MONTHYEAR2CAN012401, U.S. Additional Protocol2024-01-17017 January 2024 U.S. Additional Protocol 2CAN012403, Supplemental Information - Adopt Risk-Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 42024-01-11011 January 2024 Supplemental Information - Adopt Risk-Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4 0CAN012401, Registration of Cask Use2024-01-10010 January 2024 Registration of Cask Use 1CAN122301, Responses to Request for Additional Information for Request for Alternative for Implementation of Extended Reactor Vessel Inservice Inspection Interval (ANO1-ISl-037)2023-12-14014 December 2023 Responses to Request for Additional Information for Request for Alternative for Implementation of Extended Reactor Vessel Inservice Inspection Interval (ANO1-ISl-037) 2CAN112302, Submittal of Amendment 31 to Safety Analysis Report2023-11-16016 November 2023 Submittal of Amendment 31 to Safety Analysis Report 0CAN102303, Registration of Cask Use2023-10-24024 October 2023 Registration of Cask Use 0CAN102302, (ANO) Emergency Plan Revision 49 and Emergency Plan On-Shift Staffing Analysis Revision 32023-10-11011 October 2023 (ANO) Emergency Plan Revision 49 and Emergency Plan On-Shift Staffing Analysis Revision 3 0CAN102301, Evacuation Time Estimate (ETE) Study2023-10-0404 October 2023 Evacuation Time Estimate (ETE) Study 1CAN092301, Supplemental Information - Adopt Risk-Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 42023-09-21021 September 2023 Supplemental Information - Adopt Risk-Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4 0CAN092302, Supplement to Request for Alternative Frequency to Containment Unbonded Post-Tensioning System Inservice Inspection (ANO-CISI-002)2023-09-14014 September 2023 Supplement to Request for Alternative Frequency to Containment Unbonded Post-Tensioning System Inservice Inspection (ANO-CISI-002) 2CAN092301, Reply to a Notice of Violation2023-09-0808 September 2023 Reply to a Notice of Violation 0CAN092301, Emergency Plan Implementing Procedure Revision2023-09-0505 September 2023 Emergency Plan Implementing Procedure Revision 0CAN082301, Units 1 and 2 - Changes to the Quality Assurance Program Approval Form for Radioactive Material Package No. 03412023-08-17017 August 2023 Units 1 and 2 - Changes to the Quality Assurance Program Approval Form for Radioactive Material Package No. 0341 2CAN082301, Inservice Inspection Summary Report for the Arkansas Nuclear One, Unit 2, Twenty-Ninth Refueling Outage (2R29)2023-08-10010 August 2023 Inservice Inspection Summary Report for the Arkansas Nuclear One, Unit 2, Twenty-Ninth Refueling Outage (2R29) 0CAN072301, Registration of Cask Use2023-07-18018 July 2023 Registration of Cask Use 1CAN062304, Supplement Related to License Amendment Request to Remove Technical Specification Condition Allowing Two Reactor Coolant Pump Operation2023-06-29029 June 2023 Supplement Related to License Amendment Request to Remove Technical Specification Condition Allowing Two Reactor Coolant Pump Operation 0CAN062301, Status of Actions to Return to Compliance2023-06-26026 June 2023 Status of Actions to Return to Compliance 0CAN062302, Submittal of Revision 22 of the ANO Fire Hazards Analysis2023-06-20020 June 2023 Submittal of Revision 22 of the ANO Fire Hazards Analysis 1CAN062301, Request for Alternative for Implementation of Extended Reactor Vessel Inservice Inspection Interval (ANO1-ISI-037)2023-06-0808 June 2023 Request for Alternative for Implementation of Extended Reactor Vessel Inservice Inspection Interval (ANO1-ISI-037) 0CAN052303, Annual 10 CFR 50.46 Report for Calendar Year 20222023-05-24024 May 2023 Annual 10 CFR 50.46 Report for Calendar Year 2022 0CAN052302, Emergency Plan Rev. 482023-05-11011 May 2023 Emergency Plan Rev. 48 0CAN052301, Units 1 and 2 - Annual Radiological Environmental Operating Report for 20222023-05-0909 May 2023 Units 1 and 2 - Annual Radiological Environmental Operating Report for 2022 2CAN052301, Cycle 30 Core Operating Limits Report (COLR)2023-05-0303 May 2023 Cycle 30 Core Operating Limits Report (COLR) 0CAN042302, Annual Occupational Radiation Exposure Report for 20222023-04-27027 April 2023 Annual Occupational Radiation Exposure Report for 2022 0CAN042301, Radioactive Effluent Release Report for 20222023-04-14014 April 2023 Radioactive Effluent Release Report for 2022 2CAN042301, License Amendment Request to Revise Technical Specifications to Adopt Risk-Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 42023-04-0505 April 2023 License Amendment Request to Revise Technical Specifications to Adopt Risk-Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4 1CAN032301, License Amendment Request to Modify the Arkansas Nuclear One, Unit 1, Technical Specification 3.3.1, Reactor Protection System Instrumentation, Turbine Trip Function on Low Control Oil Pressure2023-03-30030 March 2023 License Amendment Request to Modify the Arkansas Nuclear One, Unit 1, Technical Specification 3.3.1, Reactor Protection System Instrumentation, Turbine Trip Function on Low Control Oil Pressure 2CAN032303, Responses to Request for Additional Information Concerning the Request for Alternative Regarding