stierheim County Manager of Metropolitan Dade County Miami, Florida 33130 Resident Inspector U.S. Nuclear Requlatory Commission Turkey Point Nuclear Generating Station Post Office Box 57-1185 Miami, Florida 33257-1185 Mr. Allan Schubert, Manager Office of Radiation Cont~ol Department of Health and Rehabilitative Services 1317 Winewood Blvd.

Tallahassee, Florida 32301 Intergovernmental Coordination and Review Office of Planning 5 Budget Executive Office of the Governor The Capitol Building Tallahassee, Florida 32301 Administra tor Department of Environmental Regulation Power Plant Sitina Section State of'lorida 2600 Blair Stone Road Tallahassee, Florida 32301 Regional Administrator, Region II U.S. Nuclear Regulatory Comnission Suite 2900 101 Marietta Street Atlanta, Georgia 30323 Martin H. Hodder, Esquire 1131 NE, 86th Street Miami, Florida 33138 Joette Lorion 7269 SW, 54 Avenue Miami, Florida 33143 Mr.,Chris J. Raker, Plant Manager Turkey Point Nuclear Plant Florida Power and Light Company P.O.

Box 029100 Miami, Florida 33102 Attorney General Department of Legal Affairs The Capitol Tallahassee, Florida 32304