ML17333A730

From kanterella
Jump to navigation Jump to search
Monthly Operating Rept for Dec 1996 for DC Cook Nuclear Plant Unit 2
ML17333A730
Person / Time
Site: Cook American Electric Power icon.png
Issue date: 12/31/1996
From: Minor J, Russo M, Sampson J
AMERICAN ELECTRIC POWER CO., INC.
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
References
NUDOCS 9701140212
Download: ML17333A730 (7)


Text

'

REGULA INFORMATION DISTRIBUTIO STEM (RIDS)

ACCESSION NBR:9701140212 DOC.DATE: 96/12/31 NOTARIZED:

NO DOCKET FACIL:50-316 Donald C.

Cook Nuclear Power Plant, Unit 2, Indiana M

05000316 AUTH.N~E AUTHOR AFFILIATION MINOR,J.W.

American Electric Power Co., Inc.

RUSSOEM.E.

American Electric Power Co., Inc.

SAMPSON,J.R.

American Electric Power Co., Inc.

RECIP.NAME RECIPIENT AFFILIATION

SUBJECT:

Monthly operating rept for Dec 1996 for DC Cook Nuclear Plant Unit 1.W/970103 ltr.

DISTRIBUTION CODE:

IE24D COPIES RECEIVED:LTR 1

ENCL 3 SIZE: 0 TITLE: Monthly Operating Report (per Tech Specs)

NOTES:

RECIPIENT ID CODE/NAME PD3-3 PD INTERNAL: AEOD/SPD/RRAB NRR/DRPM/PECB RGN3 EXTERNAL: LITCO BRYCE,J H

NRC PDR COPIES LTTR ENCL 1

1 1

1 1

1 1

1 1

1 1

1 RECIPIENT ID CODE/NAME HICKMAN,J E CENTER OC/DB PAD NOAC COPIES LTTR ENCL 1

1 1

1 1

1 1

1 D

U NOTE TO ALL "RIDS" RECIP1ENTS:

PLEASE HELP US TO REDUCE WASTE!

CONTACT THE DOCUMENT CONTROL DESK, ROOM OWFN 5D-5(EXT. 415-2083)

TO ELIMINATE YOUR NAME FROM DISTRIBUTION LISTS FOR DOCUMENTS YOU DON'T NEED!

TOTAL NUMBER OF COPIES REQUIRED:

LTTR 10 ENCL

'10

American Electric~

Cook Nuclear Plant One Cook Place Sridgman, Ml 49106 616 465 5901 January 3,

1997 k

U.S. Nuclear Regulatory Commission ATTN:

Document Control Desk Washington, D.C.

20S55 Gentlemen:

Pursuant to the requirements of Donald C.

Cook Nuclear Plant Unit 2 Technical Specification 6.9.1.10, the attached Monthly Operating Report for the month of December 1996 is submitted.

Respectfully, J.R.

Sampson Plant Manager Attachment c:

NRC Region III D.R.

Hahn R.C. Callen S.

Hamming INPO Records Center ANI Nuclear Engineering Department E.E. Fitzpatrick A.A. Blind P.A. Barrett S.J.

Brewer D.W. Paul J.A.

Kobyra D.L. Noble W.H. Schalk D.G. Turner B.L. Bartlett M.E. Russo R

N.R.C.

OPERATING DATA REPORT DOCKET NO.

50-316 DATE 03/Jan/97 COMPLETED BYJohn W. Minor TELEPHONE 616-465-5901 ATUS D.

C.

Cook Unit 2 OPERATING ST

1. Unit Name
2. Reporting Period DEC/96
3. Licensed Thermal Power (MWt) 3411 4.

Name Plate Rating (Gross MWe) 1133

5. Design Electrical Rating (Net MWe) 1090 6.

Maximum Dependable Capacity (GROSS MWe) 1100 7.

Maximum Dependable Capacity (Net MWe) 1060 notes

8. If Changes Occur in Capacity Ratings (Items no.

3 through

7) Since Last Report Give Reasons 9.

Power Level To Which Restricted. If Any (Net MWe) 10.. Reasons For Restrictions. If Any:

11. Hours in Reporting Period 12.

No. of Hrs. Reactor Was Critical

13. Reactor Reserve Shutdown Hours 14.

Hours Generator on Line 15.-Unit Reserve Shutdown Hours 16.

