ML17339A339

From kanterella
Jump to navigation Jump to search
Forwards IE Insp Repts 50-250/79-30 & 50-251/79-30 on 790924-28.No Noncompliance Noted
ML17339A339
Person / Time
Site: Turkey Point  NextEra Energy icon.png
Issue date: 10/17/1979
From: Sutherland J
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
To: Robert E. Uhrig
FLORIDA POWER & LIGHT CO.
Shared Package
ML17339A340 List:
References
NUDOCS 7911300147
Download: ML17339A339 (3)


See also: IR 05000250/1979030

Text

~R RED

~o

Op

ClO

I

Op

~O

++*++

UNITED STATES

NUCLEAR REGULATORY COMMISSION

REGION II

101 MARIETTAST., N.W., SUITE 3100

ATLANTA,GEORGIA 30303

In Reply Refer To:

RII:PAT

50-250/79-30

50"251/79-30

OCT 1 7 879

Florida Power and Light Company

Attn:

R. E. Uhrig, Vice President

Advanced

Systems

and Technology

Post Office Box 529100

Miami, Florida

33152

Gentlemen:

This refers to the inspection

conducted

by P.

AD Taylor of this office on

September

24-28,

1979 of activities authorized by NRC License

Nos.

DPR-31

and

DPR-41 for the Turkey Point facility, and to the discussion of our findings held

with H. E. Yaeger at the conclusion of the inspection.

Areas

examined during the inspection

and our findings are discussed

in the

enclosed

inspection report.

Within these

areas,

the inspection consisted of

selective

examinations

of procedures

and representative

records,

interviews with

personnel,

and observations

by the inspectors.

Within the scope of this inspection,

no items of noncompliance

were disclosed.

We have

examined actions you have taken with regard to previously reported

unresolved

items.

The status of these

items is discussed

in the enclosed report.

Two new unresolved

items resulted

from this inspection

and are discussed

in the

enclosed report.

These

items will be examined during subsequent

inspections.

In accordance

with Section 2.790 of the NRC's "Rules of Practice",

Part 2,

Title 10,

Code of Federal Regulations,

a copy of this letter and the enclosed

inspection report will be placed in the NRC's Public Document

Room. If this

report contains

any information that you (or your contractor) believe to be

proprietary, it is necessary

that you make

a written application within 20 days

to this office to withhold such information from public disclosure.

Any such

application must include

a full statement

of the reasons

on the basis of which

it is claimed that the information is proprietary,

and should be prepared

so

that proprietary information identified in the application is contained in a

separate

part of the document.

If we do not hear from you in this regard within

the specified period,

the report will be placed in the Public Document Room.

79113 00

OCT 17 1979

Florida Power and Light Company

Should you have

any questions

concerning this letter,

we will be glad to discuss

them with you.

Sincerely,

T. Sutherland,

Chief

Fuel Facility and Materials

Safety Branch

Enclosures:

Inspection Report Nos. 50-250/79-30

and 50-251/79-30

cc w/enclosures:

H. E. Yaeger, Plant Manager

Post Office Box 013100

Miami, Florida

33101