ML17331A293

From kanterella
Jump to navigation Jump to search
Insp Repts 50-315/93-06 & 50-316/93-06 on 930322-0401.No Violations Noted.Major Areas Inspected:Implementation of Licensee Response to GL 89-10, Safety-Related MOV Testing & Surveillance
ML17331A293
Person / Time
Site: Cook  
Issue date: 04/23/1993
From: Huber M, Jeffrey Jacobson, Replogle G, James Smith
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
To:
Shared Package
ML17331A292 List:
References
50-315-93-06, 50-315-93-6, 50-316-93-06, 50-316-93-6, GL-89-10, NUDOCS 9304300076
Download: ML17331A293 (12)


See also: IR 05000315/1993006

Text

U. S.

NUCLEAR REGULATORY COI1!'IISSION

REGION III

Reports

No. 50-315/93006(ORS);

No.

50-316/93006(ORS)

Docket I<os.:

50-315;

50-316

Licenses

No.

DPR-58;

No.

OPR-74

Licensee:

Indiana tiichigan Power. Company

1 Riverside

Plaza

Columbus,

OH

43216

Facility, Name:

Donald

C.

Cook Nuclear

Power Plant - Units

1

and

2

Inspection At:

Bridgman,

HI

Inspection

Conducted:

t1arch

22 through April 1,

1993

Inspectors:

gy..S. gy~ ave

H..

Huber

X.'/Mrr,

G.

O.

Rep

og

e

ete

Date

mit

>2i7

Date

Observer:

O.

E.

Roth

Approved

By:

75@. v/~ ."'a<

. h.

acobson,

ie

t1aterials

& Processes

Section

ate

Ins ection

Summary

Ins ection conducted

Harch

22 throu

h April 1.

1993

Re orts

No.

50-315

93006

DRS

No. 50-316

93006

ORS

Areas

Ins ected:

Announced safety inspection of the implementation of the

licensee's

response

to Generic Letter (GL) 89-10,

"Safety-Related

l1otor-

Operated

Valve

(t10V) Testing

and Surveillance"

(2515/109).

Results:

The licensee

developed

and

implemented

a program which was

progressing

in accordance

with the guidance of GL 89-10.

The inspection

disclosed

two unresolved

items

(Sections

2.2.2

and 2.3)

and

t.wo inspection

followup items

(Sections

2.3

and 2.8. 1).

9304300076

930423'DR

"ADOCK 05000315

Q

PDR

TABLE OF

COf<TENTS

Pacae

1.0

2.0

3.0

4.0

5.0

6.0

Persons

Contacted..

Inspection of the Implementation of the Program

Developed

Response

to Generic Letter 89-10.

2.1

Selected

HOVs.

2.2

Design Basis

Reviews

2.2. 1

Differential Pressure

and Flow Requirements..

2.2.2

Degraded

Voltage Calculations

2.3

HOV Switch Settings

2.4

Design Basis Capability.

2 .4 . 1

Review of OATIS Diagnostic Traces'.

2.5

Periodic Verification of IIOV Capability.

2.6

HOV Failures,

Corrective Actions and Trending

2.7

Schedule

2.8

Associated

Reviews

2.8.

1

Haintenance

2.8.2

Diagnostics

2.8.3

'ilalkdown..

2..8.4

Pressure

Locking and Thermal

Binding.

Licensee

Self-Assessment

Unresolved

Items.

inspection

Follow-up Items

Exit Heeting,.

1

ln

2

2

2

2

2

'

3

4

5

5

5

6

6

6

7

7

7

DETAILS

Persons

Contacted

American Electric Power Service

Com an

AEP

D

S

J

J

.S

R

W

J

M

L

A

J

R

T

tl

P

R

M

G

C

F. Powell, Assistant

Section

Manager,

Nuclear Engineering

J.

Brewer,

Group Manager,

Nuclear Safety Licensing Coordinator

B. Kingseed,

Manager,

Nuclear Safety

A. Kobyra, Manager,

Nuclear'Design

and Electrical

Systems

P.

Hodge,

Manager,

Mechanical

Systems

L. Simms,

Manager,

Nuclear Assessment

G. Smith, Jr., Chief Nuclear Engineer

R. Anderson, Assistant

Manager,

Power Systems

and

Human Factors

J. Finissi, Electrical

Engineer

DeMarco, Electrical

Engineer

J.

Lewandowski,

Mechanical

Engineer

G. Nogrady,

Mechanical

Engineer

A. Kadlec,

Mechanical

Engineer'.

