Notice of Violation from Insp on 870921-1019.Violation Noted:Nuclear Operator Manipulated Thermostat for Heat Tracing Circuit Number 8 & Failed to Submit Plant Work Order to Have Electrical Maint Check Heat Tracing Thermostat
ML17342B025
Person / Time
Site: Turkey Point  
Issue date: 11/12/1987
From: Reyes L
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
To:
Shared Package
ML17342B024 List:
References
50-250-87-43, 50-251-87-43, NUDOCS 8711190283
Download: ML17342B025 (4)


Text

ENCLOSURE 1

NOTICE OF VIOLATION Florida Power and Light Company Turkey Point Units 3 and 4

Docket Nos.

50-250 and 50-251 License Nos.

DPR-31 and DPR-41 During the Nuclear Regulatory Commission (NRC) inspection conducted on September 21 October 19,

1987, a

violation of NRC requirements was identified.

The violation involved three examples of failure to implement approved procedures:

The failure to properly implement off normal operating procedures for removal of a nuclear instrument from service and for adjustment of a critical heat tracing circuit 'thermostat and for fail~re to properly implement an administrative procedure which, ensures control of locked valves.

In accordance with "General Statement of Policy and Procedure for NRC Enforcement Action,"

10 CFR Part 2, Appendix C (1986),

the violations are listed below.

Technical Specification 6'. 1 requires that written procedures and administrative policies shall be established, implemented and maintained that meet or exceed the requirements and recommendations of Appendix A of USNRC Regulatory Guide 1.33.

Regulatory Guide 1.33, Appendix A, Item 5, recommends that procedures for

abnormal, offnormal, or alarm conditions should contain the meaning of an annunciator, the source of the signal, the immediate operator action and the long-range actions.

Two examples of failure to implement Regulatory Guide 1.33, Appendix A, Item 5, were identified.

Off-Normal Operating Procedure O-ONOP-048, entitled

,Off Normal Critical Heat Tracing System Temperature, revision dated June 26,

1985, requires, in Section 3.2, that if no degraded insulation or abnormal system operation is discovered, submit a Plant Work Order (PWO) to have Electrical Maintenance check the heat tracing thermostat.

Contrary to the

above, on September 28,
1987, in response to a Heat Tracing Trouble 'alarm annunciator, a Nuclear Operator (NO), at the direction of the Unit 4 Reactor Control Operator (RCO),manipulated the thermostat for heat tracing circuit number 8

and failed to submit a

PWO to have electrical maintenance check the heat tracing thermostat.

2.

87lll90283 PDR ADOCK G

Off Normal Operating Procedure 4-0NOP-059.3, entitled Nuclear Instrumentation Malfunction, revision dated April 14,

1987, Section 5.3.1, requires the RCO to transfer the Comparator Channel Defeat Switch to the failed channel when one power range channel fails low during power operation-Mode 1.

87lll2 05000250 PDR

4

Florida Power and Light Company Turkey Point Units 3 and 4

Docket Nos.

50-250 and 50-251 License Nos.

DPR-31 and DPR-41 Contrary to the above, on October 2, 1987, with Unit 4 in Mode 1, the Unit 4 RCO failed to transfer the Comparator Channel Defeat Switch in response to power range nuclear instrument channel N-44 failure.

Regulatory Guide 1.33, Appendix A, Item 1.c specifies that procedures should be developed to control equipment through locking and tagging.

3.

Administrative Procedure O-ADM-205, entitled Administrative Control of Valves,

Locks, and
Switches, revision dated August 11,
1987, requires, in Attachment 2, that the A Boric Acid Storage Tank (BAST) recirculation isolation valve,
344, be controlled locked open.

Contrary to the

above, on October 3, 1987, valve 344 was found open but not properly locked.

This is a Severity Level IV violation (Supplement I)

. Pursuant to the provisions of 10 CFR 2.201, Florida Power and Light Company is hereby required to submit to this Offfice within 30 days of the date of the letter transmitting this Notice a writen statement or explanantion in reply including (for each violation):

(1) admission or denial of the violation, (2) the reason for the violation if admitted, (3) the corrective steps which have been taken and the results

achieved, (4) the corrective steps which will be taken to avoid further violations, and (5) the date when full compliance will be achieved.

Where good cause is

shown, consideration will be given to extending the response time.

FOR THE NUCLEAR REGULATORY COMMISSION Original Signed by Charles W. Hehl

/for Luis A. Reyes, Director Division of Reactor Projects Dated at Atlanta, Georgia this 12th day of November, 1987