NRC Hq Pre-Submittal LaSalle CSCS LAR 12-7-2017 Final
ML17339A181
Person / Time
Site: LaSalle  Constellation icon.png
Issue date: 12/07/2017
From: Kimberly Green
Plant Licensing Branch III
To:
Green K, NRR/DORL/LPLIII
Shared Package
ML17339A178 List:
References
Download: ML17339A181 (18)


Text

License Amendment Request for CSCS-ECW Repairs at LaSalle County Station NRC/Exelon Meeting, NRC Headquarters Guy Ford Larry Lehman Ryan Sprengel December 7, 2017

Agenda

  • Introductions and Opening Remarks
  • Objectives
  • Need for Licensing Action
  • Maintenance Details
  • License Amendment Request Overview
  • Regulatory Evaluation
  • Summary
  • Schedule 1

Objectives

  • Present and discuss maintenance activities and need for License Amendment Request (LAR)
  • Describe key aspects of the planned LAR
  • Present proposed Technical Specification (TS) changes
  • Discuss and receive feedback on the key aspects and proposed changes 2

Need for Licensing Action

  • The planned LAR is to support plant maintenance which will improve equipment reliability.
  • Proposed changes will allow installation of isolation valves and proactive CSCS-ECW piping maintenance without a dual unit shutdown.
  • The maintenance replaces piping that has degraded due to long term wear and corrosion. The new isolation valves will also ensure future isolation capability.
  • Four outages will be utilized to align divisional work for each unit, two divisions on each of the two units:
  • L2R17 (2019) - Division 2
  • L1R18 (2020) - Division 1
  • L2R18 (2021) - Division 1
  • L1R19 (2022) - Division 2 3

Need for Licensing Action

  • The proposed CSCS-ECW maintenance replaces 4 and 6 DGCW piping and installs new isolation valves. The specific pipelines are 1DG06A-4, 1DG23B-6, 2DG06A-4 and 2DG23B-6. Because the downstream side of the pipelines are not currently equipped with isolation valves, the lines will be isolated by hot tapping and installing line stops.
  • CSCS-ECW is subject to the requirements of the ASME B&PV Code Section III. Because the line stops are non-Code the impacted CSCS-ECW subsystems will be declared inoperable.
  • Even though inoperable, the impacted CSCS-ECW subsystems, will remain available with no impact on risk or design function (see slide 10).
  • 7 days will allow sufficient time to install and test new isolation valves to provide ASME B&PV Code Section III isolation capability.

4

Maintenance Details - Line Stop (Stopple)

  • Line Stop - nonconforming line-stop used to isolate branch lines and allow installation of isolation valves
  • Will be designed to meet or satisfy system design requirements (e.g. pressure capacity and seismically mounted) 5

Maintenance Details - Division 1 6

Maintenance Details - Unit 1, Division 2 7

Maintenance Details - Unit 2, Division 2 8

Maintenance Details - DGCW Supported Systems

  • DGCW Division 1
  • Division 1 DG (Common 0)
  • ECCS cubicle area coolers
  • LPCS pump motor cooler
  • DGCW Division 2
  • Division 2 DGs (Unit 1 1A and Unit 2 2A)
  • ECCS cubicle area cooler
  • Redundant equipment and divisions will be protected in accordance with the LaSalle County Station risk management program 9

License Amendment Request Overview

  • Example: Unit 2, Division 2 System/Equipment Outage Planned Work Affected Subsystems*

Remaining Replace a 70 ft section of piping U-2, Div-2 DGCW U-2, Div-1 DGCW 2DG06A-4 between valve Inoperable/available Operable 2DG007 and line 2RH83BB-24. U-2, Div-2 DG 2A U-2, Div-1 RHRSW Inoperable/available Operable And U-2, Div-2 RHRSW U-0, Div-1 DG 0A Inoperable/available Operable L2R17 Install new isolation valve in line U-1, Div-2 DGCW U-1, Div-1 DGCW 2019 Inoperable/available Operable 2DG06A-4 adjacent to line U-1, Div-2 DG 1A U-1, Div-1 RHRSW 2RH83BB-24.

Inoperable/available Operable U-1, Div-2 RHRSW 2DG06A-4 is part of the U-2, Div -2 DGCW Inoperable/available subsystem

(*) Work is being performed on Unit 2, Division 2 DGCW subsystem; both units share a common Division 2 discharge line, therefore the work also affects the Unit 1, Division 2. Additional, supported systems are not included in this table.

10

License Amendment Request Overview

  • Single submittal applicable to four outages:
  • L2R17 (2019) - Division 2
  • L1R18 (2020) - Division 1
  • L2R18 (2021) - Division 1
  • L1R19 (2022) - Division 2
  • Proposed change to TS 3.7.2 Conditions to allow 7 days with DGCW subsystems inoperable but available
  • Proposed change to TS 3.8.1 Conditions to allow 7 days with Division 2 Diesel Generators on both units inoperable but available 11

License Amendment Request Overview

  • Proposed TS changes provided as handout
  • Applicability is constrained to four upcoming outages
  • During the maintenance period, additional TS Conditions may be entered, with no changes requested
  • The Safety Function Determination Program (SFDP) will be applied as appropriate for supported systems with no Loss of Safety Function 12

Regulatory Evaluation

  • Regulatory requirements:
  • Licensing Basis
  • UFSAR Section 9.2.1 CSCS Equipment Cooling Water
  • Precedent Amendments
  • LaSalle County Station 75/161, 180/167
  • Braidwood Station 30
  • Byron Station 136 13

Summary

  • EGC is planning to submit a LAR to support plant maintenance which will improve equipment reliability.
  • The LAR will propose changes which would revise TS 3.7.2 and 3.8.1 to allow 7 days with one or more DGCW trains inoperable and two Division 2 DGs inoperable, during four upcoming refueling outages
  • Additional system inoperability will be evaluated using the Safety Function Determination Program and will follow existing TS LCOs
  • Discussion and feedback is requested on the key aspects and proposed changes 14

Schedule for Submittal

  • EGC plans to submit the license amendment request in January 2018 15

Questions?

16

Acronym Key

  • ASME B&PV Code - American Society of Mechanical Engineers Boiler and Pressure Vessel Code
  • CFR - Code of Federal Regulations
  • DG - Diesel Generator
  • DGCW - Diesel Generator Cooling Water
  • EGC - Exelon Generation Company
  • LCO - Limiting Condition for Operation
  • NRC - U.S. Nuclear Regulatory Commission
  • TS - Technical Specification