Forwards IE Inspec Repts 50-250/78-19 & 50-251/78-19 on 780828-31 During Which No Items of Noncompliance Were Noted
ML17338A293
Person / Time
Site: Turkey Point  NextEra Energy icon.png
Issue date: 10/17/1978
From: Murphy C
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
To: Robert E. Uhrig
FLORIDA POWER & LIGHT CO.
Shared Package
ML17338A292 List:
References
NUDOCS 7811240027
Download: ML17338A293 (3)


See also: IR 05000250/1978019

Text

<p,s ~aco<

Wp

+

0

Op

lfit*44

In Reply Refer To:

RII:JJB

50-250/78-19

50-251/78-19

UNITED STATES

NUCLEAR REGULATORY COMMISSION

REGION II

101 MARIETTASTREET, N.W.

ATLANTA,GEORGIA 30303

DCT 1 V >978

Florida Power

and Light Company

Advanced

Systems

6 Technology

Attn:

Robert E. Uhrig, Vice President

P. 0.

Box 529100

MiarIIi, Florida

33152

Gentlemen:

This refers to the inspection

conducted

by Mr. J. J.

Blake of this

office on August 28-31,

1978, of activities authorized

by NRC Operating

License

Nos.

DPR-31

and

DPR-41 for the Turkey Point Units

3 and

4

facilities,

and to the discussion of our findings held with Mr. J.

K. Hays

at the conclusion of the inspection.

Areas

examined during the inspection

and our findings are discussed

in

the enclosed

inspection report.

Within these

areas,

the inspection

consisted

of selective

examinations

of procedures

and representative

records,

interviews with personnel,

and observations

by the inspector.

Within the scope of this inspection,

no items of noncompliance

vere

disclosed.

In accordance

with Section 2.790 of the NRC's "Rules of Practice",

Part 2, Title 10,

Code of Federal Regulations,

a copy of this letter

and

the enclosed

inspection report will be placed in the NRC's Public

Document

Room.

If this report contains

any information that you (or

your contractor) believe to be proprietary, it is necessary

that you

make

a written application within 20 days to this office to vithhold

such information from public disclosure.

Any such application

must

include

a full statement

of the reasons

on the basis of which it is

claimed that the information is proprietary,

and should

be prepared

so

that proprietary information identified in the application is contained

in a separate

part of the document.

If ve do not hear

from you in this

regard vithin the specified period, the report will be placed in the

Public Document

Room.

g.sLMV

Florida Power

and Light Co.

-2"

Should you have

any questions

concerning this letter,

we will be glad

to discuss

them with you.

Sincerely,

C.

E. Murphy, Chief

Reactor Construction

and

Engineering

Support

Branch

Enclosure:

Inspection Report Nos.

50-250/78-19

and 50-251/78-19

cc w/encl:

Mr. H. E. Yaeger,

Plant Manager

Turkey Point Plant

P.

O.

Box 013100

9250 West Flagler Street

Miami, Florida

33101