Notice of Extension Until 811101 for Completion of Final Mod,Listed in 810328 Ser,To Fire Protection Sys at Facilities
ML17341A561
Person / Time
Site: Turkey Point  
Issue date: 09/04/1981
From: Harold Denton
Office of Nuclear Reactor Regulation
To:
Shared Package
ML17341A560 List:
References
NUDOCS 8109300200
Download: ML17341A561 (2)


Text

7590-01 U. S.

NUCLEAR REGULATORY COMMISSION DOCKET NOS.

50-250 5 50-251 FLORIDA POWER 8r LIGHT COMPANY NOTICE OF EXTENSION OF COMPLETION DATES By letter dated July 28, 1981,'lorida Power E Light Company (the licensee) requested that the U. S. Nuclear Regulatory Commission (the Commission) grant an extension until November 1, 1981, for completion of the final modification listed in the Safety Evaluation Report dated March 28, 1981, to the fire protection system at the Turkey Point Plant Unit Nos.

3 and 4 located in Dade County, Florida.

The Commission's Director of Nuclear Reactor Regulation has concluded that good cause has been shown and that such postponement will not adversely affect the health and safety of the public.

Accordingly, pursuant to 10 CFR 50,48(d),

the request has been granted.

)

For further details with respect to this action, see (1) the licensee's request dated July 28,

1981, and (2) the Director's letter to the licensee dated this 4th day of September 1981.

FOR THE NUCELAR REGULATORY COMMISSION Dated at Bethesda,

Maryland, 4th day of September 1981 Harold R.

Denton, Director Office of Nuclear Reactor Regulation