Monthly Operating Rept for Jan 1995 for DCP Unit 2
ML17332A566
Person / Time
Site: Cook American Electric Power icon.png
Issue date: 01/31/1995
From: Bublick D, Janisse J
INDIANA MICHIGAN POWER CO. (FORMERLY INDIANA & MICHIG
To:
Shared Package
ML17332A564 List:
References
NUDOCS 9502150092
Download: ML17332A566 (4)


Text

N.R.C.

OPERATING DATA REPORT DOCKET NO.

50-316 DATE 07/Feb/95 COMPLETED BY JD Janisse TELEPHONE 616-465-5901 OPERATING STATUS

1. Unit Name D.

C.

Cook Unit 2

2. Reporting Period Jan 1995 notes
3. Licensed Thermal Power (MWt) 3411 4.

Name Plate Rating (Gross MWe) 1133

5. Design Electrical Rating (Net MWe) 1090 6.

Maximum Dependable Capacity (GROSS MWe) 1100 7.

Maximum Dependable Capacity (Net MWe) 1060

8. If Changes Occur in Capacity Ratings (Items no.

3 through

7) Since Last Report Give Reasons 9.

Power Level To Which Restricted. If Any (Net MWe) 10.

Reasons For Restrictions. If Any:

11. Hours in Reporting Period 12.

No. of Hrs. Reactor Was Critical

13. Reactor Reserve Shutdown Hours
14. Hours Generator on Line
15. Unit Reserve Shutdown Hours
16. Gross Therm. Energy Gen.

(MWH)

17. Gross Elect.

Energy Gen.

(MWH)

18. Net Elect.

Energy Gen.

(MWH)

19. Unit Service Factor
20. Unit Availability Factor
21. Unit Capacity Factor (MDC Net)
22. Unit Capacity Factor (DER Net)
23. Unit Forced Outage Rate 24.

Shutdowns Scheduled over Next Six None This Mo.

Yr.

744.0 744.0 0.0 744.0 0.0 2533412 833510 807133 100.0 100.0 102.3 99.5 0.0 Months (Type, to Date 744.0 744.0 0.0 744.0 0.0 2533412 833510 807133 100.0 100.0 102.3 99.5 0.0 Date,and Cumm.

149760.0 100760.5 0.0 97279.1 0.0 296631594 96140500 92564568 66.0 66.0 59.1 57.6 15.7 Duration):

25'f Shut Down At End of Report Period, Estimated Date of Startup:

26. Units in Test Status (Prior to Commercial Operation):

Forecast Achieved INITIALCRITICALITY INITIALELECTRICITY COMMERCIAL OPERATION 9502150092 950207 PDR ADQCK 05000316 R

PDR

)

AVERAGE DAILY POWER LEVEL (MWe-Net)

MONTH DOCKET NO.

50-316 UNIT TWO DATE 07/Feb/95 COMPLETED BY JD Janisse TELEPHONE 616-465-5901 Jan 1995 DAY 95/01/01 95/01/02 95/01/03 95/01/04 95/01/05 95/01/06 95/01/07 95/01/08 95/01/09 95/01/10 95/01/11 95/01/12 95/01/13 95/01/14 95/01/15 95/01/16 AVERAGE DAILY POWER LEVEL 1083 1085 1082 1079 1090 1086 1086 1089 1081 1083 1089 1089 1080 1083 1088 1084 DAY 95/01/17 95/01/18 95/01/19 95/01/20 95/01/21 95/01/22 95/01/23 95/01/24 95/01/25 95/01/26 95/01/27 95/01/28 95/01/29 95/01/30 95/01/31 AVERAGE DAILY POWER LEVEL 1084 1084 1081 1085 1081 1090 1089 1083 1087 1085 1083 1086 1084 1086 1087

DOCKET O.:

UNIT NAME'OMPLETED BY'ELEPHONE'ATE:

PAGE'0-316 D.C. Cook Unit 2 D. L. Bublick (616) 465-5901 Feb 2, 1995 Page 1 of 1

MONTHLY OPERATING ACTIVITIES JANUARY 1995 HIGHLIGHTS The unit entered this reporting period in Mode 1 at 100% RTP.

The unit exited this reporting period in Mode 1 at 100% RTP.

There were no challenges to the pressurizer safety valves or power operated relief valves.

Gross Electrical generation for the month of January was 833510 MWH.

DETAILS No details to report.

UNIT SHUTDOWNS AND POWER REDUCTIONS REPORT MONTH: JANUARY 1995 UNIT NAME:

DATE:

COMPLETED BY:

TELEPHONE:

PAGE:

D.

C.

COOK UNIT, 2 Feb 2, 1995 DE L. Bublick (616) 465-5901 Page 1'of 1 NO.

DATE TYPE'URATION HOURS METHOD OF SHUTTING DOWN REASON~

REACTOR~

LICENSEE EVENT REPORT NO.

SYSTEM CODE4 COMPONENT CODEs CAUSE AND CORRECTIVE ACTION TO PREVENT RECURRENCE None There were no unit shutdowns or significant power reductions fro 100%

RTP this month.

1 F

S:

Forced Scheduled 2

Reason:

A:

Equipment Failure (Explain)

B:

Maintenance or Test C:

Refueling D:

Regulatory Restriction E:

Operator Training and License Examination F:

Administrative G:

Operational Error (Explain)

H:

Other (Explain) 3 Method:

1:

Manual 2:

Manual Scram 3:

Automatic Scram 4:

Other (Explain) 4Exhibit G - Instructions for preparation of data entry sheets for Licensee Event Report (LER) File (NUREG 1061) 5Exhibit I: