CATEGORY 1
REGULATOFINFORMATION DISTRIBUTION TEM (RIDE)
>ACCESSION NBR:9708140255 DOC.DATE: 97/07/31 NOTARIZED:
NO FACZL:5t0-316 Donald C.
Cook Nuclear Power Plant, Unit 2, Indiana M
AUTH.NOME AUTHOR AFFILIATION MINOR,J.W.
American Electric Power Co., Inc.
CENTER,J.F.
American Electric Power Co., Inc.
SAMPSON,J.R.
American Electric Power Co., Inc.
'ECZP.NAME RECIPIENT AFFILIATION DOCKET 05000316
SUBJECT:
Monthly operating rept for Jul 1997 for DC Cook Nuclear Plant, Unit 2.W/970807 ltr.
(
DISTRIBUTION CODE:
IE24D COPIES RECEIVED:LTR ENCL SIZE:
TITLE: Monthly Operating Report (per Tech Specs)
NOTES:
RECIPIENT ID CODE/NAME PD3-3 PD INTERNAL: AEOD/SPD/RRAB NRR/DRPM/PECB RGN3 COPIES LTTR ENCL 1
1 RECIPIENT ID CODE/NAME HICKMAN,J 1
FILE CENTER 1
1 COPIES LTTR ENCL 1
1 1
1 1
1 EXTERNAL: LITCO BRYCE,J H
NRC PDR 1
1 1
1 NOAC 1
1 NOTE TO ALL "RIDS" RECIPIENTS:'LEASE HELP US TO REDUCE WASTE!
CONTACT THE DOCUMENT CONTROL DESK, ROOM OWFN 5D-5(EXT ~ 415-2083)
TO ELIMINATE YOUR NAME FROM DISTRIBUTION LISTS FOR DOCUMENTS YOU DON'T NEED!
TOTAL NUMBER OF COPIES REQUIRED:
LTTR 10 ENCL 10
Indiana Michigan Power Company Cook Nuciear PIant One Cook Place Bridgman, MI49106 R
U.S. Nuclear Regulatory Commission" ATTN: Document Control Desk Washington, D.C. 20555 August 7, 1997 Gentlemen, Pursuant to the requirements of Donald C. Cook Nuclear Plant Unit 2 Technical SpeciTIcation 6.9.1.10, the attached Monthly Operating Report for the month of July 1997 is submitted.
Sincerely, J.R. Sampson Plant Manager
/jc Attachment NRC Region III D.R. Hahn R.C. Callen S.
Hamming B.
Lewis INPO Records Center ANI Nuclear Engineering Department E.E. Fitzpatrick A.A. Blind P.A. Barrett S.J. Brewer
.D.W. P.aul
'.A. Kobyra D.L. Noble W.H. Schalk D.G. Turner B.L. Bartlett M.E. Russo 9708%40255 9'7073i PDR ADOCK 050003ib R
PDR lillllllllilllilllilllllllllllllllllllll
.R.C. OPERATING DATAREPORT
~
~
~
DOCKET NO.
DATE COMPLETED BY TELEPHONE 50 - 316 August 4, 1997 JW Minor 616465-5901 OPERATING STATUS
- 1. Unit Name
- 2. Reporting Period
- 3. Licensed Thermal Power (MWt)
- 4. Name Plate Rating (Gross MWe)
- 5. Design Electrical Rating (Net MWe)
- 6. Maximum Dependable Capacity (GROSS M
- 7. Maximum Dependable Capacity (Net MWe)
D. C. Cook Unit2 Jul-97 3411 1133 1090 We) 1100 1060 Notes:
- 8. IfChanges Occur in Capacity Ratings (Items no. 3 through 7) Since Last Report Give Reasons:
9.
