Monthly Operating Rept for Apr 1997 for DC Cook Nuclear Plant Unit 2
ML17334B623
Person / Time
Site: Cook 
Issue date: 04/30/1997
From: Minor J, Sampson J
INDIANA MICHIGAN POWER CO.
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
References
NUDOCS 9705130080
Download: ML17334B623 (8)


Text

CATEGORY 1 REGULAT INFORMATION DISTRIBUTION STEM (RIDS)

ACCESSIOQ NBR:9705130080 DOC.DATE: 97/04/30 NOTARIZED: NO FACIL:50-316 Donald C.

Cook Nuclear Power Plant, Unit 2, Indiana M

AUTH.NAME AUTHOR AFFILIATION

'INOR,J.W.

Indiana Michigan Power Co.

SAMPSON,J.R.

Indiana Michigan Power Co.

RECIP.NAME RECIPIENT AFFILIATION DOCKET 05000316

SUBJECT:

Monthly operating rept for Apr 1997 for DC Cook Nuclear Plant Unit 2.W/970502 ltr.

DISTRISDTION CODE:

IE24D COPIES RECEIVED:LTR I

ENCL i SIZE.

TITLE: Monthly Operating Report (per Tech Specs)

NOTES:

C' RECIPIENT ID CODE/NAME PD3-3 PD INTERNAL: AEOD/SPD/RRAB NRR/DRPM/PECB RGN3 COPIES LTTR ENCL 1

1 1

1 1

1 1

1 RECIPIENT ID CODE/NAME HICKMAN J LE CENTER 01 OC'BA" 'P 'D" COPIES LTTR ENCL 1

1 1

1 1

1 EXTERNAL: LITCO BRYCE,J H

NRC PDR 1

1 1

1 NOAC 1

1 D

0 N

NOTE TO ALL "RIDS" RECIPIENTS:

PLEASE HELP US TO REDUCE WASTE.

TO HAVE YOUR NAME OR ORGANIZATION REMOVED FROM DISTRIBUTION LISTS OR REDUCE THE NUMBER OF COPIES RECEIVED BY YOU OR YOUR ORGANIZATION, CONTACT THE DOCUMENT CONTROL DESK (DCD)

ON EXTENSION 415-2083 TOTAL NUMBER OF COPIES REQUIRED:

LTTR 10 ENCL 10

~ K ~

I 1

I

Indiana Michig'an Power Company ~

Cook NUclear Plant~

One Cook Place Biidgman, MI49106 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, D.C. 20555 May 2, 1997 Gentlemen, Pursuant to the requirements of Donald C. Cook Nuclear Plant Unit 2 Technical Specification 6.9.1.10, the attached Monthly Operating Report for the month of April 1997 is submitted.

Sincerely, J.R. Sampson Plant Manager

/mr Attachment y3000'7 NRC Region III D.R. Hahn R.C. Callen S.

Hamming INPO Records Center ANI Nuclear Engineering Department E.E. Fitzpatrick A.A. Blind P.A. Barrett S.J. Brewer D.W. Paul J.A. Kobyra D.L. Noble W.H. Schalk D.G; Turner B.L. Bartlett M.E. Russo t!

IIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIII

'705i30080 970430 PDR ADQCK 050003ih R

PDR

\\

tQ N.R.C. OPERATING DATAREPORT DOCKET NO.

50 - 316 DATE May 2, 1997 COMPLETED BY JW Minor TELEPHONE 616465-5901 OPERATING STATUS

1. Unit Name
2. Reporting Period
3. Licensed Thermal Power (MWt)
4. Name Plate Rating (Gross MWe)
5. Design Electrical Rating (Net MWe)
6. Maximum Dependable Capacity (GROSS M
7. Maximum Dependable Capacity (Net MWe)

D. C. Cook Unit2 Apr-97 3411 1133 1090 We) 1100 1060 Notes:

8. IfChanges Occur in Capacity Ratings (Items no. 3 through 7) Since Last Report Give Reasons:

I 9.