the Half-Nozzle Repair of Reactor Vessel Closure Head Penetration 462023-03-29029 March 2023 Responses to Request for Additional Information Concerning the Request for Alternative Regarding the Half-Nozzle Repair of Reactor Vessel Closure Head Penetration 46 2CAN032304, Supplement to the Request for Alternative Regarding the Half-Nozzle Repair of Reactor Vessel Closure Head Penetration 462023-03-29029 March 2023 Supplement to the Request for Alternative Regarding the Half-Nozzle Repair of Reactor Vessel Closure Head Penetration 46 2CAN032305, 03 Post Examination Analysis2023-03-23023 March 2023 03 Post Examination Analysis 1CAN032302, Inspection Summary Report for the Thirtieth Refueling Outage (1R30)2023-03-20020 March 2023 Inspection Summary Report for the Thirtieth Refueling Outage (1R30) 1CAN012301, Responses to Request for Additional Information for Request for Relief ANO1-ISI-0352023-01-30030 January 2023 Responses to Request for Additional Information for Request for Relief ANO1-ISI-035 2CAN012303, U.S. Additional Protocol2023-01-23023 January 2023 U.S. Additional Protocol 2CAN012302, Relief Request ANO2-RR-23-001, Half-Nozzle Repair of Reactor Vessel Closure Head Penetration 462023-01-20020 January 2023 Relief Request ANO2-RR-23-001, Half-Nozzle Repair of Reactor Vessel Closure Head Penetration 46 1CAN122201, License Amendment Request to Revise Technical Specifications to Adopt Risk-Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 42022-12-22022 December 2022 License Amendment Request to Revise Technical Specifications to Adopt Risk-Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4 0CAN122202, Registration of Cask Use2022-12-21021 December 2022 Registration of Cask Use 0CAN122201, Reply to a Notice of Violation; EA-22-0992022-12-0808 December 2022 Reply to a Notice of Violation; EA-22-099 0CAN112201, Request for Alternative Frequency to Containment Unbonded Post-Tensioning System Inservice Inspection (ANO-CISI-002)2022-11-10010 November 2022 Request for Alternative Frequency to Containment Unbonded Post-Tensioning System Inservice Inspection (ANO-CISI-002) 1CAN102202, Application to Remove Technical Specification Condition Allowing Two Reactor Coolant Pump Operation2022-10-31031 October 2022 Application to Remove Technical Specification Condition Allowing Two Reactor Coolant Pump Operation 1CAN102203, Cycle 31 Core Operating Limits Report2022-10-24024 October 2022 Cycle 31 Core Operating Limits Report 1CAN102201, Supplement to Proposed Technical Specifications 3.4.12 and 3.4.13 Revised Dose Calculations2022-10-13013 October 2022 Supplement to Proposed Technical Specifications 3.4.12 and 3.4.13 Revised Dose Calculations 0CAN092201, Supplement to License Amendment Request for Approval of Changes to the Emergency Plan Staffing Requirements2022-09-29029 September 2022 Supplement to License Amendment Request for Approval of Changes to the Emergency Plan Staffing Requirements 1CAN092201, Supplement to Request for Relief from American Society of Mechanical Engineers Section XI Volumetric Examination Requirements - Fifth 10-Year Interval, First Period2022-09-0808 September 2022 Supplement to Request for Relief from American Society of Mechanical Engineers Section XI Volumetric Examination Requirements - Fifth 10-Year Interval, First Period 0CAN082201, License Amendment Request for Approval of Changes to the Emergency Plan Staffing Requirements2022-08-30030 August 2022 License Amendment Request for Approval of Changes to the Emergency Plan Staffing Requirements 1CAN082201, Request for Relief from American Society of Mechanical Engineers Section XI Volumetric Examination Requirements - Fifth 10-Year Interval, First Period2022-08-24024 August 2022 Request for Relief from American Society of Mechanical Engineers Section XI Volumetric Examination Requirements - Fifth 10-Year Interval, First Period 2CAN072201, Response to Request for Additional Information Requests for Relief from American Society of Mechanical Engineers Section XI Volumetric Examination Requirements - Fourth 10-Year Interval, Second and Third Periods2022-07-20020 July 2022 Response to Request for Additional Information Requests for Relief from American Society of Mechanical Engineers Section XI Volumetric Examination Requirements - Fourth 10-Year Interval, Second and Third Periods 0CAN072201, Registration of Cask Use2022-07-14014 July 2022 Registration of Cask Use 0CAN062202, Registration of Cask Use2022-06-0909 June 2022 Registration of Cask Use 1CAN062201, Response to the Request for Additional Information Proposed Technical Specifications 3.4.12 and 3.4.13 Revised Dose Calculations2022-06-0202 June 2022 Response to the Request for Additional Information Proposed Technical Specifications 3.4.12 and 3.4.13 Revised Dose Calculations 1CAN052201, Request for Relief Related to American Society of Mechanical Engineers (ASME) Code Case N-729-6 Augmented Examination Requirements ANO1-ISI-0352022-05-31031 May 2022 Request for Relief Related to American Society of Mechanical Engineers (ASME) Code Case N-729-6 Augmented Examination Requirements ANO1-ISI-035 2024-01-17
[Table view] |
Text
Entergy Operations, Inc.
