Monthly Operating Rept for Jan 1995 for DCP Unit 2
ML17332A566
Person / Time
Site: Cook American Electric Power icon.png
Issue date: 01/31/1995
From: Bublick D, Janisse J
INDIANA MICHIGAN POWER CO. (FORMERLY INDIANA & MICHIG
To:
Shared Package
ML17332A564 List:
References
NUDOCS 9502150092
Download: ML17332A566 (4)


Text

N.R.C. OPERATING DATA REPORT DOCKET NO. 50-316 DATE 07/Feb/95 COMPLETED BY JD Janisse TELEPHONE 616-465-5901 OPERATING STATUS

1. Unit Name D. C. Cook Unit 2
2. Reporting Period Jan 1995 notes
3. Licensed Thermal Power (MWt) 3411
4. Name Plate Rating (Gross MWe) 1133
5. Design Electrical Rating (Net MWe) 1090
6. Maximum Dependable Capacity (GROSS MWe) 1100
7. Maximum Dependable Capacity (Net MWe) 1060
8. If Changes Occur in Capacity Ratings (Items no. 3 through Last Report Give Reasons
7) Since
9. Power Level To Which Restricted. If Any (Net MWe)
10. Reasons For Restrictions. If Any:

This Mo. Yr. to Date Cumm.

11. Hours in Reporting Period 744.0 744.0 149760.0
12. No. of Hrs. Reactor Was Critical 744.0 744.0 100760.5
13. Reactor Reserve Shutdown Hours 0.0 0.0 0.0
14. Hours Generator on Line 744.0 744.0 97279.1
15. Unit Reserve Shutdown Hours 0.0 0.0 0.0
16. Gross Therm. Energy Gen. (MWH) 2533412 2533412 296631594
17. Gross Elect. Energy Gen. (MWH) 833510 833510 96140500
18. Net Elect. Energy Gen. (MWH) 807133 807133 92564568
19. Unit Service Factor 100.0 100.0 66.0
20. Unit Availability Factor 100.0 100.0 66.0
21. Unit Capacity Factor (MDC Net) 102.3 102.3 59.1
22. Unit Capacity Factor (DER Net) 99.5 99.5 57.6
23. Unit Forced Outage Rate 0.0 0.0 15.7
24. Shutdowns Scheduled over Next Six Months (Type, Date,and Duration):

25 'f None Shut Down At End of Report Period, Estimated Date of Startup:

26. Units in Test Status (Prior to Commercial Operation):

Forecast Achieved INITIAL CRITICALITY INITIAL ELECTRICITY COMMERCIAL OPERATION 9502150092 950207 PDR ADQCK 05000316 R PDR )

AVERAGE DAILY POWER LEVEL (MWe-Net)

DOCKET NO. 50-316 UNIT TWO DATE 07/Feb/95 COMPLETED BY JD Janisse TELEPHONE 616-465-5901 MONTH Jan 1995 AVERAGE DAILY AVERAGE DAILY DAY POWER LEVEL DAY POWER LEVEL 95/01/01 1083 95/01/17 1084 95/01/02 1085 95/01/18 1084 95/01/03 1082 95/01/19 1081 95/01/04 1079 95/01/20 1085 95/01/05 1090 95/01/21 1081 95/01/06 1086 95/01/22 1090 95/01/07 1086 95/01/23 1089 95/01/08 1089 95/01/24 1083 95/01/09 1081 95/01/25 1087 95/01/10 1083 95/01/26 1085 95/01/11 1089 95/01/27 1083 95/01/12 1089 95/01/28 1086 95/01/13 1080 95/01/29 1084 95/01/14 1083 95/01/30 1086 95/01/15 1088 95/01/31 1087 95/01/16 1084

DOCKET O.:

UNIT D.C. Cook Unit 2 PAGE'0-316 NAME'OMPLETED BY'ELEPHONE'ATE:

D. L. Bublick (616) 465-5901 Feb 2, 1995 Page 1 of 1 MONTHLY OPERATING ACTIVITIES JANUARY 1995 HIGHLIGHTS The unit entered this reporting period in Mode 1 at 100% RTP.

The unit exited this reporting period in Mode 1 at 100% RTP.

There were no challenges to the pressurizer safety valves or power operated relief valves.

Gross Electrical generation for the month of January was 833510 MWH.

DETAILS No details to report.

UNIT SHUTDOWNS AND POWER REDUCTIONS UNIT NAME: D. C. COOK UNIT, 2 DATE: Feb 2, 1995 REPORT MONTH: JANUARY 1995 COMPLETED BY: DE L. Bublick TELEPHONE: (616) 465-5901 PAGE: Page 1'of 1 METHOD OF SHUTTING LICENSEE TYPE'URATION DOWN EVENT SYSTEM COMPONENT CAUSE AND CORRECTIVE ACTION NO. DATE HOURS REASON~ REACTOR~ REPORT NO. CODE4 CODEs TO PREVENT RECURRENCE None There were no unit shutdowns or significant power reductions fro 100% RTP this month.

1 2 3 4 5 F Forced Reason: Method: Exhibit G - Instructions Exhibit I: same S: Scheduled A: Equipment Failure (Explain) 1: Manual for preparation of data Source B: Maintenance or Test 2: Manual Scram entry sheets for Licensee C: Refueling 3: Automatic Scram Event Report (LER) File D: Regulatory Restriction 4: Other (Explain) (NUREG 1061)

E: Operator Training and License Examination F: Administrative G: Operational Error (Explain)

H: Other (Explain)