Georgantis,

Licensing Engineer

A. Vilken, Nuclear Safety

M. McCarty, Site ljuality Assurance

H. Hevener,

equality Assurance

Engineer

T. Buetlemann,

equality Assurance

Engineer

P. Roulett,

Nuclear Safety

J.

Dudiak, Electrical Training

'ndiana

Michi an

Power

Com an

IM

A. A. Blind; Plant Manager

K.

R. Baker, Assistant

Plant Manager.

Production

J.

E.- Ruteov(ski, Assistant

Plant Manager,

Technical

Support

J.

Hiebe,

Safety

8 Assessment

Superintendent

G.

A.

1 cher,

Plant Engineering

Superintendent

A.

Godet,

MOV Coordinator

R. i(est,

Licensing Coordinator,

Safety

and Assessment

P.

Helms,

Engineering Supervisor,

Plant Engineering

Additional plant

and corporate

personnel

were contacted

during

inspection.

S.

fnuclear

Re ul ator

Commission

NRC

tne

A. Isom, Senior Resident

Inspector

The persons listed above attended

the exit meeting

on April I, !993.

2.0

Ins ection of the

Im lementation of the

Pro

ram Develo

ed in

Res

onse

to Generic Letter 89-10'.1

Selected

MOVs

The licensee

had

252

HOVs in the

GL 89-10 program

and differential pressure

(dp) testing

was planned for 153

HOVs.

The inspectors

selected

the

HOVs

listed in Enclosure

2 For

a detailed

review to verify the adequacy

of the

program established

in response

to GL 89-10.

The

HOYs were selected

on the

basis of safety significance,

previous test'results,

and to examine

a cross-

section of the

MOV population.

The details of the review are discussed

in the

remainder of the report.

2..2

Desi

n Basis

Reviews

2.2.1

Differential Pressure

and

Flow Reouirements

The inspectors

reviewed the licensee's

design basis

maximum expected

differential pressure

(HEDP) calculations

and

no significant anomalies

were

disclosed.

The

FSAR, technical

specifications,

normal,

abnormal

and emergency

operating

procedures,

and other plant documents

were reviewed to determine

the

worst case

design

basis conditions for each

HOV.

The most challenging

conditions

and resulting

system condition calculations

were used in the switch

setting cal'culations.

2.2.2

De raded Volta e Calculations

Degraded

voltage calculations

performed

by the licensee

were not done using

the methodology described

in GL 89-10

and its supplements.

The calculations

did not

assume

the worst, case grid voltage

as the starting point for

evaluating

the available voltage at

HOV motors.

The worst case grid voltage

was considered

by the

NRC to be 0.896 per unit (pu) (just above the

4kV

degraded

voltage relay setpoint

minimum value).

Instead,

the license=

used

the minimum expected grid voltage

(0.938 pu)

eased

on

a study of the previous

grid history.

The licensee

considered

this minimum expected

value,

not the

minimum degraded

voltage relay setpoint,

as

the licensing basis.

In response

to the inspectors'oncerns,

the licensee

performed

HOV capability

calculations

for several

marginal

MOVs .using

.896

pu as

the starting point.

No immediate

HOV operability concerns

were noted

as

a result of the reduced

electrical

system capacity.

However, further

NRC review is required to

determine

the applicability of the licensee's

grid history study to

HOV

capability determinations.

Therefore,

this issue

is considered

an unresolved

item pending further review by the

NRC (50-315/93006-01(DRS);

50-316/93006-

01(DRS)).

The degraded

voltage calculations

did not include margins to account for the

high ambient

temperature

effects

on motor performance.

However, Limitorque

was evaluating

the issue

and

was expected

to provide the

industry.y with

information concerning this matter.

The licensee

planned to incorporate

the

information from Limitorque into the

GL 89-10 program

when it becomes

available.

2.3

MOV Switch Settin

s

The inspectors

reviewed

the licensee's

calculations

and the

MOV switch setting

methodology for the selected

HOVs.

Independent

calculations

were performed

by

the inspectors

for each

HOV in the

sample population to confirm the licensee's

results.

Concerns identified are discussed

below.

The licensee did not justify assumptions

for valve factors,

stem friction

factors

and load sensitive

behavior in the calculations for torque switch

settings.

Additionally, the licensee

did not account for MOV degradation

that

may occur over the maintenance

and refurbishment intervals.

- The

stem

lubrication interval

For most

HOVs was three refueling outages

(approximately

54 months),

which was considered

excessively

long.

The Limitorque recommended

lubrication interval

was

18 months.

