Forwards Insp Repts 50-315/93-25 & 50-316/93-25 on 940124-28.No Violations Noted.Operating Portion of Requalification Exam Administration on Facility Control Room Simulator Not Observed
ML17331B229
Person / Time
Site: Cook  
Issue date: 02/18/1994
From: Ring M
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
To: Fitzpatrick E
ILLINOIS POWER CO.
Shared Package
ML17331B230 List:
References
NUDOCS 9402240036
Download: ML17331B229 (6)


See also: IR 05000315/1993025

Text

FORD I

REGULATORY INFORMATION DISTRIBUTION SYSTEM (RIDS)

~

~

~

ACCESSION NBR:9402240036

DOC.DATE: 94/02/18

NOTARIZED: NO

DOCKET I

FACIL:50-315 Donald C.

Cook Nuclear

Power Plant, Unit 1, Indiana

M

05000315

50-316 Donald C.

Cook Nuclear

Power Plant, Unit 2, Indiana

M

05000316

AUTH.NAME

.

AUTHOR AFFILIATION

RING,M.A.

Region

3 (Post

820201)

RECIP.NAME

RECIPIENT AFFILIATION

FITZPATRICK,E.

Illinois Power

Co.

SUBJECT:

Forwards insp repts

50-315/93-25

a 50-316/93-25

on

940124-28.No violations noted. Operating portion of

requalification

exam administration

on facility control

room simulator not observed.

DISTRIBUTION CODE:

IE42D

COPIES

RECEIVED:LTR /

ENCL /

SIZE: 8+'

TITLE: Operator Licensing Examination Reports

NOTES:

RECIPIENT

'OPIES'D

CODE/NAME

LTTR ENCL

PD3-1

PD

1

1

INTERNAL: N~

H HHFBPT

1

0

R

FILE

02

1

1

RECIPIENT

ID CODE/NAME

HICKMANIJ

NRR/DRCH/HOLB10

RGN3

FILE

01

COPIES

LTTR ENCL .

1

1

1

1

1

1

EXTERNAL: NRC

PDR

1

1-

NSIC

NOTE TO ALL RIDS" RECIPIENTS:

PLEASE HELP US TO REDUCE WASTE! CONTACT THE DOCUMENT CONTROL DESK.

ROOM P 1-37 (EXT. 504-2065) TO ELIMINATEYOUR NAh<E FROM DISTRIBUTION

LISTS FOR DOCUMENTS YOU DON'T NEED!

TOTAL NUMBER OF COPIES

REQUIRED:

LTTR

8

ENCL

7

February 18,

1994

Docket

No. 50-315

Docket

No. 50-316

Indiana Michigan Power

Company

ATTN:

Hr.

E.

E. Fitzpatrick

Vice President

1 Riverside

Plaza

Columbus,

OH

43216

Dear Hr. Fitzpatrick:

The enclosed

report refers to the inspection

and re-take operating

examinations

conducted

by Hr.

C. Osterholtz

and Hr.

D. Shepard of this office

on January

24

28,

1994.

The inspection

evaluated activities at the

D.

C.

Cook Nuclear

Power Station,

Units

1 and 2, authorized

by

NRC 'Operating

License

Numbers

DPR-58

and

DPR-74.

We discussed

our inspection findings with Mr. K.

Baker

and

members of your staff at the exit interview on January

28,

1994.

I

The purpose of the inspection

was to assess

the licensed

operator

requalification program.

The inspectors

reviewed training administrative

procedures,

representative

records,

r equalification training materials,

and

observed

licensed

operators during'equalification

examination administration.

Additionally, the inspectors

interviewed

members of the operations

and

training staffs.

The operating portion of requalification examination administration

on the

facility's control

room simulator

was not observed

in this inspection.

The

simulator portions of the operating test

(scenarios

and job performance

measures)

are being deferred until additional training

on control

room

upgrades

is complete.

Weaknesses

in your program administrative guidelines notwithstanding,

the.

inspectors

concluded that the licensed operator requalification training

program

was being

implemented

in accordance

with 10 CFR Part 55 requirements.

Re-take

dynamic simulator operating

examinations

were administered

to two

initial operator licensing candidates,

one senior reactor operator instant

and

one senior reactor operator

upgrade.

Both candidates

passed

the examinations.

4

In accordance

with 10 CFR 2.790 of the Commission's

regulations,

a copy of

this letter

and the enclosed

inspection report will be placed in the

NRC

Public Document

Room.

9402240036

9402i8

PDR

ADOCN 05000355

8

PDR

1

4

Indiana Michigan Power

Company

February

18,

1994

We will gladly discuss

any questions

you may have concerning

the inspection or

administered

operating

examinations.

Sincerely,

Enclosures:

l.

Inspection

Reports

No. 50-315/93025(DRS);

No. 50-316/93025(DRS)

2.

Simulation Facility Report

cc w/enclosure:

A. A. Blind, Plant Manager

OC/LFDCB

Resident

Inspector,

RIII

James

R. Padgett,

Michigan Public

Service

Commission

EIS Coordinator,

USEPA

Region

5 Office

Michigan Department of

Public Health

D.

C. Cook,

LPM,

NRR

R. Gallo,

LOLB,

NRR

M.

W. Hodges,

Rl

A. F. Gibson,

RII

S. J. Collins,

RIV

K.

E. Perkins,

RV

B. Boger,

RCHF,

NRR

J.

S. Wermiel,

HFAB,

NRR

bcc:

PUBLIC IE-42

Original Signed By

Mark A. Ring, Chief

Operations

Branch

RIII

RIII

RIII

Osterholtz/lc

Burdick

Kropp

2/

94

2/

/94

2/

/94

~RI I

Ring

2/g/94

Indiana Michigan Power

Company

February 18,

1994

We will gladly discuss

any questions

you may have concerning

the inspection or

administered

operating examinations'incerely,

Enclosures:

1.

Inspection

Reports

No. 50-315/93025(DRS);

No. 50-316/93025(DRS)

2.

Simulation Facility Report

cc w/enclosure:

A. A. Blind, Plant Manager

OC/LFDCB

Resident

Inspector, RIII

James

R. Padgett,

Michigan Public

Service

Commission

EIS Coordinator,

USEPA

Region

5 Office

Michigan Department of

Public Health

D.

C.

Cook,

LPM,

NRR

Original Signed By

Mark A. Ring, Chief

Operations

Branch

cS

R 'I

Os erholtz/lc

2/ISA 4

RlQ

Burdock

2/ l9/94

RIII

Kropp

2/g /94

RIII

Ring

2/

/94