ACCELERATED D RIBUTION DEMONST TION SYSTEM I
REGULATORY INFORMATION DISTRIBUTION SYSTEM (RIDS)
DOCKET 05000315 05000316 wrxtte P
DISTRIBUTION CODE:
IE23D COPIES RECEIVED:LTR ENCL SIZE:
TITLE: Environmental Event Report (per Tech Specs)
NOTES:
ACCESSION NBR:9103040344 DOC.DATE: 91/02/26 NOTARIZED: NO FACIL:50-315 Donald C.
Cook Nuclear Power Plant, Unit 1, Indiana 50-316 Donald C.
Cook Nuclear Power Plant, Unit 2, Indiana AUTH.NAME AUTHOR AFFILIATION BAKER,D.L.
(formerly Indiana
& Michigan Ele RECIP.NAME RECIPIENT AFFILIATION MORLEY,F.
Michigan, State of I
SUBJECT:
NPDES noncompliance notification:on 910220
& 2l,unmonitored discharges occurred from turbine room sump. Caused by D
inoperable pH meter. Turbine sump room isolated
& job order n to re air meter.
RECIPIENT ID CODE/NAME PD3-1 LA COLBURN,T.
INTERNAL: AEOD/DSP/TPAB NRR/DREP/PEPB9D OGC/HDS2 RGN3 EXTERNAL: NRC PDR COPIES LTTR E CL 3
1 RECIPIENT ID CODE/NAME PD3-1 PD AEOD/PTB NRR PMAS ILRB12 01 RGB/'D
/EPRPB NSIC COPIES LTTR ENCL D
D R
NOTE TO ALL"RIDS" RECIPIENTS:
D D
PLEASE HELP US TO REDUCE WASTE! CONTACI'HE DOCUMENT CONTROL DESK, ROOM P 1-37 (EXT. 20079) TO ELIMINATEYOUR NAME FROM DISTRIBUTION LISTS FOR DOCUMENTS YOU DON'T NEED!
TOTAL NUMBER OF COPIES REQUIRED:
LTTR 15 ENCL
Indiana I'~michigan~
Power Company ~
One Summit Square P.O. Box 60 Fort Wayne, IN 46801 219 425 2111 RF ENQIANA NICMIGAM FORAM February 26, 1991 Fred Morley, District Supervisor Surface Water Quality Division Michigan Department of Natural Resources 621 North 10th Street P.O.
Box 355 Plainwell, MI 49080
Dear Mr. Morley:
RE:
NPDES Permit No. MI 0005827 Cook Nuclear Plant Bridgman, Michigan Between the hours of 0745 1324 and 1651 1955 on February 20,
- 1991, and 0022 and 0750 on February 21,
These resulted from an inoperable pH
- meter, which was discovered during the daily calibration check on February 21.
The Turbine Room.Sump was isolated immediately upon discovery and a
job order was written to repair the pH meter.
In the interim, discharges from the Sump are being manually sampled for pH.
An estimated 700,000 gallons of water were released prior to the sump isolation.
We have no reason to believe that any effluent limitations were exceeded during this period.
Very truly yours, g~g/Su&~
Donald L. Baker Environmental Affairs Director DLB/cyj c:
A. B. Davis NRC Region III J.
A. Isom NRC Resident Inspector (Dr. T. E. Murl'ey N~RR NRC Document Control 9103040344 910226 PDR "ADOCK 05000315 S
0 r