The inspectors

evaluated

VOTES static

test data for valve 1-ICM-305 and

found the actual

degradation

oF the

MOV to

be significant (the tests

were performed just prior to and just after

maintenance).

The calculated

stem friction coefficient prior to maintenance

was 0.30 while the factor just after maintenance

was 0. 13.

The analysis

demonstrated

that

MOV degradation

can occur

and

can

be significant.

Furthermore,

the limitations in the

OATIS diagnostic

equipment

used during

testing inhibited the ability to quantify the assumptions.

The licensee

purchased

the

VOTES diagnostic

equipment

which will allow assumptions

to be

evaluated

anc quantified.

The licensee

planned

to appropriately evaluate

future test cata

and justify the assumptions

for valve factors,

stem friction

factors,

loac sensitive

behavior

and

MOV degradation

used

in the switch

setting calculations.

This issue is considered

an inspection

follow-up item

pending furt: er review of the licensee's

justification (50-315/93006-02("RS);

50-316/93006-32(ORS)).

Some thrust windows were calculated

to be negative after. the application of

the

OATIS in-."curacies.

That is, the minimum required thrust

exceeded

the

maximum perm ssible thrust.

Torque switches

on

some

HOVs were set at

a point

that

may

be c: eater

than the motor capability under design basis conditio..s.

As

a result,

he subject

HOV motors could stall while closing, without

tripping the -.orque switches.

The licenseestarted

an evaluation for each

affected

MOV -.o determine

the potential

consequences.

This issue

is

considered

ar. unresolved

item pending further

NRC review oF the licensee's

evaluation

(:0-315/93006-03(DRS);

50-316/93006-03(ORS)).

Valve struct: al limits were not included

in the weak-link. analysis

performed

for all safe

-related

HOVs.

However,

the licensee

identified this

defi".ienc'rior

to the inspection

and planned

to obtain the appropriate

informatio.. fro;.,

the valve marufacturers.

This issue will be reviewed during

a future

inspection.

2.4

-=si

n Basis

Ca abilit

The inspecto.s

reviewed completed static

and dp testing

packages

to veri=; the

methodology

sed to demonstrate

HOV capability.

Fifty-two dp tests

were

complete

at :he

time of the inspection

and approximately

100 additional ;ests

were scheduled

to be performed prior to June

1994.

The licensee

had completed

more

dp tests

than most other licensees

in Region III.

The inspectors

considered

the progress

of the dp testing

program to be

a strength.

2.4.1

Review of OATIS Dia nostic Traces

Anomalies observed

during diagnostic'testing

were'ot

always comprehe'nsively

evaluated.

For example,

OATIS diagnostic

traces

for HOVs I/2-HCH-221 and

231

(auxiliary feed turbine isolation globe valves with flow under the seat)

indicated that

an unexpected pull-out force

was required

in the opening

direction

and the thrust requirements

for closing were

much less

than

expected.

These irregularities could indicate lower than expected

dp across

the valves in the closing direction,

reverse installation,

or valve

degradation.

The lack'f an evaluation for these particular

HOV test results

"

was not safety significant because

the valves did not have

a safety function

to reposition against

dp.

However,'he

licensee

was not aware of this fact at

the time the traces

were evaluated

and indicated that other diagnostic traces,

involving other

HOVs, were evaluated

in

a similar manner.

The inspectors

were also concerned

with the accuracy of data

taken during dp

tests.

The dp test data

and subsequent

analysis of the data

must

be accurate

and comprehensive

to allow for comparison of data

and to justify assumptions

that

may

be applied to valves that cannot

be dp tested.

The inspectors

cau-

tioned the licensee

to thoroughly evaluate

data

and anomalies

observed

during

testing.

The licensee's

evaluation of the traces

was considered

a weakness.

Dynamic testing results

at less

than design

basis conditions

were evaluated

using

a one point extrapolation

method.

The licensee

did not provide multi-

point testing or other justificati,on for using the one point extrapolation.

'The program specified that the technique

was sufficient for valve closure

when

at least

80% of the

HEDP was achieved for some

HOVs

(HEDP greater

than or

equal

to 500 psid)

and

50% of the

HEDP was achieved for other

HOVs

(HEDP less

than

500 psid).

The

NRC inspectors

considered

the approach

to be acceptable

for the first stage of the two-stage

approach

outlined in

GL 89-10.

Extrapolating test results

to the design-basis

HEDP may require further

qualification..

This issue will be reviewed during

a future inspection.