Power Level To Which Restricted, IfAny (Net MWe):

10. Reasons For Restrictions, IfAny:
11. Hours in Reporting Period
12. No. of Hrs. Reactor Was Critical
13. Reactor Reserve Shutdown Hours
14. Hours Generator on Line
15. Unit Reserve Shutdown Hours
16. Gross Thermal Energy Gen. (MWH)
17. Gross Electrical Energy Gen. (MWH)
18. Net Electrical Energy Gen. (MWH)
19. Unit Service Factor
20. Unit AvailabilityFactor
21. Unit Capacity Factor (MDC Net)
22. Unit Capacity Factor (DER Net)
23. Unit Forced Outage Rate This Month 720.0 720.0 0.0 720.0 0.0 2451401.1 809740.0 783532.0 100.0 100.0 102.7 99.8 0.0 Year-to-Date 2880.0 2754.2 0.0 2717.5 0.0 8738130.9 2878300.0 2781404.0 94.4 94.4 91.1 88.6 5.6 Cumulative 169440.0 118766.1 0.0 115165.1 0.0 355916397.9 115382690.0 111163970.0 69.0 69.0 62.7 61.1 14.0
24. Shutdowns Scheduled over Next Six Months (Type, Date, and Duration):

Refuelin outa e to be in Se tember19 1997 for an estimated duration of48da s

25. IfShut Down At End of Report Period, Estimated Date of Startup:
26. Units in Test Status (Prior to Commercial Operation):

INITIALCRITICALITY INITIALELECTRICITY COMMERCIALOPERATION Forecast Achieved

E

~

DOCKET NO.

UNIT NAME DATE COMPLETED BY TELEPHONE 50- 316 D.C. Cook Unit 2 May 2, 1997 JW Minor 616465-5901 AVERAGE DAILYPOWER LEVEL (MWe-Net)

APRIL 1997 DAY AVERAGE DAILY POWER LEVEL DAY AVERAGE DAILY POWER LEVEL 4/1/97 4/2/97 4/3/97 4/4/97 4/5/97 4/6/97 4/7/97 4/8/97 4/9/97 4/10/97 4/11/97 4/12/97 4/13/97 4/14/97 4/15/97 4/16/97 1090 1096 1096 1091 1073 1084 1079 1081 1075 1078 1080 1096 1096 1093 1093 1095 4/17/97 4/18/97 4/1 9/97 4/20/97 4/21/97 4/22/97

'/23/97 4/24/97 4/25/97 4/26/97 4/27/97 4/28/97 4/29/97 4/30/97 1086 1086 1092 1093 1093 1093 1092 1093 1089 1090 1089 1088 1084 1084

~

~

1 DOCKET NO.

UNIT NAME DATE COMPLETED BY TELEPHONE

'PAGE 50 - 316 D.C. Cook Unit 2 May 2, 1997 ME Russo 616-697-5100 1 of1 MONTHLYOPERATING ACTIVITIES-APRIL 1997 HIGHLIGHTS The unit entered this reporting period in Mode 1 at 100% RTP.

The unit exited this reporting period in Mode 1 at 100% RTP.

There were no challenges to the pressurizer safety valves or power operated relief valves.

Gross electrical generation for the month of Aprilwas 809740 MWh.

DETAILS No details to report.

f

~,n

DOCKET NO.

UNIT NAME DATE COMPLETED BY TELEPHONE PAGE 50 - 316 D.C. Cook Unit 2-f May 2, 1997 ME Russo 616497-5100 1 of1 UNITSHUTDOWNS AND POWER REDUCTIONS - APRIL 1997 METHOD OF SHUTTING LICENSEE DURATION DOWN EVENT SYSTEM COMPONENT NO.

DATE TYPE" HOURS REASON2 REACTOR>

REPORT NO.

CODE4 CODE5 CAUSE AND CORRECTIVE ACTION TO PREVENT RECURRENCE None There were no unit shutdowns or significant power reductions from 100%

RTP this month.

1 TYPE:

F: Forced S: Scheduled 2 REASON:

A: Equipment Failure (Explain)

B: Maintenance or Test C: Refueling D: Regulatory Restriction E: Operator Training and License Examination F: Administrative G: Operational Error (Explain)

H: Other (Explain) 3 METHOD:

1: Manual 2: Manual Scram 3: Automatic Scram 4: Other (Explain) 4 SYSTEM:

Exhibit G - Instructions for preparation of data entry sheets for Licensee Event Report (LER) File (NUREG 0161) 5 COMPONENT:

Exhibit I: Same Source