Notice of Violation from Insp on 781106-09
ML17338A427
Person / Time
Site: Turkey Point  NextEra Energy icon.png
Issue date: 11/30/1978
From:
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
To:
Shared Package
ML17338A422 List:
References
50-250-78-27, 50-251-78-27, NUDOCS 7901170441
Download: ML17338A427 (2)


Text

~P,Q Rhody (4

Op0 eo 0

~a*++

UNITED STATES NUCLEAR REGULATORY COMMISSION REGION II 101 MARIETTASTREET, N.W.

ATLANTA,GEORGIA 30303 RePort NoeI 50-250/78-27 and 50-251/78-27 Docket No.:

50-250 and 50-251 License NoeI DPR-31 and DPR-41 Licensee:

Florida Power and Light Company P.

O.

Box 023100 9250 West Flagler Street Miami, Florida 33101 Facility Name:

Turkey Point Units 3 and 4

Inspection conducted:

November 6-9, 1978 Inspectors:

E.

H. Verdery S. A. Elrod Approved by:

Z C.

R.

C. Lewis, Chief Reactor Projects Section No.

2 Reactor Operations and Nuclear Support Branch Date Ins ection Summar Ins ection on November 6-9 1978 (Re ort Nos. 50-250/78-27 and 50-251/78-27)

Areas Ins ected:

Routine, unannounced inspection of plant operations; licensee corrective actions on items of noncompliance; licensee actions on reportable events; tour of accessible plant areas; and follow-up on open and unresolved items.

The inspection involved 64 inspector-hours on-site by two NRC inspectors.

Results:

Of the five areas inspected, no items of noncompliance were found in three areas; two apparent items of noncompliance were found in two areas (infraction - failure to establish and implement housekeeping and removal of combustible materials program (250/78-27-01, 251/78-27-01)

- paragraph I-5a; infraction - failure to conduct gC surveillance as required (250/78-27-02, 251/78-27-02)

- paragraph I-5b).

One previously cited item of noncompliance denied by the licensee was confirmed as noncompliance - paragraph I-6.