Forwards Request for Addl Info Re Pressurized Thermal Shock Flux Reduction Program.Response Requested within 3 Wks of Ltr Receipt.W/O Encl
ML17346A452
Person / Time
Site: Turkey Point  NextEra Energy icon.png
Issue date: 07/26/1984
From: Varga S
Office of Nuclear Reactor Regulation
To: Williams J
FLORIDA POWER & LIGHT CO.
References
REF-GTECI-A-49, REF-GTECI-RV, TASK-A-49, TASK-OR NUDOCS 8408070075
Download: ML17346A452 (5)


Text

'l"*

r Docket Nos.

50-250 and 50-251 July 26, 1984 Mr. J.

W. Williams, Jr., Vice President Nuclear Energy Department Florida Power and Light Company Post Office Box 14000 Juno Beach, Florida 33408

Dear Mr. Williams:

DISTRIBU ON c

e 1

RC PDR L PDR Gray File ORB81 Rdg CParrish DMcDonald DEisenhut OELD ACRS 10 EJordan JNGrace RFerguson

SUBJECT:

PRESSURIZED THERMAL SHOCK (PTS)

FLUX REDUCTION PROGRAM - REQUEST FOR ADDITIONAL NEUTRON SOURCE DATA, TURKEY POINT UNITS 3 AND 4 By letters dated March 1, 1984, April 2, 1984, and June 4, 1984, you have provided the integral neutron source data we requested in our letter of November 17, 1983.

We are evaluating the data to verify the flux reduction resulting from your PTS program for the Turkey Point Plant.

We request that the information identified in the enclosure to this letter be provided in order for us to complete our evaluation.

To meet our current review schedule, we request this information be provided within three weeks of receipt of this letter as discussed with your staff.

The reporting and/or recordkeeping requirements of this letter affect fewer than ten respondents; therefore, OMB clearance is not required under P.L.96-511.

Sincerely,

/s/SVarga

Enclosure:

As stated cc w/enclosure:

See next pag ORBgl:DL C

DMcDonald;ps V r 7/yy/84 84 Steven A. Varga, Chief Operating Reactors Branch 01 Division of Licensing I8408070075 840726'DR ADOCK 05000250 PDR

~,r I

Il Q

1 h

II 1t 1"

, s1 P

I tl k

C

J.

W. Williams, Jr.

Florida Power and Light Company Turkey Point Plants Units 3 and 4

cc:

Harold F. Reis, Equire Lowenstein,

Newman, Reis and Axelrad 1025 Connecticut
Avenue, N.W.

Suite 1214 Washington, DC 20036 Bureau of Intergovernmental Relations 660 Apalachee Parkway Tallahassee, Florida 33130 Norman A. Coll, Esquire

Steel, Hector and Davis 1400 Southeast First National Bank Building Miami, Florida 33131 Mr. Henry Yaeger, Plant Manager Turkey Point Plant Florida Power and Light Company P.O.

Box 013100 Miami, Florida 33101 Mr. M.

R. Stierheim County Manager of Metropolitan Dade Count/

Miami, Florida 33130 Resident Inspector Turkey Point Nuclear Generating Station U.S. Nuclear Regulatory Commission Post Office Box 1207 Homestead, Florida 33030 Regional Radiation Representative EPA Region IV 345 Courtland Street, N.W.

Atlanta, GA 30308 Mr. Jack Shreve Office of the Public Counsel'oom 4, Holland Building Tallahassee, Florida 32304 Administrator Department of Environmental Regulation Power Plant Siting Section State of Florida 2600 Blair Stone Road Tallahassee, Florida 32301 James P. O'Reilly Regional Administrator, Region II U.S Nuclear Regulatory Commission Suite 2900 101 Marietta Street
Atlanta, GA 30303 Martin H. Hodder, Esquire 1131 N.E. 86th Street

'iami, Florida 33138 Joette Lorion 7269 SW 54 Avenue Miami, Florida 33143

10 13.

Proposed technical specification changes'o require periodic test ing of the unde rvo Lt age shunt trip func't i ons and the manua L reactor t r ip sw'it'ch contacts and wi ring.

Prior to starting the reactor af ter installation of the shunt-trip modi fi cation~

PGE wi L L submit a technical specif i cation change re quest to require periodi c testing of the UY and shunt trip functions

~ and the manual reactor trip switch contacts and wiring.

Me find this commitment to be acceptable.

CONCLUSION Based on the review of the Licensee's response to the plant specific questi ons identi fi ed in the staf f '

evaluation of the Owner' Group generic design modifications~

we find that the are acceptable.

desi gn modi fi cat i ons t

The staff requests that the licensee submit confirmation that the seismic qualification of the shunt trip attachment has been successfuLLy completed as noted in Item 6.

Principal Contributor:

N. Trehan, ICSB