1448 S.R. 333 Russellville, AR 72802 Tel 479-858-3110 Richard L. Anderson Site Vice President Arkansas Nuclear One 0CAN111701 November 20, 2017 U.S. Nuclear Regulatory Commission Attn: Document Control Desk Washington, DC 20555
SUBJECT:
Generic Letter 2004-02 Commitment Extension Arkansas Nuclear One - Units 1 and 2 Docket Nos. 50-313 and 50-368 License Nos. DPR-51 and NPF-6
REFERENCES:
- 1. Entergy letter to NRC, Generic Letter 2004-02 Commitment Extension, dated May 31, 2016 (0CAN051606) (ML16152A662)
- 2. Entergy Letter to NRC, GL 2004-02 Closure Extension, dated November 26, 2014 (0CAN111402) (ML14330A638)
- 3. Entergy letter to NRC, GL 2004-02 Closure Option, dated May 16, 2013 (0CAN051301) (ML13137A126)
- 4. NRC Letter to Entergy, Arkansas Nuclear One, Units 1 and 2 -
GL 2004-02 Supplemental Response, dated January 26, 2010 (0CNA011002) (ML100190320)
Dear Sir or Madam:
In accordance with Reference 1, Entergy Operations, Inc. (Entergy) committed to complete bypass re-testing and incorporate results into Arkansas Nuclear One (ANO) calculations related tor Generic Letter (GL) 2004-02 by December 15, 2017. Due to the reasons discussed below, it is necessary to extend this date.
The Pressurized Water Reactor Owners Group (PWROG) has performed a comprehensive in-vessel testing and analysis to provide plant-specific in-vessel fiber limits. The results from the PWROG have been submitted to the NRC as PWROG Topical Report WCAP-17788, Comprehensive Analysis and Test Program for GSI-191 Closure, and are currently under NRC review.
Entergy has completed the large-scale bypass testing for ANO and is currently in the process of incorporating the results into ANO calculations; however, the calculations are being issued with open items pending the results of the final NRC approved version of WCAP-17788. Entergy will incorporate the results from WCAP-17788 into the ANO calculations and update the current licensing basis within six months of NRC approval of WCAP-17788. In addition, ANO will
0CAN111701 Page 2 of 2 complete the insulation replacements, remediation, or model refinements prior to startup from the second refueling outage for each respective unit after NRC approval of WCAP-17788, as necessary. Finally, ANO will submit a final updated supplemental response to support closure of GL 2004-02 within 12 months of NRC approval of WCAP-17788. The NRR Project Manager was informed of this commitment revision on November 14, 2017.
Reference 4 remains valid as supported by References 1, 2, and 3, and the defense-in-depth measures described in Reference 3 continue to remain in place, thus providing a basis for the units safe continued operation in the interim period.
The revised commitments from References 1 and 3 are included in the attachment. Should you have any questions concerning the content of this letter, please contact Stephenie Pyle at 479.858.4704.
I declare under penalty of perjury that the foregoing is true and correct. Executed on November 20, 2017.
Sincerely, ORIGINAL SIGNED BY RICHARD L. ANDERSON RLA/nbm
Attachment:
List of Regulatory Commitments cc: Mr. Kriss Kennedy Regional Administrator U. S. Nuclear Regulatory Commission, Region IV 1600 East Lamar Boulevard Arlington, TX 76011-4511 NRC Senior Resident Inspector Arkansas Nuclear One P.O. Box 310 London, AR 72847 U. S. Nuclear Regulatory Commission Attn: Mr. Thomas Wengert MS O-08B1A One White Flint North 11555 Rockville Pike Rockville, MD 20852
Attachment to 0CAN111701 List of Regulatory Commitments
Attachment to 0CAN111701 Page 1 of 1 List of Regulatory Commitments The following table identifies those actions committed to by Entergy Operations, Inc. (Entergy) in this document. Any other statements in this submittal are provided for information purposes and are not considered to be regulatory commitments.
TYPE SCHEDULED (Check One) COMPLETION COMMITMENT DATE ONE-TIME CONTINUING (If Required)
ACTION COMPLIANCE Entergy will incorporate the results from Within six months of WCAP-17788 into Arkansas Nuclear One X NRC approval of (ANO) calculations and update the current WCAP-17788 licensing basis.
Prior to startup from the second refueling Entergy will complete the insulation outage for each replacements, remediation, or model X respective unit after refinements, as necessary.
NRC approval of WCAP-17788 Entergy will submit a final updated Within twelve supplemental response to support closure months of NRC X
of Generic Letter 2004-02 for ANO-1 and approval of WCAP-ANO-2. 17788