2.5

Periodic Verification of HOV Ca abilit

The licensee

planned

to use static di.agnostic testing

to periodically verify

HOV capability,

however static testing

may not

be adequate

to model

HOV

behavior

under dynamic conditions.

The plans

met the

CL 89-!0 guidance with

respect

to frequency,

but the licensee

needs

to justify the method

used

to

provide assurance

that

an

HOV would. work properly when called upon.

This

issue will be reviewed during

a future inspection.

2.6

HOV Failures

Corrective Actions

and Trendin

The inspectors

reviewed

problem reports

associated

with recent

HOV failures.

Evaluation of HOY failures

and corrective actions

appeared

effective.

The

trending

program

was still evolving.

Only failures were trended,

but

a

program

was under development

that would trend performance

parameters,

with

the intent of being more predictive.

2.7

Schedule

The licensee

planned to meet the

recommended

schedule

in

GL 89-10

and testing

was being accomplished

as prescribed

by the Program.

However,

the

number of

tests

that remained indicate that it may be difficult to complete

the planned

dp testing within the schedule.

Additionally, since

the licensee

was

transitioning

from the

use of OATIS diagnostic

equipment

to the more

comprehensive

VOTES system,

they may decide that

some

IIOVs should

be retested

in order to obtain more useful data.

The inspectors notified the licensee

that results of the planned testing

needed

to be evaluated

and incorporated

into the program,

as necessary,

prior to program completion.

If a testing

schedule

extension

becomes

necessary,

the

NRC should

be notified as

soon

as

possible.

2.8

Associated

Reviews

2.8.1

I1aintenance

Oiagnostic testing

was not performed after packing adjustments

as

long

as

the

packing gland nut torque

was not adjusted

beyond

a predetermined

value.

However,

the licensee

did not demonstrate

that the torque limitation method

was

used

since plant startup

and sufficient testing

was not performed -to

determine

the actual

packing loads for each

HOV.

An incorrect

assumption

for

packing

loads could cause

other factors

(such

as valve factor) to

be

incorrectly calculated

and excessive

packing loads could challenge

HOV

operability.

The licensee

based its position

on

a study performed

by Chesterton

Packing

Company.

The study

showed that if the original packing gland nut torque

was

not exceeded

the packing

load would not change significantly.

However,

the

test data

was limited in that testing

was only performed

on one

f10V and

neglected

the effects of various foreign materials

(such

as boric acid

crystals

that

may

be present

at the stem/packing

interface)

or packing

damage

(that

may occur

as

a result of

a packing leak).

As

a result of the

GL 89-10

Part

I inspection,

the licensee

planned to perform testing

on

a sample of tlOVs

to justify the assumptions

concerning

packing loads.

However,

adequate

measurement

techniques

were unavailable until recently

when the licensee

acquired

VOTES diagnostic

equipment.

This is considered

an inspection

follow-

up item pending

a review of the licensee's justification (50-315/93006-

04(ORS):

50-316/93006-04(DRS)).

Stem lubrication was required to be checked

(not replaced)

every three

refueling outages

for most

IIOVs and every refueling outage for IIOVs in harsh

environments.

The licensee

had not included

a term for degradation

in the

switch setting calculations

and the

3 refueling outage

interval

was excessive

when compared

to the

18 month interval

recommended

by Limitorque.

Furthermore,

since

the procedure

only required

checking

(not replacing)

the

lubrication,

the actual lubrication interval for individual

HOYs could

be

as

long as six or more refueling outages.

The licensee

planned

to implement

changes

to require replacing lubrication every three

outages

and to =-valuate

degradation

as discussed

in Paragraph

2.3.

2.8.2

The accuracy

recommendations

provided

by the

OATIS diagnostic

equipment

manufacturer

(ABB Impell) were based solely on test data

from the

f10V Users

Group

(HUG) validation testing

program.

The data

from the

HUG validation

testing

was very limited and

may not 'be comparable

to the results

that might

be observed

at the O.C.

Cook plant.

Additionally, another diagnostic

equipment manufacturer,

with an almost identical

system,

perFormed

independent

testing

and reported

inaccuracy

values significantly greater

than the'BB

Impell recommendations.

This issue will be addressed

in

a future Supplement

to

GL 89-10.

The licensee will be expected

to justify the diagnostic

equipment

accuracy

assumptions

in response

to the Generic Letter Supplement.

The review of the OATIS equipment

accuracy

was identified as

an unresolved

item '(50-315/91009-01(DRS);

50-316/91009-01(ORS))

during the Part

1 inspection

and will remain

open.

2.8.3

1!alkdown

The inspectors

performed

a general

inspection of the plant

as well as

a

detailed

inspection of several

HOVs.