Power Level To Which Restricted, IfAny (Net MWe):
- 10. Reasons For Restrictions, IfAny:
- 11. Hours in Reporting Period
- 12. No. of Hrs. Reactor Was Critical
- 13. Reactor Reserve Shutdown Hours
- 14. Hours Generator on Line
- 15. Unit Reserve Shutdown Hours
- 16. Gross Thermal Energy Gen. (MWH)
- 17. Gross Electrical Energy Gen. (MWH)
- 18. Net Electrical Energy Gen. (MWH)
- 19. Unit Service Factor
- 20. Unit AvailabilityFactor
- 21. Unit Capacity Factor (MDC Net)
- 22. Unit Capacity Factor (DER Net)
- 23. Unit Forced Outage Rate This Month 744.0 744.0 0.0 744.0 0.0 2530391.7 796170.0 769267.0 100.0 100.0 97.5 94.9 0.0 Year-to-Date 5088.0 4823.1 0.0 4769.8 0.0 15652839.1 5087500.0 4916445.0 93.7 93.7 91.2 88.7 6.3 Cumulative 171648.0 120835.0 0.0 1 17217.4 0.0 362831106.1 117591890.0 113299011.0 69.3 69.3 63.1 61.4 13.9
- 24. Shutdowns Scheduled over Next Six Months (Type, Date, and Duration):
Refueling outage to begin September 26, 1997 for an estimated duration of 40 days
- 25. IfShut Down At End of Report Period, Estimated Date of Startup:
- 26. Units in Test Status (Prior to Commercial Operation):
INITIALCRITICALITY INITIALELECTRICITY COMMERCIALOPERATION Forecast Achieved
DOCKET NO.
UNIT NAME DATE COMPLETED BY TELEPHONE 50- 316 D.C. Cook Unit 2 August 4, 1997 JW Minor 616465-5901 AVERAGE DAILYPOWER LEVEL (MWe-Net)
JULY 1997 DAY 7/1/97 7/2/97, 7/3/97 7/4/97 7/5/97 7/6/97 7/7/97 7/8/97 7/9/97 7/10/97 7/11/97 7/12/97 7/13/97 7/14/97 7/1 5/97 7/16/97 AVERAGE DAILY POWER LEVEL 1029 1032 1025 1029 1034 1032 1040 1042 1051 1050 1037 1036 1032 1027 1023 1019 DAY 7/1 7/97 7/1 8/97 7/19/97 7/20/97 7/21/97 7/22/97 7/23/97 7/24/97 7/25/97 7/26/97 7/27/97 7/28/97 7/29/97 7/30/97 7/31/97 AVERAGE DAILY POWER LEVEL 1017 1008 979 1023 1023
, 1041 1061 1065 1053 1031 1022 1024 1055 1066 1050
DOCKET NO.
UNIT NAME DATE COMPLETED BY TELEPHONE PAGE 50- 316 D.C. Cook Unit 2 August 5, 1997 JF Center 616-697-5098 1 of1 MONTHLYOPERATING ACTIVITIES-JULY 1997 HIGHLIGHTS The unit entered this reporting period in Mode 1 at 100% RTP.
The unit exited this reporting period in Mode 1 at 100% RTP.
There were no challenges to the pressurizer safety valves or power operated relief valves.
Gross electrical generation for the month of July was 796170 MWh.
DETAILS-07-18-97 07-1 9-97 1910 Commenced Reactor power reduction to conduct Moderator Temperature Coefficient testing.
0010 Reactor power stablized at 95% RTP.
1457 Moderator Temperature Coefficient testing complete.
Commenced Reactor power ascension.
1615 Power stablized at 100% RTP.
Alltime entries are Eastern Standard Time (EST).
DOCKET NO.
UNIT NAME DATE COMPLETED BY TELEPHONE PAGE 50 - 316 D.C. Cook Uhit2 August 5, 1997 JF Center 616-697-5098 1 of1 UNIT SHUTDOWNS AND POWER REDUCTIONS - JULY 1997 METHOD OF SHUTTING LICENSEE DURATION DOWN EVENT SYSTEM COMPONENT NO.
DATE TYPE" HOURS REASQN2 REACTQR3 REPORT NQ.
CODE4 CODE5 CAUSE ANDCORRECTIVE ACTION TO PREVENT RECURRENCE None There were no unit shutdowns or significant power reductions from 100% RTP this month.
1 TYPE:
F: Forced S: Scheduled 2 REASON:
A: Equipment Failure (Explain)
B: Maintenance or Test C: Refueling D: Regulatory Restriction E: Operator Training and License Examination F: Administrative G: Operational Error (Explain)
H: Other (Explain) 3 METHOD:
1: Manual 2: Manual Scram 3: Automatic Scram 4: Other (Explain) 4 SYSTEM:
Exhibit G - Instructions for preparation of data entry sheets for Licensee Event Report (LER) File (NUREG 0161) 5 COMPONENT:
Exhibit I: Same Source