Forwards IE Insp Repts 50-250/80-21 & 50-251/80-21 on 800501-31 & Notice of Violation
ML17340A265
Person / Time
Site: Turkey Point  NextEra Energy icon.png
Issue date: 06/30/1980
From: Robert Lewis
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
To: Robert E. Uhrig
FLORIDA POWER & LIGHT CO.
Shared Package
ML17340A263 List:
References
NUDOCS 8010170017
Download: ML17340A265 (4)


See also: IR 05000250/1980021

Text

~

r

~8 AE0y

+4

"o

C

O

0

Cy

+~

~0

+a*++

In Reply Refer To:

RII:RVL

50-250/80-21

50-251/80-21

UNITED STATES

NUCLEAR REGULATORY COMMISSION

REGION II

101 MARIETTAST., N.W., SUITE 3100

ATLANTA,GEORGIA 30303

JUN 3 0 1980

Florida Power and Light Company

ATTN:

R. E. Uhrig, Vice President

P. 0. Box 529100

Miami, FL

33152

Gentlemen:

This refers

to the

inspection

conducted

by R. Vogt-Iowell of this office on

May 1 through

31,

1980 of activities authorized

by

NRC Operating

License

Nos.

DPR-31

and

DPR-41 for the Turkey Point facility, and to the discussion of our

findings held with J.

K. Hays at the conclusion of the inspection.

Areas

examined

during the

inspection

and

our findings

are

discussed

in the

enclosed

inspection

report.

Within these

areas,

the inspection

consisted

of

selective

examinations

of procedures

and representative

records,

interviews with

personnel,

and observations

by the inspector.

During the inspection, it was

found that certain activities under your license

appear

to be in noncompliance with NRC requirements.

These

items

and references

to pertinent requirements

are listed in the Notice of Violation enclosed herewith

as Appendix A.

This notice is sent to you pursuant to the provisions of Section

2.201 of the NRC's "Rules of Practice," Part 2, Title 10,

Code of Federal Regula-

tions.

Section

2.201 requires

you to submit to this office, within 20 days of

your receipt of this notice,

a written statement or explanation in reply including:

(1) corrective steps

which have been taken by you and the results

achieved;

(2)

corrective steps

which will be taken to avoid further noncompliance',

and (3) the

date when full compliance will be achieved.

In accordance

with Section 2.790 of the NRC's "Rules of Practice," Part 2, Title

10, Code of Federal Regulations,

a copy of this letter and the enclosed inspection

report will be placed in the NRC's Public Document

Room. If this report contains

any information that you (or your contractor) believe to be proprietary, it is

necessary

that you make

a written application within 20 days to this office to

withhold

such

information

from public disclosure.

Any such application

must

include

a full statement

of the reasons

on the basis of which it is claimed that

the information is proprietary,

and should be prepared

so that proprietary infor-

mation identified in the application is contained in a separate

part of the

document. If we do not hear from you in this regard within the specified period,

the report will be placed in the Public Document Room.

0

0

Florida Power and Light Company

'JUN 3

(} 1980

Should you have any questions

concerning this letter,

we will be glad to discuss

them with you.

Sincerely,

g.c.

R.

C.

ewis, Acting Chief

Reactor Operations

and Nuclear

Support Branch

Enclosures:

1.

Appendix A, Notice of Violation

2.

Inspection Report Nos. 50-250/80-21

and 50-251/80-21

cc w/encl:

H. E. Yaeger, Plant Manager