Docket Nos.
50-315/316 April 6, 1990 Mr. Milton Alexich Indiana Michigan Power Company c/o American Electric Power Service Corporation 1 Riverside Plaza
- Columbus, Ohio 43216
Dear Mr. Alexich:
SUBJECT:
UNIMPLEMENTED UNRESOLVED SAFETY ISSUES AT D.C.
COOK On October 19, 1989 the staff issued Generic Letter (GL) 89-21 which requested information concerning the status of implementation of unresolved safety issues (USIs) at your facility.
Based on your response to this GL, dated November 29, 1989 and revised December 7, 1989, our review of Agency records and discussions between your staff and the NRC Project Manager, the NRC staff has compiled the enclosed list representing our assessment of USI implementa-tion.
These results were presented to the Commission at a meeting on February 14, 1990.
The enclosure presents the staff understanding of the current status of all unimplemented USIs for D.C.
Cook.
The staff encourages your effort to complete the unimplemented USIs.
If you have questions or comments about the enclosed information please contact your NRC Project Manager.
Sincerely,
Enclosure:
As stated Original signed by Joseph G. Giitter, Project Manager Project Directorate III-1 Division of Reactor Projects III, IV, V 8 Special Projects Office of Nuclear Reactor Regulation DISTRIBUTION NRC 8 Local PDRs PD31 Reading JZwolinski MRShuttleworth JGiitter OGC EJordan ACRS(10)
JThoma KEccleston PM/PE).;PRSP JGi)64@
04K /90 9004i60fb2 900406 I,
PDR ADOCK 05000315 P
PDC (A)0/PD31:
RSP JThoma 04/6 /90 pl
M g
1 4
II H
L 8
pe RfgI Cq 1
E
+**<<~
Docket Nos.
50-315/316 UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D. C. 20555 April 6, 1990 Mr. Hilton Alexich Indiana Michigan Power Company c/o American Electric Power Service Corporation 1 Riverside Plaza
- Columbus, Ohi o 43216
Dear Mr. Alexich:
SUBJECT:
UNIMPLEMENTED UNRESOLVED SAFETY ISSUES AT D.C.
COOK On October 19, 1989 the staff issued Generic Letter (GL) 89-21 which requested information concerning the status of implementation of unresolved safety issues (USIs) at your facility.
Based on your response to this GL, dated November 29, 1989 and revised December 7, 1989, our review of Agency records and discussions between your staff and the NRC Project Manager, the NRC staff has compiled the enclosed list representing our assessment of USI implementa-tion.
These results were presented to the Commission at a meeting on February 14, 1990.
The enclosure presents the staff understanding of the current status of all unimplemented USIs for D.C.
Cook.
The staff encourages your effort to complete the unimplemented USIs.
If you have questions or comments about the enclosed information please contact your NRC Project Manager.
Sincerely,
'<<P. -,'/. Q tl
(
Joseph G. Giitter, Project Manager Project Directorate III-1 Division of Reactor Projects III, IV, V 8 Special Projects Office of Nuclear Reactor Regulation
Enclosure:
As stated
,1 fair. lli1 ton A 1 ex ich Indiana tlichigan Power Company Donald C.
Cook Nuclear Plant CC:
Regional Administrator, Region III U.S. Nuclear Regulatory Commission 799 Roosevelt Road Glen Ellyn, Illinois 60137 Attorney General Department of Attorney General 525 l(est Ottawa Street Lansing, Michigan 48913 Township Supervisor Lake Township Hall Post Office Box 818 Bridgman, tlichigan 49106 Al Blind, Plant Nanager Donald C.
Cook Nuclear Plant Post Office Box 458 Bridgman, Michigan 49106 U.S. Nuclear Regulatory Commission Resident Inspectors Office 7700 Red Arrow Highway Stevensvi lie, Nichigan 49127 Gerald Charnoff, Esquire Shaw, Pittman, Potts and Trowbridge 2300 N Street, N.N.
Washington, DC 20037 Yiayor, City of Bridgman Post Office Box 366 Bridgman, Michigan 49106 Special Assistant to the Governor Room 1 - State Capitol Lansing, Michigan 48909 Nuclear Facilities and Environmental honitoring Section Office Division of Radiological Health Department of Public Health 3500 N. Logan Street Post Office Box 30035 Lansing, tlichigan 48909 l1r. S.
Brewer American Electric Power Service Corporation 1 Riverside Plaza
- Columbus, Ohio 43216
ENCLOSURE USI A-44 A-46 TITLE Station Blackout Seismic qualification of Equipment in Operating Plants Estimated Implemented Date 6/91 12/93 Remarks Staff reviewing licensee's April 14, 1989 submittal, as supplemented (at the request of NUMARC) on 3/30/90.
Plant walk downs scheduled for 12/92 may be delayed if licensing issues aren't resolved as as scheduled.
A"47 Safety Implementations of TBD Control Systems in LMR Nuclear Power Plants New requirement.
Licensee responded on 3/20/90.
A-48 Hydrogen Control Measure and Effects of Hydrogen Burns on Safety Equipment X2/9Z Licensee is address-ing A-48 issues in conjunction with their IPE program.