Forwards Insp Repts 50-315/97-18 & 50-316/97-18 on 970926- 1107 & Notice of Violations Re Examples of Inadequate Emergency Operating Procedures
ML17334A619
Person / Time
Site: Cook  American Electric Power icon.png
Issue date: 01/13/1998
From: Grant G
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
To: Fitzpatrick E
AMERICAN ELECTRIC POWER CO., INC.
Shared Package
ML17334A620 List:
References
50-315-97-18, 50-316-97-18, NUDOCS 9801210190
Download: ML17334A619 (8)


See also: IR 05000315/1997018

Text

gAR 4EC(g~

P0

Cy

0

p"

++*++

UNITED STATES

NUCLEAR REGULATORY COMMISSION

REGION III

801 WARRENVILLEROAD

LISLE, ILLINOIS60532-4351

January 13, 1998

Mr. E. E. Fitzpatrick

Executive Vice President

Nuclear Generation Group

American Electric Power Company

500 Circle Drive

Buchanan,

MI 49107-1395

SUBJECT:

NOTICE OF VIOLATIONAND NRC INSPECTION REPORT

NO. 50-315/97018(DRP); 50-316/97018(DRP)

Dear Mr. Fitzpatrick:

On November 7, 1997, the NRC completed an inspection at your D. C. Cook 1 and 2 reactor

facilities. The enclosed report presents the results of that inspection.

During the 6-week period covered by this inspection report, the inspectors observed that the

plant was operated in a safe manner, maintenance was generally performed well, and

radiological work practices were properly followed.

Based on the results of this inspection, one violation of NRC requirements was identified. The

violation is cited in the enclosed Notice of Violation (Notice), and the circumstances

surrounding

it are described in detail in the subject inspection report. The violation is of concern because the

inspectors identified two examples of inadequate operations procedures, that were used for

cross-tying safety-related buses, containing Insufficient guidance to ensure that the activities

were properly conducted.

A third example of the violation identified a procedure that contained

incorrect set points and is of concern because the emergency operating procedure for

responding to reactor trips and safety injections contained values different than the plant set-

point document.

You are required to respond to this letter and should followthe instructions specified in the

enclosed Notice when preparing your response.

The NRC willuse your response,

in part, to

determine whether further enforcement action is necessary to ensure compliance with regulatory

requirements.

~>) +pe 'j

lllllllllllllllllllllllllllllllllllllll

980i2iOi90 980ii3

PDR

ADQCK 050003i5

8

PDR

E. Fitzpatrick

-2-

In accordance with 10 CFR 2.790 of the NRC's "Rules of Practice," a copy of this letter, its

enclosures,

and your response will be placed in the NRC Public Document Room.

Sincerely,

Geoffrey E. Grant, Director

Division of Reactor Projects

Docket No. 50-315, 50-316

License No. DPR-58, DPR-74

Enclosures:

1.

Notice of Violation

2.

Inspection Report

No. 50 315/970018(DRP); 50-316/97018(DRP)

cc w/encls:

A. A. Blind, Site Vice President

John Sampson,

Plant Manager

Richard Whale, Michigan Public

Service Commission

Michigan Department of

Environmental Quality

lt

E. Fitzpatrick

-2-

In accordance with 10 CFR 2.790 of the NRC's "Rules of Practice," a copy of this letter, its

enclosures,

and your response willbe placed in the NRC Public Document Room (PDR).

Sincerely,

/s/ Narc L. Dapas

Docket No. 50-315, 50-316

License No. DPR-58, DPR-74

Geoffrey E. Grant, Director

Division of Reactor Projects

Enclosures:

cc w/encls:

1.

Notice of Violation

2.

Inspection Report

No. 50-315/970018(DRP); 50-316/97018(DRP)

A. A. Blind, Site Vice President

John Sampson,

Plant Manager

Richard Whale, Michigan Public

Service Commission

Michigan Department of

Environmental Quality

Distribution:

Docket File w/encls

PUBLIC IE-01 w/encls

Project Manager, NRR w/encls

Rill Enf. Coordinator w/encls

CAA1 w/encls (E-mail)

TSS w/encls

DRP w/encls

SRI DC Cook w/encls

A. B. Beach w/encls

Deputy RA w/encls

Rill PRR w/encls

DRS (2) w/encls

DOCDESK (E-mail)

DOCUMENT NAME: R:Insprptshpowershcookhdcc97018.drp

SEE PREVIOUS CONCURRENCES

To recehre e copy of this document, Indicete In the box

C

~ Copy without ettechment/enclosure

E

m Copy with ettechment/enclosure

N" aNoco

OFFICE

Rill

Rill

Rill

Rill

NAME

Schweibinz:dp

Burgess

Creed

Grant

DATE

01/ /98

01/ /98

01/ /98

01P'898

OFFICIALRECORD COPY

E. Fitzpatrick

-2-

In accordance with 10 CFR 2.790 of the NRC's "Rules of Practice," a copy of this letter, its

enclosures,

and your response willbe placed in the NRC Public Document Room (PDR).

Sincereiy,

/s/ Narc L. Dapas

Geoffrey E. Grant, Director

Division of Reactor Projects

Docket Nos. 50-315, 50-316

License Nos. DPR-58, DPR-74

Enclosures:

1.

Notice of Violation

2.

Inspection Report

No. 50-315/970018(DRP); 50-316/97018(DRP)

cc w/encls:

A. A. Blind, Site Vice President

John Sampson,

Plant Manager

Richard Whale, Michigan Public

Service Commission

Michigan Department of

Environmental Quality

Distribution:

Docket File w/encls

PUBLIC IE-01 w/encls

Project Manager, NRR w/encls

Rill Enf. Coordinator w/encls

CAA1 w/encls (E-mail)

TSS w/encls

DRP w/encls

SRI DC Cook w/encis

A. B. Beach w/encis

Deputy RA w/encls

Rill PRR w/encls

DRS (2) w/encls

DOCDESK (E-mail)

DOCUMENT NAME: R:hlnsprptstpowershcookhdcc97018.drp

To receive s copy of this document, Indlcste In the box

C

~ Copy without sttschmentlencloeure

E

s Copy wtth sttschment/enclosure

N

s Noes

OFFICE

NAME

.

DATE

Rill

Schweibinz:d

@

0119/98

Rill

p

I

Bur

s

01498

RIII

01

/98

RIII

Grant

01/ /98

OFFICIALRECORD COPY