Gross Therm.

Energy Gen.

(MWH) 17.

Gross Elect.

Energy Gen.

(MWH) 18.

Net Elect.

Energy Gen.

(MWH)

19. Unit Service Factor
20. Unit Availability Factor
21. Unit Capacity Factor (MDC Net)
22. Unit Capacity Factor (DER Net)
23. Unit Forced Outage Rate 24.

Shutdowns Scheduled over Next Six None This Mo.

Yr. to Date 744.0 8784.0 744.0 7687".6 0.0 0.0 744.0 7641.9 0.0 0.

0'535082 25543803 840230 8298030 813357 8022603 100.0 87.0 100.0 87.0 103.1 86.2 100.3 83.8 0.0 0.1 Months (Type, Date,and Cumm.

166560.0 116011.9 0.0 112447.6 0.0 347178267 112504390 108382566 68.5 68.5 62.2 60.6

14. 2 Duration):
25. If Shut Down At End of Report Period, Estimated Date of Startup:
26. Units in Test Status (Prior to Commercial Operation):

Forecast Achieved INITIALCRITICALITY INITIALELECTRICITY COMMERCIAL OPERATION

I

AVERAGE DAILY POWER LEVEL (MWe-Net)

MONTH DOCKET NO.

50-316 UNiT TWO DA'E 03/Jan/97 COMPLETED BYJohn W. Minor TELEPHONE 616-465-5901 DEC/96 DAY 96/12/01 96/12/02 96/12/03 96/12/04 96/12/05 96/12/06 96/12/07 96/12/08 96/12/09 96/12/10 96/12/11 96/12/12 96/12/13 96/12/14 96/12/15 96/12/ j 6 AVERAGE DAILY POWER LEVEL 1092 1094 1086 1095 1094 1098 1093 1094 1093 1093 1091 1090 1092 1091 1092 1092 DAY 96/12/17 96/12/18 96/12/19 96/12/20 96/12/21 96/12/22 96/12/23 96/12/24 96/12/25 96/12/26 96/12/27 96/12/28 96/12/29 96/12/30 96/12/31 AVERAGE DAILY POWER LEVEL 1091 1093 1095 1096 1096 1095 1098 1097 1097 1097 1093 1080 1095 1096 109~

DOCKET NO:

50-316 UNIT NAME:

D.C.

Cook Unit 2 COMPLETED BY:

M.E. Russo TELEPHONE:

616-697-5100 DATE:

January 3,

1997 PAGE:

Page 1 of 1

MONTHLY OPERATING ACTIVITIES DECEMBER 1996 HIGHLIGHTS The unit entered this reporting period in Mode 1 at 100%

RTP.

The unit exited this reporting period in Mode 1 at 100%

RTP.

There were no challenges to the pressurizer safety valves or power operated relief valves.

Gross electrical generation for the month of December was 840230 MWH.

DETAILS No details to report.

UNIT SHUTDOWNS AND POWER REDUCTIONS REPORT MONTH:

DECEMBER 1996 DOCKET NO:

UNIT NAME:

DATE:

COMPLETED BY:

TELEPHONE:

PAGE:

50-316 D.C.

COOK UNIT'2 January 3,

1997 M.E. Russo 616-697-5100 Page 1 OF 1

DURATION NO.

DATE TYPE HOURS METHOD OF SHUTTING LICENSEE DOWN EVENT SYSTEM COMPONENT CAUSE AND CORRECTIVE ACTION REASON REACTOR REPORT NO.

CODE CODE TO PREVENT'RECURRENCE None There were no unit shutdowns or significant power reductions from 100%

RTP this month.

1 2

F:

Forced Reason:

S:

Scheduled A:

Equipment Failure (Explain)

B:

Maintenance or Test C:

Refueling D:

Regulatory Restriction E:

Operator Training and License Examination F:

Administrative G:

Operational Error (Explain)

H:

Other (Explain) 3 Method:

1:

Manual 2:

Manual Scram 3:

Automatic Scram 4:

Other (Explain) 4Exhibit G Instructions for preparation of data entry sheets for Licensee Event Report (LER) File (NUREG 0161) 5Exhibit I:

Same Source