ML17317B130

From kanterella
Jump to navigation Jump to search
Responds to Violation Noted in NRC .Corrective Action:Temporary Sheet Modified to Clarify Instruments for Proper Completion of Form NRC/DOE-742
ML17317B130
Person / Time
Site: Cook  American Electric Power icon.png
Issue date: 03/23/1979
From: Dolan J
AMERICAN ELECTRIC POWER CO., INC.
To: James Keppler
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
Shared Package
ML17317B129 List:
References
AEP:NRC:00157, AEP:NRC:157, NUDOCS 7904280140
Download: ML17317B130 (2)


Text

AMERICAN ELECTRIC POWER Seri'i ce Corporation AEP 2 Broadu'ay. Xeu )'ork..~'. ). 10004 (212j 422 4800 JOHÃ E DOLING i+i Chairman Enyiscrnn JI and Cor~(ration March 23, 1979 AEP:NRC:00157 Donald C. Cook Nuclear Plant Units 1 and 2

Docket Nos.

50-315 and 50-316 License Nos.

DPR-58 and DPR-74 Mr. J.

G. Keppler, Regional Director U.

S. Nuclear Regulatory Commission Office of Inspection and Enforcement Region IZI 799 Roosevelt Road Glen Ellyn, ZL 60137

Dear Mr. Keppler:

This letter responds to Mr. J.

A. Hind' letter dated February 27, 1979 which requested additional information concerning the corrective action taken to preclude recurrence of the deficiency identified in his letter of January 12, 1979.

As stated in our response dated February 7,

1979, a "Temporary Sheet" was written to modify the Donald C.

Cook Nuclear Plant Special Nuclear Materials (SNM) Manual in order to clarify the instructions for the proper completion of Form NRC/DOE-742 so that the errors cited in the Notice of Violation would not recur.

Zn this letter, further details of this modification to the SNM Manual are given as requested.

This modification of the SNM Manual was done in accordance with Technical Specification 6.8.3 and consisted of the permanent addition of a section to Appendix C of the SNM Manual.

Appendix C is entitled "Instructions for the Completion of NRC/ERDA Forms".

This new section clarified two points.

One was that the subschedule attached to line 30 of the Form NRC/DOE-742 should contain the difference between the revised quantity and the previously submitted quantity.

The other was that weight corrections should be reported for the semiannual period during which the revised Form NRC/DOE-741 from the vendor is receivedi and not necessarily for the semiannual period during which the physical transaction occurred.

The SNM Manual, including Temporary Sheets, is available at the Plant for audit.

7 9042801'te

Mr. J.

G. Keppler March 23, 1979 AEP:NRC:00157 We wish to thank you for the clarification in Mr. Hind's letter regarding the status of our previous response with respect to 10 CFR 2.790(d).

We have no objection to the placement of that response in the NRC Public Document Room.

Very truly yours, John E. Dolan Vice Chairman Engineering and Construction JED/emc