In general,

housekeeping

was reasonable

in most areas.

However, four HOVs were leaking oil from the actuators.

The

licensee

agreed

to evaluate

the leaks

and take appropriate corrective actions.

2.8.4

Pressure

Lockina and Thermal

Bindin

The licensee's

actions

in the areas

of pressure

locking and thermal binding

were considered

acceptable.

The early recognition

and response

to pressure

locking was considered

a strength.

".round

1975 (prior the publication of SOER 84-07),

the licensee

recognized

the

pressure

locking/thermal binding problem

and

began modifying applicable

gate

alves

by means

such

as equalizing lines.

As subsequent

information about

pressure

locking and thermal

binding became available,

additional corrective

actions

were implemented

to resolve

these

problems.

These actions

included

both equipment modification and procedure

revisions.

About 30 gate valves

were modifiec.

The inspectors

reviewed

the normally closed

valves

in the

systems

where

these

proble...s

were observed

in other plants.

The licensee

took steps

to preclude

=-ither pressure

locking or thermal

binding in all valves subject

to those

": obl e.-:s.

"..0

Licensee

Self-Assessment

The licensee

performed surveillances

and audits of the

GL 89-10

HOV program.

The efforts in this area

were considered

to be acceptable.

The audit compared

the

t<OV program to the recommendations

of GL 89-10

and to results of other

HOV

inspections.

The surveillances

reviewed

aspects

of the program related

to

plant quality control requirements.'

4

0

Unresolved

Items

Unresolved

items are matters

about which more information is required

in order

to ascertain

whether they are acceptable

items,

items of noncompliance,

or

deviations.

Unresolved

items disclosed

during this inspection

are discussed

in Sections

2.2.2

and 2.3 of this report.

5.0

Ins ection Follow-u

Items

Inspection

follow-up items are matters

which have

been discussed

with the

licensee

which will be reviewed further by the inspectors

and which in:olve

some action

on the part of the

NRC or licensee or both.

Two inspection

Follow-up items were identified during this inspection

and are discuss=d

in

Sections

2.3

and 2;8.1.

6.0

Exit Heetin

The inspectors

met with licensee

representatives

(denoted

in Paragrapn

I) at

the conclusion of the. inspection

on April 1,

1993.

The inspectors

su.-..-..arized

the purpose

and

scope of the inspection

and the findings, including t;,e

unresolved

items

and inspection follow-up items identified during thi=

inspection.

The inspectors

also discussed

the likely informational content of

the inspection report with regard to documents

or processes

reviewed

L" the

inspectors

during the inspection.

ENCLOSURE

2

MOV REVIEW LISTING

1-ICM-251

BORON INJECTION TANK (BIT) TRAIN "B" OUTLET CONTAINMENT

ISOLATION VALVE - SHB-0 - 4" gate

1-IMO-262

Sl

PUMPS

RECIRC

TO

RWST TK-33 TRAIN "A" S/0

VALVE SHB-00-

2" globe

1-IMO-263 - SI

PUMPS

RECIRC

TO

RWST TK-33 TRAIN "B" S/0

VALVE - SHB-00-

2" globe

1-IHO-270

SI

PUMPS

DISCHARGE CROSS-TIE

TRAIN "A" S/0

VALVE SMB-00-

gate

1- IMO-316 -

EAST

RHR

8. NORTH SI

TO

RCS

LOOPS

-..'1

8 ;4

COLD

LEGS S/0

VALVE

- SMB-! - 8" gate

2-IHO-2o2

Sl

PUMPS

RECIRC

TO Rl(ST TK-33 TRAIN "A" S/0

VALVE - Sf1B-00-

2" globe

2- IHO-Zo3

SI

PUMPS

RECIRC

TO

RWST TK-33 TRAIN "B" S/0

VALVE - SHB-00-

2

gl obe

2-IMO-256

BIT TRAIN "B" INLET S/0

VALVE - SHB-0 - 4" gate

1-IHO-340 -

EAST

RHR HX TO CENTRIFUGAL CHARGING PUMP

(CCP)

SUCTION S/0

VALVE - SMB-I - 8" gate

I-If10-~}0 -

Rl(ST

TO CVCS

CCPS

SUCTIOl( HEADER TRAIN "A" S/0

VALVE -

Sf1B-

00 - 8" gate

2-IMO-"=11 -

RWST

TO

CVCS

CCPS

SUCTIOl( HEADER TRAIN "B" S/0

VALVE - SHB-

00 - 8'ate