'gl l DISTRIBUTION Docket Files 0-25 /251
'NRC PDRs (2)
Local PDR TERA NSIC NRR Reading ORbl Reading D. Eisenhut T. Novak S.
Varga N. Grotenhuis J. Olshinski J.
'Heltemes I&E (3)
- Attorney, OELD C. Parrish Docket Nos.60-260 and 60-261, Jury 9 g logo Dr. Robert E. Uhrfg, Vfce Presfdont Advanced Systems and Technology Florida Power and Lfght Company Post Office Box 629100 Hfamf, Florida 33152
Dear Dr. Uhrfg:
l<e request that you respond to these questfons wfthfn 30 days from July 10, 1980 so that the review schedule for the Draft Envfronmenta'l Impact Statement may be mafntafned.
Sfncerely, On triarch 28, 1980 you fssued Revfsfon 7 to your Steam Generator Repair Report for the Turkey Pofnt Plant. Unft Hos 3 and 4.
>le have revfewed that materia'l and find that we need addftfonal information r elatfng to the radiological assessment.
The enclosed request for addftfonal fnformatfon was discussed with your staff on July 10, 1980 to clarffy the questions.
In addition, a meeting fn Bethesda, lfaryland has been set for July 21, 1980 for further dfscussfon of the questfons fi't fs necessary.
Enclosure:
As Stated
',cc:
w/enclosure See next page
~Q dweeb +
RRCZR@r $f R:<<s,'5 Thomas t3. Novak, Assfstant Director for Operatfng Reactors Dfvfsfon. of Lfcensfng 80081 2 00/0 DL:0 3
t'FFIGEy DL:OR 1
5URNAME
. ~ 86rote nb>. s.
OATEP...0?/+. (80 80 07~/80 NRC.FORM 318 (9-76) NRCM 0240 4 U 5. GOYERNMENT PRINTING OFFICE: 1979 239'369
pg~F Ih OW
~p,g Afcy c<
~4 0~c T4 Cy YJ+
<<0 Docket Nos. 50-250 and 50-251 UNITF0 STATES NUCLEAR REGULATORY COMMISSION WASKINGTOt4, D. C. 20555 July 29, 1980 Dr. Robert E. Uhrig, Vice President Advanced Systems and Technology Florida Power and 'Light Company Post Office Box 5291 00 Miami, Florida 33152 Dear Dr.
Uhr ig:
Qn March 28, 1980 you issued Revision 7 to your Steam Generator -Repair Report for the Turkey Point Plant, Unit Nos.
3 and 4.
We have reviewed that material and find-that we need additional information relating to the radiological assessment.
The enclosed request for additional information was discussed with your staff on July 10, 1980 to clarify the questions.
In addition, a meeting in Bethesda, Maryland has been set for July 21, 1980 for further discussion of the questions if it is necessary.'e request that. you nespond to these ques'tions within 30 days from July 10, 1980 so that the, review schedule for the Draft Environmental Impact Statement may be maintained.
S incerel y, Thomas M. Novak, Assistant Director for'perating Reactors Division of Licensing
Enclosure:
As Stated cc:
w/enclosure See next page
RADIOLOGICAL ASSESSMENT Describe how you will incorporate the following provisions of Regulatory Guide 8.8, Revision 3, June 1978, in the steam gener-ator replacement project.
C.2 Facility and Equi pment Design Features sections
- a. all subsections
- b. (2), (3), (5), (7), (8), (10)
- c. (2), (3) d- (1), (2), (4)
(6)
- e. all subsections
- f. (1), (2), (3)
- g. all subsections h.
(8)
- i. (11),
(15)
- j. shielding by maintaining the steam generator water level when possible.
Revise section 3.3.4.2 to include a ccmmitment to implement a
bioassay program in accordance with Regulatory Guide 8.9, "Acceptable
- Concepts, Models, Equation, and Assumptions for a Bioassay Program," or equivalent alternative.
Provide a copy of your analysis resulting in person-rem estimates for the mechanical and electro-poli shing decontamination, cutting of the divider plate, cutting the steam generator channel head and the steam generator blowdown pipi ng and upper dome.
This should include for each:
(1) a detailed procedure outline (2) the timq and personnel involved in the job (3) dose rate estimated i n the area where the job will be performed (4) total man-rem to complete job.
Provide the basis for the decontamination factor (DF) of 12 on page 3.17.
Provide a description of your contamination control program i ncl uBi ng:
(1) Limits for demarcation of controlled surface contamination areas and for release of equipment and facilities for unre-stricted use (acceptable limits are listed in Regulatory Guide 1.86, "Termination of Operating Licenses for,Nuclear Reactors,"
or equi val ent alternative).
331-2 (2) methods of restricting contamination to controlled surface contamination areas.
(3) specification of skin dose eval uation criteri a includi ng action points for dose evaluation.
Provide a breakdown of the person-rem for the project, dividing the doses into four phases -- preparation, removal, installation and storage.
In the event of a large volatilization accident with the decontamination solution at Turkey Point, what precautions have been taken to assure safe habitability or evacuation of the workers in the steam generator areas:
(1),how will'he workers in other areas be notified of such an event; (2) what protection is afforded to the workers; and (3) what procedures will be followed in the event of such an accident?
What is the estimated dose to workers for such an accident?
Provide a description of the radiation protection training program for outside contractor personnel working in restricted areas.
Describe your administrative control system to assure that worker dose will be 'kept within the limits of Part 20 and will be maintained ALARA.
Describe the new facilities for the project, including locker
- rooms, shower
- rooms, access control stations, laboratory facili-ties for radioactivity analyses, and decontamination facilities (for equipment and personnel).
Indicate in a table the radiation protection equipment that is provided during this operation to meet the anticipated needs of the operating unit (for normal and accident conditions) and the steam generator repair project.
Include in the table the types of i nstruments, their numbers, sensitivi ties, and ranges.
In
- addition, include a table specifying the quantity and types of respiratory protection equipment available.
Describe the organization and staffing necessary to provide the radiation protection program for the steam generator replace-
~
ment.
Identify by title the individuals who will be responsible for the program and describe their functional responsibilities, experience and qualifications.
II I
~
v-331-3 t
Describe the reasons for the estimated increase'rom 1301 man-rems/
unit to 2985 per unit.
Your application specifies that a substantial'ortion of your ALARA program is written in the FPL Health Physics Manual.
Provide a.copy of the FPL Health Physics Hanual.
. Describe the cutup and handling for alternatives a,
b and c in Table 3.4-3.
It should include items 1-4 in question 3.
'